Compulsory voting at elections to local bodies in Gujarat Last week, the Gujarat Local Authorities Laws (Amendment) Act, 2009 received the Governor’s assent.  The Act introduces an ‘obligation to vote’ at the municipal corporation, municipality and Panchayat levels in the state of Gujarat.  To this end, the Act amends three laws related to administration at the local bodies- the Bombay Provincial Municipal Corporation Act, 1949; the Gujarat Municipalities Act, 1963 and; the Gujarat Panchayats Act, 1993. Following the amendments, it shall now be the duty of a qualified voter to cast his vote at elections to each of these bodies.  This includes the right to exercise the NOTA option.  The Act empowers an election officer to serve a voter notice on the grounds that he appears to have failed to vote at the election.  The voter is then required to provide sufficient reasons within a period of one month, failing which he is declared as a “defaulter voter” by an order. The defaulter voter has the option of challenging this order before a designated appellate officer, whose decision will be final. At this stage, it is unclear what the consequences for being a default voter may be, as the penalties for the same are to be prescribed in the Rules.  Typically, any disadvantage or penalty to be suffered by an individual for violating a provision of law is prescribed in the parent act itself, and not left to delegated legislation.  The Act carves out exemptions for certain individuals from voting if (i) he is rendered physically incapable due to illness etc.; (ii) he is not present in the state of Gujarat on the date of election; or (iii) for any other reasons to be laid down in the Rules. The previous Governor had withheld her assent on the Bill for several reasons.  The Governor had stated that compulsory voting violated Article 21 of the Constitution and the principles of individual liberty that permits an individual not to vote.  She had also pointed out that the Bill was silent on the government’s duty to create an enabling environment for the voter to cast his vote.  This included updating of electoral rolls, timely distribution of voter ID cards to all individuals and ensuring easy access to polling stations. Right to vote in India Many democratic governments consider participating in national elections a right of citizenship.  In India, the right to vote is provided by the Constitution and the Representation of People’s Act, 1951, subject to certain disqualifications.  Article 326 of the Constitution guarantees the right to vote to every citizen above the age of 18.  Further, Section 62 of the Representation of Peoples Act (RoPA), 1951 states that every person who is in the electoral roll of that constituency will be entitled to vote.  Thus, the Constitution and the RoPA make it clear that every individual above the age of 18, whose name is in the electoral rolls, and does not attract any of the disqualifications under the Act, may cast his vote.  This is a non discriminatory, voluntary system of voting. In1951, during the discussion on the People’s Representation Bill in Parliament, the idea of including compulsory voting was mooted by a Member.  However, it was rejected by Dr. B.R. Ambedkar on account of practical difficulties.  Over the decades, of the various committees that have discussed electoral reforms, the Dinesh Goswami Committee (1990) briefly examined the issue of compulsory voting.  One of the members of the committee had suggested that the only effective remedy for low voter turn outs was introducing the system of compulsory voting.  This idea was rejected on the grounds that there were practical difficulties involved in its implementation. In July 2004, the Compulsory Voting Bill, 2004 was introduced as a Private Member Bill by Mr. Bachi Singh Rawat, a Member of Parliament in the Lok Sabha.  The Bill proposed to make it compulsory for every eligible voter to vote and provided for exemption only in certain cases, like that of illness etc.  Arguments mooted against the Bill included that of remoteness of polling booths, difficulties faced by certain classes of people like daily wage labourers, nomadic groups, disabled, pregnant women etc. in casting their vote.  The Bill did not receive the support of the House and was not passed. Another Private Member Bill related to Compulsory Voting was introduced by Mr. JP Agarwal, Member of Parliament, in 2009.  Besides making voting mandatory, this Bill also cast the duty upon the state to ensure large number of polling booths at convenient places, and special arrangements for senior citizens, persons with physical disability and pregnant women.  The then Law Minister, Mr. Moily argued that if compulsory voting was introduced, Parliament would reflect, more accurately, the will of the electorate.  However, he also stated that active participation in a democratic set up must be voluntary, and not coerced. Compulsory voting in other countries A number of countries around the world make it mandatory for citizens to vote.  For example, Australia mandates compulsory voting at the national level.  The penalty for violation includes an explanation for not voting and a fine.  It may be noted that the voter turnout in Australia has usually been above 90%, since 1924.  Several countries in South America including Brazil, Argentina and Bolivia also have a provision for compulsory voting.  Certain other countries like The Netherlands in 1970 and Austria more recently, repealed such legal requirements after they had been in force for decades.  Other democracies like the UK, USA, Germany, Italy and France have a system of voluntary voting.  Typically, over the last few elections, Italy has had a voter turnout of over 80%, while the USA has a voter turnout of about 50%. What compulsory voting would mean Those in favour of compulsory voting assert that a high turnout is important for a proper democratic mandate and the functioning of democracy.  They also argue that people who know they will have to vote will take politics more seriously and start to take a more active role.  Further, citizens who live in a democratic state have a duty to vote, which is an essential part of that democracy. However, some others have argued that compulsory voting may be in violation of the fundamental rights of liberty and expression that are guaranteed to citizens in a democratic state.  In this context, it has been stated that every individual should be able to choose whether or not he or she wants to vote.  It is unclear whether the constitutional right to vote may be interpreted to include the right to not vote.  If challenged, it will up to the superior courts to examine whether compulsory voting violates the Constitution. [A version of this post appeared in the Sakal Times on November 16, 2014]

