The objective of this blog is to supplement the information provided on the PRS website, with more analysis, information, that might be useful for readers. We expect to discuss issues about legislation and policy on some occasions and about the functioning of Parliament at other times. Interesting Parliament trivia will also find their place on the blog from time to time. The Parliament itself puts up significant amount of information on its website, making it relatively easy for anyone tracking the institution to access data. But what we at PRS have tried to do is to add value to the information that we have accessed from Parliament, and make our products even more relevant to users. We hope readers of this blog will share their views with us on a range of issues. We know that a number of people both in India and abroad use our website as a resource on legislation and Parliament. Our somewhat tentative beginning on Twitter (www.twitter.com/prslegislative) is now being followed more widely. Recent updates from Twitter will also be displayed on the Blog. The only way in which our legislation will become better over time is when lots of people like us scrutinise issues in detail, engage with our law makers and ensure that the process takes into account the inputs of citizens from across the country. As we prepare ourselves for the upcoming Budget session of Parliament, we expect to post on our blog quite regularly. We hope you will find this useful in the weeks and months ahead! Please spread the word about this new blog, and thank you for all your continued support.
Recently, the government issued letters de-allocating coal blocks of various companies, based on the recommendations of the Inter Ministerial Group (IMG). This post discusses the history behind the de-allocations, the parameters the IMG used while examining the progress of various coal blocks and the action that has been taken by the government. The Comptroller and Auditor General (CAG) released a performance audit report on 'Allocation of Coal Blocks and Augmentation of Coal Production' on August 17, 2012. Some of the key findings of the Report were:
The IMG on Coal was constituted for the periodic review of the development of coal blocks and end use plants. The IMG had requested a status paper from the Coal Controller, MoC. This has been submitted to the IMG but is not available. The IMG will decide if private allottees have made substantial progress based on certain parameters. The parameters used by IMG are: approval of Mining Plan, status of environment and forest clearance, grant of mining lease and progress made in land acquisition. They are also examining the physical status of End Use Plant (EUP), investment made and the expected date of opening of the mine and commissioning of EUP. The IMG has made the following recommendations:
[table id=1 /]
[table id=5 /]
Of the coal blocks that the IMG has recommended for de-allocation, until now the government has accepted the de-allocation of the following: Bramhadih block, Gourangdih, New Patrapara, Chinora block, Warora (Southern Part) block, Lalgarh (North) block, Bhaskarpara block, Dahegaon/Makardhokra-IV block, Gondkhari block and Ramanwara North block. The government has accepted the deduction of bank guarantees for blocks such as Moitra, Jitpur, Bhaskarpara, Durgapur II/Sariya, Dahegaon/Makardhokra-IV, Marki Mangli II, III and IV, Gondhkari, Lohari, Radhikapur East, Bijahan and Nerad Malegaon. The letters issued by the government de-allocating coal blocks and deducting bank guarantees are available here.
For a detailed summary of the CAG Report, click here.