The Uttarakhand Assembly concluded a two-day session on November 30, 2022. The session was scheduled to be held over five days. In this post we look at the legislative business that was carried out in the Assembly, and the state of state legislatures.
13 Bills were introduced and passed within two days
As per the Session Agenda, a total of 19 Bills were listed for introduction in the span of two days. 13 of these were listed to be discussed and passed on the second day. These included the Uttarakhand Protection of Freedom of Religion (Amendment) Bill, 2022, University of Petroleum and Energy Studies (Amendment), Bill, 2022, and the Uttarakhand Anti-Littering and Anti-Spitting (Amendment) Bill, 2022.
The Assembly had proposed to discuss and pass each Bill (barring two) within five minutes (see Figure 1). Two Bills were allocated 20 minutes each for discussion and passing - the Haridwar Universities Bill, 2022, and the Public Service (Horizontal Reservation for Women) Bill, 2022. As per news reports, the Assembly passed all 13 Bills within these two days (this excludes the Appropriation Bills). This raises the question on the amount of scrutiny that these Bills were subject to, and the quality of such laws when the legislature intends to pass them within mere minutes.
Figure 1: Excerpt of Uttarakhand Assembly's November 2022 Session Agenda
Law making requires deliberation, scrutiny
Our law-making institutions have several tools at their disposal to ensure that before a law is passed, it has been examined thoroughly on various aspects such as constitutionality, clarity, financial and technical capacity of the state to implement provisions, among others. The Ministry/Department piloting a Bill could share a draft of the Bill for public feedback (pre-legislative scrutiny). While Bills get introduced, members may raise issues on constitutionality of the proposed law. Once introduced, Bills could be sent to legislative committees for greater scrutiny. This allows legislators to deliberate upon individual provisions in depth, understand if there may be constitutional challenges or other issues with any provision. This also allows experts and affected stakeholders to weigh in on the provisions, highlight issues, and help strengthen the law.
However, when Bills are introduced and passed within mere minutes, it barely gives legislators the time to go through the provisions and mull over implications, issues, or ways to improve the law for affected parties. It also raises the question of what the intention of the legislature is when passing laws in a hurry without any discussion. Often, such poorly thought laws are also challenged in Courts.
For instance, the Uttarakhand Assembly passed the Uttarakhand Freedom of Religion (Amendment) Bill, 2022 in this session (five minutes had been allocated for the discussion and passing of the Bill). The 2022 Bill amends the 2018 Act which prohibits forceful religious conversions, and provides that conversion through allurement or marriage will be unlawful. The Bill has provisions such as requiring an additional notice to be sent to the District Magistrate (DM) for a conversion, and that reconversion to one’s immediate previous religion will not be considered a conversion. Some of these provisions seem similar to other laws that were passed by states and have been struck down by or have been challenged in Courts. For example, the Madhya Pradesh High Court while examining the Madhya Pradesh Freedom of Religion Act, 2021 noted that providing a notice to the DM for a conversion of religion violates the right to privacy as the right includes the right to remain silent. It extends that understanding to the right to decide on one’s faith. The Himachal Pradesh Freedom of Religion Act, 2006 exempted people who reconvert to their original religion from giving a public notice of such conversion. The Himachal Pradesh High Court had struck down this provision as discriminatory and violative of the right to equality. The Court also noted that the right to change one’s belief cannot be taken away for maintaining public order.
Uttarakhand MLAs may not have had an opportunity to think about how issues flagged by Courts may be addressed in a law that regulates religious conversions.
Most other state Assemblies also pass Bills without adequate scrutiny
In 2021 44% states passed Bills on the day it was introduced or on the next day. Between January 2018 and September 2022, the Gujarat Assembly introduced 92 Bills (excluding Appropriation Bills). 91 of these were passed in the same day as their introduction. In the 2022 Monsoon Session, the Goa Assembly passed 28 Bills in the span of two days. This is in addition to discussion and voting on budgetary allocation to various government departments.
Figure 2: Time taken by state legislatures to pass Bills in 2021
Note: The chart above does not include Arunachal Pradesh and Sikkim. A Bill is considered passed within a day if it was passed on the day of introduction or on the next day. For states with bicameral legislatures, bills have to be passed in both Houses. This has been taken into account in the above chart for five states having Legislative Councils, except Bihar (information was not available for Council).
Sources: Assembly websites, E-Gazette of various states and Right to Information requests; PRS.