Recently, the central government launched the Pradhan Mantri Sahaj Bijli Har Ghar Yojana (or Saubhagya).[i],[ii]  The scheme seeks to ensure universal household electrification (in both rural and urban areas) by providing last mile connectivity.  The scheme is expected to cover three crore households.  Note that currently about four crore households are un-electrified.  A rural electrification scheme has also been under implementation since 2005.  In light of this, we discuss the current situation of, and key issues related to rural electrification in the country.

Regulatory and policy framework

Under the Electricity Act, 2003, the central and state governments have the joint responsibility of providing electricity to rural areas.  The 2003 Act also mandates that the central government should, in consultation with the state governments, provide for a national policy on (i) stand-alone power systems for rural areas (systems that are not connected to the electricity grid), and (ii) electrification and local distribution in rural areas.  Consequently, the Rural Electrification Policy was notified in August 2006.[iii]

The Rajiv Gandhi Grameen Vidyutikaran Yojana (RGGVY), launched in 2005, was the first scheme on rural electrification.  In December 2014, Ministry of Power launched the Deendayal Upadhyaya Gram Jyoti Yojana (DDUGJY), which subsumed the RGGVY.[iv]  Components of DDUGJY include: (i) separation of agricultural and non-agricultural electricity feeders to improve supply for consumers in rural areas, (ii) improving sub-transmission and distribution infrastructure in rural areas, and (iii) rural electrification by carrying forward targets specified under the RGGVY.

The total financial outlay for DDUGJY over the implementation period (until 2021-22) is Rs 82,300 crore which includes budgetary support of Rs 68,900 crore.  The central government provides 60% of the project cost as grant, the state power distribution companies (discoms) raise 10% of the funds, and 30% is borrowed from financial institutions and banks.

Status of rural electrification

As of August 2017, about 1% of the villages in India remain un-electrified (3,146 villages).  However, with regard to households, around 23% (4.1 crore households) are yet to be electrified.  Table 1 at the end of this post shows the status of rural electrification across all states.

Issues with rural electrification

Definition of an electrified village

An electrified village is defined as one that has the following: (i) provision of basic infrastructure such as distribution transformers and lines in the inhabited locality, (ii) provision of electricity in public places like schools, panchayat office, health centers, dispensaries, and community centers, and (iii) at least 10% of the total number of households in the village are electrified.[iv]

Therefore, a village is considered to be electrified if 10% of the total number of households in the village have been electrified.  This is apart from the basic infrastructure and electrification of certain public centers in the village.  The Standing Committee on Energy (2013) had observed that according to this definition, a village would be called electrified even if up to 90% of households in it do not have an electricity connection.[v]  It also noted that the infrastructure being provided under the scheme is highly inadequate, unreliable and unsustainable.  The Committee recommended that the actual electrification requirement of villages must be assessed, and it should be ensured that the state discoms provide electricity to the remaining households in the village.

