In today's Opinion piece, in the Indian Express, we discuss how enacting hasty new legislation in response to public events may not be the answer.  The recent spot fixing controversy in the Indian Premier League has brought the issue of betting in sports back into the limelight. As a result, public debate around betting, and steps that need to be taken to prevent the recurrence of such events, is gaining traction. The government's response to this incident has been somewhat predictable. The minister of state for sports has reportedly stated that his ministry is committed to putting in place new legislation to deal with the menace of fixing in sports. This approach to law making points towards a growing trend of initiating policy and legislative decisions as a reaction to public events. This is not something new. The Mumbai terror attack in 2008 was the catalyst for the enactment of the National Investigation Agency Act, and the brutal rape and murder of a young girl in Delhi led to the overhaul of India's penal code to ensure stricter penalties for crimes against women. Both these bills were passed without effective scrutiny, as they were not referred to a parliamentary standing committee for examination. Events in the country may, on occasion, highlight gaps in our policy and legislative framework. However, they often point out the ineffectiveness of existing laws and the lack of proper implementation. And that is not always a result of not having enough laws in the country. There are more than a 1,000 Central laws and over 15,000 state laws. The problem lies with our law-making process, which is ad hoc in nature. It is geared towards churning out legislation that is not entirely evidence based and does not take the feedback of different stakeholders into account. In its reports, the National Commission to review the working of the Constitution had observed that "our legislative enactments betray clear marks of hasty drafting and absence of Parliament scrutiny from the point of view of both the implementers and the affected persons and groups". Take, for example, the Gram Nyayalaya Act, which establishes village courts to provide people with easy access to justice and reduce the case law burden on the court system. Structured feedback from villagers, whom this act is trying to empower, prior to introducing the bill in Parliament would have given valuable insights about implementation challenges. A comprehensive study to examine the impact that village courts would have in reducing pendency in the judicial system would have provided hard numbers to substantiate what types of cases should be adjudicated by the village courts. A detailed financial analysis of the cost implications for the Central and the state governments for implementing the law would have helped policymakers decide on the scale and effectiveness of implementation. In the absence of these studies, there is no way to measure whether the law has been effective in giving villagers easy access to justice and in reducing the burden on the judicial system. The importance of stakeholder consultation was recently stressed by the parliamentary committee examining the land acquisition bill. In its report on the bill, the committee recommended that, "before bringing in any bill in future, the government should ensure wider, effective and timely consultations with all relevant and stakeholders so that all related issues are addressed adequately." Rajya Sabha MP N.K. Singh, while testifying before the parliamentary standing committee on the National Food Security Bill, had drawn the attention of the committee towards the need for an accurate financial memorandum accompanying the bill, to "avoid serious consequences in the implementation of the bill." The National Advisory Council has also suggested a process of pre-legislative scrutiny of bills and delegated legislation. In its approach paper, the Financial Sector Legislative Reforms Commission had suggested that delegated legislation should also be published in draft form to elicit feedback and that a cost benefit analysis of the delegated legislation should be appended to the draft. New laws can have a significant impact on the lives of people, so it is important that our law-makers enact "effective laws". For this to happen our law-making process needs to evolve. While there will always be public pressure for new laws, the solution lies in ensuring that the law-making process is robust, consultative and deliberative. The solution to addressing policy opportunities does not always lie in making new laws but in ensuring that whatever law is enacted is well thought out and designed to be effective.  

On November 28, 2012, the Comptroller and Auditor General submitted its report on the implementation of the Jawaharlal Nehru National Urban Renewal Mission (JNNURM).  According to the report most of the projects initiated under JNNURM have not been completed.  For instance with respect to urban infrastructure projects, only 231 projects out of the 1298 sanctioned projects have been completed.  Similarly, with respect to housing projects, only 22 of the 1517 projects have been completed.  Some of the other key recommendations of the report are:

  •  Some of the reasons for the delay in completing the projects include: (i) delay in acquiring land; (ii) deficiency in preparation of projects; and (iii) non-identification of beneficiaries which increased the risk of ineligible beneficiaries getting the benefits.
  •  A total allocation of Rs 66,084 crore had been made by the Planning Commission.  However, against this total allocation, the central government had made an allocation of only Rs 37,070 out of which until March 30, 2011 only Rs 32,934 had been released.
  • There was a delay in releasing these funds to the states.  A large portion of the funds was released only in the last quarter and more particularly in March.
  • The JNNURM guidelines were deficient as they did not provide adequate guidance to the states on the method of parking the funds and utilization of interest.

The need and objectives of JNNURM According to the 2011 census India’s urban population has increased from 286 million in 2001 to 377 million in 2011 .  With the increase in urban population, there is a requirement to improve the urban infrastructure and improve the service delivery mechanisms.  With these specific objectives in mind, the central government launched the Jawaharlal Nehru National Urban Renewal Mission 2005-2006.  The aim of the Mission is to encourage reforms and fast track planned development of identified cities (such as cities with a population of more than 1 million as per the 2001 census).  JNNURM has two main components namely : (i) Urban Infrastructure and Governance  and (ii) Urban Infrastructure Development for Small and Medium Towns. The duration of JNNURM was from 2005-06 to 2011-12. However, as the projects have not been completed the Government has extended its duration until March 2014. Funds for JNNURM The funds for JNNURM are provided through the Additional Central Assistance.  This implies that the funds are provided as grants to the states directly from the centre.   In the 2012 Union Budget, the central government has allocated Rs 12,522 crore for JNNURM. This represents around 10 % of the total central assistance through the different schemes to states and union territories in 2012-13. As on June 30 2012, 554 projects at a total cost of Rs 62,253 crore have been sanctioned under the Urban Infrastructure and Governance sub-mission of JNNURM.   The table below shows the status of the sanctioned JNNURM  projects in the different states. State wise status of the projects under JNNURM                 (as on August 6, 2012)

Name of State Total Allocation (Rs Lakh) Number of sanctioned projects Completed Projects
Andhra Pradesh 2,11,845 52 18
Arunachal Pradesh 10,740 3 NA
Assam 27,320 2 NA
Bihar 59,241 8 NA
Chandigarh 27,087 3 NA
Chattisgarh 24,803 1 NA
Delhi 2,82,318 23 4
Goa 12,094 2 NA
Gujarat 2,57,881 72 40
Haryana 32,332 4 NA
Himachal Pradesh 13,066 5 NA
Jammu & Kashmir 48,836 5 NA
Jharkhand 94,120 5 NA
Karnataka 1,52,459 47 22
Kerala 67,476 11 NA
Madhya Pradesh 1,32,850 23 7
Maharashtra 5,50,555 80 21
Manipur 15,287 3 NA
Meghalaya 15,668 2 NA
Mizoram 14,822 4 NA
Nagaland 11,628 3 NA
Orissa 32,235 5 NA
Punjab 70,775 6 1
Puducherry 20,680 2 NA
Rajasthan 74,869 13 2
Sikkim 10,613 2 NA
Tamil Nadu 2,25,066 48 12
Tripura 14,018 2 NA
Uttar Pradesh 2,76,941 33 4
Uttarakhand 40,534 14 NA
West Bengal 3,21,840 69 15

Source: Jawaharlal Nehru National Urban Renewal Mission; PRS.

  • Gujarat at 55.55% has the highest number of completed projects, while Uttar Pradesh at 12.24% has the lowest number of completed projects.
  • Out of the larger states, Delhi and Maharashtra at 17% and 26% have a comparatively low rate of completed projects.
  • Maharashtra has the highest number of sanctioned projects, while the North Eastern states, Chattisgarh and Puducherry have the lowest number of sanctioned projects.