Occasionally, the time actually spent deliberating upon a Bill is lesser than the allocated time. This may be due to disruptions in the House. The Himachal Pradesh Assembly provides data on the time actually spent discussing Bills. For example, in the August 2022 Session, it spent an average of 12 minutes to discuss and pass 10 Bills. However, the Uttarakhand Assembly allocated only five minutes to discuss each Bill in its November 2022 Session. This indicates the lack of intent of certain state legislatures to improve their functioning.
In the case of Parliament, a significant portion of scrutiny is also carried out by the Department Related Standing Committees, even when Parliament is not in session. In the 14th Lok Sabha (LS), 60% of the Bills introduced were sent to Committees for detailed examination, and in the 15th LS, 71% were sent. These figures have reduced recently – in the 16th LS 27% of the Bills were sent to Committees, and so far in the 17th LS, 13% have been sent. However, across states, sending Bills to Committees for detailed examination is often the exception than the norm. In 2021, less than 10% of the Bills were sent to Committees. None of the Bills passed by the Uttarakhand Assembly had been examined by a committee. States that are an exception here include Kerala which has 14 subject Committees, and Bills are regularly sent to these for examination. However, these Committees are headed by their respective Ministers, which reduces the scope of independent scrutiny that may be undertaken.
On October 2, 2021, Swachh Bharat Mission (SBM) celebrates its seventh anniversary. It was launched on October 2, 2014 to fulfil the vision of a cleaner India by October 2, 2019. The objective of the Mission was to eliminate open defecation, eradicate manual scavenging, and promote scientific solid waste management. In this blog post, we discuss the sanitation coverage leading up to the launch of the Swachh Bharat Mission and the progress made under this scheme.
Nation-wide sanitation programmes in past
According to the Census, the rural sanitation coverage in India was only 1% in 1981.
The first nationwide programme with a focus on sanitation was the Central Rural Sanitation Programme (CRSP), which was started in 1986 to provide sanitation facilities in rural areas. Later, in 1999, CRSP was restructured and launched as the Total Sanitation Campaign (TSC). While CRSP was a supply-driven infrastructure-oriented programme based on subsidy, TSC was a demand-driven, community-led, project-based programme organised around the district as the unit.
By 2001, only 22% of the rural families had access to toilets. It increased further to 32.7% by 2011. In 2012, TSC was revamped as Nirmal Bharat Abhiyan (NBA) to accelerate the sanitation coverage in rural areas through saturation approach and by enhancing incentives for Individual Household Latrines (IHHL).
In comparison to rural sanitation, fewer programmes were enacted to tackle deficiencies in urban sanitation. In the 1980s, the Integrated Low-Cost Sanitation Scheme provided subsidies for households to build low-cost toilets. Additionally, the National Slum Development Project and its replacement programme, the Valmiki Ambedkar Awas Yojana launched in 2001, were programmes that aimed to construct community toilets for slum populations. In 2008, the National Urban Sanitation Policy (NUSP) was announced to manage human excreta and associated public health and environmental impacts.
On October 2, 2014, the Swachh Bharat Mission was launched with two components: Swachh Bharat Mission (Gramin) and Swachh Bharat Mission (Urban), to focus on rural and urban sanitation, respectively. While the rural component of the Mission is implemented under the Department of Drinking Water and Sanitation, the urban one is implemented by the Ministry of Housing and Urban Affairs. In 2015, the Sub-Group of Chief Ministers on Swachh Bharat Abhiyaan under NITI Aayog had observed that the key difference between SBM and previous programmes was in the efforts to attract more partners to supplement public sector investment towards sanitation.
Swachh Bharat Mission – Gramin (SBM-Gramin)
The Sub-Group of Chief Ministers (2015) had noted that more than half of India’s 25 crore households do not have access to toilets close to places where they live. Notably, during the 2015-19 period, a major portion of expenditure under the Department of Drinking Water and Sanitation was towards SBM-Gramin (see Figure 1).
Figure 1: Expenditure on Swachh Bharat Mission-Gramin during 2014-22
Note: Values for 2020-21 are revised estimates and 2021-22 are budget estimates. Expenditure before 2019-20 were from the erstwhile Ministry of Drinking Water and Sanitation.
Sources: Union Budgets 2014-15 to 2021-22; PRS.