Supply of electricity

The Standing Committee had also noted that while the rural electrification scheme looks at creating infrastructure, the actual supply of electricity to households rests with the state discoms.[v]  These discoms are already facing huge financial losses and hence are unable to supply electricity to the villages.  Discoms continue to supply subsidised power to agricultural and residential consumers, resulting in revenue losses.  Further, the average technical and commercial losses (theft and pilferage of electricity) (AT&C losses) are at around 25%.  While the Ujjwal Discom Assurance Yojana (UDAY) has eased off some of the financial losses of the discoms, it remains to be seen whether discoms are able to reduce the cost-tariff gap and AT&C losses in the future.

It has been recommended that generation capacity should be augmented so that states can meet the additional demand under the rural electrification schemes. Further, the assistance to financially weaker states should be increased so that they can better implement the scheme.[v]

Electricity to below poverty line (BPL) households

Under the rural electrification scheme, the cost for providing free electricity connection per BPL household is Rs 3,000.  It has been observed that this cost per household may be inadequate.[v]  Due to the low cost, the quantity and the quality of work has been getting compromised leading to poor implementation of the scheme.  It has been recommended that the Ministry should revisit the cost provided under the scheme.[v]

The new electrification scheme: Pradhan Mantri Sahaj Bijli Har Ghar Yojana (or Saubhagya)

The new scheme, Saubhagya, seeks to ensure universal household electrification, that is, in both rural and urban areas.  Under Saubhagya, beneficiaries will be identified using the Socio Economic and Caste Census (SECC) 2011 data.  The identified poor households will get free electricity connections.  Other households not covered under the SECC, will be provided electricity connections at a cost of Rs 500.  This amount will be collected by the electricity distribution companies in 10 instalments.

The total outlay of the scheme will be Rs 16,320 crore, of which the central government will provide Rs 12,320 crore.  The outlay for the rural households will be Rs 14,025 crore, of which the centre will provide Rs 10,588 crore.  For urban households the outlay will be Rs 2,295 crore of which the centre will provide Rs. 1,733 crore.

The state discoms will execute the electrification works through contractors or other suitable agencies.  Information technology (mobile apps, web portals) will be used to organise camps in villages to identify beneficiaries.  In order to accelerate the process, applications for electricity connections will be completed on the spot.

So far the focus of electrification schemes has been on rural areas, where typically last mile connectivity has been difficult to provide.  Saubhagya extends the ambit of electrification projects to urban areas as well.  While DDUGJY has focused on the village as the principal unit to measure electrification, the new scheme shifts the targets to household electrification.  While the target for ensuring electricity connection in each household will be a significant step towards ensuring 24×7 power, the question of continuous and quality supply to these households will still rest on the ability of the discoms to provide electricity.  Further, while the scheme provides for free connections, the ability of these households to pay for the electricity they consume may be a concern.

Table 1: Status of rural electrification across states (as of August 2017)

Fig 1 edit

* all villages in Telangana were declared electrified before the bifurcation of the state.
Sources:  Ministry of Power; PRS.

 

[i] “PM launches Pradhan Mantri Sahaj Bijli Har Ghar Yojana “Saubhagya””, Press Information Bureau, Ministry of Power, September 25, 2017.

[ii] “FAQs on Pradhan Mantri Sahaj Bijli Har Ghar Yojana “Saubhagya””, Press Information Bureau, Ministry of Power, September 27, 2017.

[iii].  Rural Electrification Policy, Ministry of Power, August 23, 2006, http://powermin.nic.in/sites/default/files/uploads/RE%20Policy_1.pdf.

[iv].  “Office memorandum: Deendayal Upadhyaya Gram Jyoti Yojana”, Ministry of Power, December 3, 2014, http://powermin.nic.in/rural_electrification/pdf/Deendayal_Upadhyaya_Gram_Jyoti_Yojana.pdf.

[v].  “41st Report: Implementation of Rajiv Gandhi Grameen Vidyutikaran Yojana”, Standing Committee on Energy, December 13, 2013, http://164.100.47.134/lsscommittee/Energy/15_Energy_41.pdf.