TRAI released its recommendations on auction of spectrum on April 23, 2012. The recommendations are in pursuance of the Supreme Court order cancelling 122 telecom licences. The cancellation was ordered on grounds of procedural irregularities and arbitrariness in the first-cum-first-serve policy for allocation of spectrum. The recommendations, if adopted by the Department of Telecommunications, would change various aspects of the present telecom policy, including (a) relationship between a telecom licence and spectrum; (b) procedure for allocation of spectrum; (c) pricing of spectrum; (d) limits on spectrum allocation; and (e) use of spectrum. Relationship between telecom licences and spectrum Previously, under the Telecom Policy 1994 (updated in 1999), spectrum was tied in with telecom licences. Since 2003, licence conditions provided for award of two blocks of 6.2 MHz of spectrum for GSM technology and two blocks of 5 MHz for CDMA technology. As per the government’s decision of January 17, 2008 (as explained in TRAI's consultation paper, see page 3 paragraph 7) additional spectrum would be awarded on the basis of increment in the number of subscribers. Service providers had to pay a licence fee (on obtaining the licence), an annual licence fee and a spectrum usage charge determined on the basis of their adjusted gross revenue. TRAI has recommended that telecom licences and spectrum should be de-linked. The service provider would thus pay separately for the value of the licence and the spectrum. With this formulation an entity that does not hold a licence, but is eligible to secure one, may also procure spectrum. This would help in avoiding situations where licence holders have to wait to secure spectrum or offer wire line services in the absence of spectrum. Procedure for allocation of spectrum TRAI has recommended that spectrum be auctioned by means of a simultaneous multiple round ascending auction (SMRA). This means that the service providers would bid for spectrum in different blocks simultaneously. In the first round of auction a reserve price (base price) set by the government is used. Reserve price for auction and payment mechanism A reserve price indicates the minimum amount the bidder must pay to win the object. In case it is too low, it may reduce the gains made by the seller and lead to a sub-optimal sale. If it is too high, it may reduce the number of bidders and the probability of the good not being sold. Various countries have adopted a reserve price of 0.5 times the final price. TRAI has recommended that the reserve price should be 0.8 times the expected winning bid. It has also recommended that telecom companies pay 67% to 75% of the final price in installments over 10 years, depending on the spectrum band. TRAI has reasoned that a higher price would reduce the possibility of further sales upon bidders securing spectrum. However, this may lead to fewer bidders and ultimately fewer service providers. It is argued in news reports that this may increase investments to be made by the service providers and eventually an increase in tariffs. Spectrum blocks and caps TRAI has recommended that the spectrum cap should be determined on the basis of market share. A service provider can now secure a maximum of 50% of spectrum assigned in each band in each service area. However, a service provider cannot hold more than 25% of the total spectrum assigned in all the bands across the country. As per the January 2008 decision, additional spectrum could be awarded to telecom companies when they reached incremental slabs of subscribers. This could extend to two blocks of 1 MHz for GSM technology, and two blocks of 1.25 MHz for CDMA, for each slab of subscribers. TRAI has recommended that spectrum should be auctioned in blocks of 1.25 MHz. Each auction would at least offer 5 MHz of spectrum at a time. Smaller blocks would ensure that service providers who are nearing the spectrum cap may secure spectrum without exceeding the cap. However, experts have argued that 1.25 MHz block may be too limited for launching services. Also, TRAI in the recommendation has noted that a minimum of 5 MHz of contiguous spectrum is required to launch efficient services with new technologies. Use of spectrum TRAI has recommended that the use of spectrum should be liberalised. This implies that spectrum should be technology neutral. Telecom companies would now be free to launch services with any technology of their choice.
On November 28, 2012, the Comptroller and Auditor General submitted its report on the implementation of the Jawaharlal Nehru National Urban Renewal Mission (JNNURM). According to the report most of the projects initiated under JNNURM have not been completed. For instance with respect to urban infrastructure projects, only 231 projects out of the 1298 sanctioned projects have been completed. Similarly, with respect to housing projects, only 22 of the 1517 projects have been completed. Some of the other key recommendations of the report are:
The need and objectives of JNNURM According to the 2011 census India’s urban population has increased from 286 million in 2001 to 377 million in 2011 . With the increase in urban population, there is a requirement to improve the urban infrastructure and improve the service delivery mechanisms. With these specific objectives in mind, the central government launched the Jawaharlal Nehru National Urban Renewal Mission 2005-2006. The aim of the Mission is to encourage reforms and fast track planned development of identified cities (such as cities with a population of more than 1 million as per the 2001 census). JNNURM has two main components namely : (i) Urban Infrastructure and Governance and (ii) Urban Infrastructure Development for Small and Medium Towns. The duration of JNNURM was from 2005-06 to 2011-12. However, as the projects have not been completed the Government has extended its duration until March 2014. Funds for JNNURM The funds for JNNURM are provided through the Additional Central Assistance. This implies that the funds are provided as grants to the states directly from the centre. In the 2012 Union Budget, the central government has allocated Rs 12,522 crore for JNNURM. This represents around 10 % of the total central assistance through the different schemes to states and union territories in 2012-13. As on June 30 2012, 554 projects at a total cost of Rs 62,253 crore have been sanctioned under the Urban Infrastructure and Governance sub-mission of JNNURM. The table below shows the status of the sanctioned JNNURM projects in the different states. State wise status of the projects under JNNURM (as on August 6, 2012)
Name of State | Total Allocation (Rs Lakh) | Number of sanctioned projects | Completed Projects |
Andhra Pradesh | 2,11,845 | 52 | 18 |
Arunachal Pradesh | 10,740 | 3 | NA |
Assam | 27,320 | 2 | NA |
Bihar | 59,241 | 8 | NA |
Chandigarh | 27,087 | 3 | NA |
Chattisgarh | 24,803 | 1 | NA |
Delhi | 2,82,318 | 23 | 4 |
Goa | 12,094 | 2 | NA |
Gujarat | 2,57,881 | 72 | 40 |
Haryana | 32,332 | 4 | NA |
Himachal Pradesh | 13,066 | 5 | NA |
Jammu & Kashmir | 48,836 | 5 | NA |
Jharkhand | 94,120 | 5 | NA |
Karnataka | 1,52,459 | 47 | 22 |
Kerala | 67,476 | 11 | NA |
Madhya Pradesh | 1,32,850 | 23 | 7 |
Maharashtra | 5,50,555 | 80 | 21 |
Manipur | 15,287 | 3 | NA |
Meghalaya | 15,668 | 2 | NA |
Mizoram | 14,822 | 4 | NA |
Nagaland | 11,628 | 3 | NA |
Orissa | 32,235 | 5 | NA |
Punjab | 70,775 | 6 | 1 |
Puducherry | 20,680 | 2 | NA |
Rajasthan | 74,869 | 13 | 2 |
Sikkim | 10,613 | 2 | NA |
Tamil Nadu | 2,25,066 | 48 | 12 |
Tripura | 14,018 | 2 | NA |
Uttar Pradesh | 2,76,941 | 33 | 4 |
Uttarakhand | 40,534 | 14 | NA |
West Bengal | 3,21,840 | 69 | 15 |
Source: Jawaharlal Nehru National Urban Renewal Mission; PRS.