The expenditure towards Swachh Bharat – Gramin saw a steady increase from 2014-15 (Rs 2,841 crore) to 2017-18 (Rs 16,888 crore) and a decrease in the subsequent years. Moreover, during 2015-18, the expenditure of the scheme exceeded the budgeted amount by more than 10%. However, every year since 2018-19, there has been some under-utilisation of the allocated amount.
As per the Department of Drinking Water and Sanitation, 43.8% of the rural households had access to toilets in 2014-15, which increased to 100% in 2019-20 (see Figure 2). However, the 15th Finance Commission (2020) noted that the practice of open defecation is still prevalent, despite access to toilets and highlighted that there is a need to sustain the behavioural change of people for using toilets. The Standing Committee on Rural Development raised a similar concern in 2018, noting that “even a village with 100% household toilets cannot be declared open defecation-free (ODF) till all the inhabitants start using them”. The Standing Committee also raised questions over the construction quality of toilets and observed that the government is counting non-functional toilets, leading to inflated data.
Figure 2: Toilet coverage for rural households
Sources: Dashboard of SBM (Gramin), Ministry of Jal Shakti; PRS.
The 15th Finance Commission also noted that the scheme only provides financial incentives to construct latrines to households below the poverty line (BPL) and selected households above the poverty line. It highlighted that there are considerable exclusion errors in finding BPL households and recommended the universalisation of the scheme to achieve 100% ODF status.
In March 2020, the Department of Drinking Water and Sanitation launched Phase II of SBM-Gramin which will focus on ODF Plus, and will be implemented from 2020-21 to 2024-25 with an outlay of Rs 1.41 lakh crore. ODF Plus includes sustaining the ODF status, and solid and liquid waste management. Specifically, it will ensure that effective solid and liquid waste management is instituted in every Gram Panchayat of the country.
Swachh Bharat Mission – Urban (SBM-Urban)
SBM-Urban aims at making urban India free from open defecation and achieving 100% scientific management of municipal solid waste in 4,000+ towns in the country. One of its targets was the construction of 66 lakh individual household toilets (IHHLs) by October 2, 2019. However, this target was then lowered to 59 lakh IHHLS by 2019. This target was achieved by 2020 (see Table 1).
Table 1: Toilet construction under Swachh Bharat Mission-Urban (as of December 30, 2020)
Targets |
Original Target |
Revised Target |
Actual Constructed |
Individual Household Latrines |
66,42,000 |
58,99,637 |
62,60,606 |
Community and Public Toilets |
5,08,000 |
5,07,587 |
6,15,864 |
Sources: Swachh Bharat Mission Urban - Dashboard; PRS.
Figure 3: Expenditure on Swachh Bharat Mission-Urban during 2014-22 (in Rs crore)
Note: Values for 2020-21 are revised estimates and 2021-22 are budget estimates.
Sources: Union Budget 2014-15 to 2021-22; PRS.
The Standing Committee on Urban Development noted in early 2020 that toilets built under the scheme in areas including East Delhi are of very poor quality, and do not have adequate maintenance. Further, only 1,276 of the 4,320 cities declared to be open defecation free have toilets with water, maintenance, and hygiene. Additionally, it also highlighted in September 2020 that uneven release of funds for solid waste management across states/UTs needs to be corrected to ensure fair implementation of the programme.
The Standing Committee on Urban Development (2021) also expressed concern about the slow pace in achieving targets for source segregation and waste processing. The completion of their targets stood at 78% and 68% respectively of the goal set under SBM-Urban during 2020-21. In addition, other targets related to the door-to-door collection of waste also remained unfulfilled (see Table 2).
Table 2: Waste management under Swachh Bharat Mission-Urban (progress as of December 30, 2020)
Targets |
Target |
Progress |
Progress |
Door to Door Waste Collection (Wards) |
86,284 |
81,535 (96%) |
83,435 (97%) |
Source Segregation (Wards) |
86,284 |
64,730 (75%) |
67,367 (78%) |
Waste Processing (in %) |
100% |
65% |
68% |
Sources: Standing Committee on Urban Development (2021); PRS.
In February 2021, the Finance Minister announced in her budget speech that the Urban Swachh Bharat Mission 2.0 will be launched. Urban Swachh Bharat Mission 2.0 will focus on: (i) sludge management, (ii) waste-water treatment, (iii) source segregation of garbage, (iv) reduction in single-use plastics and (v) control of air pollution caused by construction, demolition, and bio-remediation of dumpsites. On October 1, 2021, the Prime Minister launched SBM-Urban 2.0 with the mission to make all our cities ‘Garbage Free’.