
The Department of Land Resources in the Ministry of Rural Development has released a draft version of The Land Titling Bill, 2011 on its website. This draft is a major revision of the original draft Bill released in 2010. Public comments on this draft are invited before June 24, 2011. A copy of the draft can be found here. The Bill provides for the registration of all immovable property to establish a system of conclusive, electronically recorded titles. It also provides for a mechanism to invite objections and for the resolution of disputes through special tribunals. The property record will be considered as conclusive ownership by the person mentioned. This will help resolve uncertainties in property transactions. Given that land is a state subject, the Bill is meant to be a model law for adoption by the states individually. The framework of the bill is explained below. I. Land Titling Authority and Preparation of Records The Bill establishes a Land Titling Authority at the State level. The Authority’s task is to prepare a record of all immovable properties in its jurisdiction. These records will contain (a) survey data of boundaries of each property; (b) a unique identification number for each property, which may be linked to a UID number; (c) any record created by an officer of the state or UT government authorised by the laws of that state to make such records; and (d) a record of Title over each property. II. Title Registration Officer and Registration Process The Bill provides for the government to create Title Registration Offices at various places, and for a Title Registration Officer (TRO) to function under the supervision of the Land Titling Authority. The TRO will have powers of a civil court and is charged with the task of creating e a Register of Titles. Steps for the registering of titles include: (a) notification of available land records data by the TRO, (b) invitation to persons with interest in such properties to make objections to the data, and (c) registration of properties by the TRO for which no dispute is brought to his notice in writing. In the case the absoluteness of the title to a property is disputed, the TRO will make an entry into the Register of Titles to that effect and refer the case to the District Land Titling Tribunal (discussed below) III. District Land Titling Tribunal and State Land Titling Appellate Tribunal The Bill proposes to set up a District Land Titling Tribunal, consisting of one or more serving officers not below the rank of Joint Collector / Sub Divisional Magistrate of the District. The government may also establish one or more State Land Titling Appellate Tribunals, to be presided over by serving Judicial Officers in the rank of District Judge. Revisions to the orders of the State Land Titling Appellate Tribunal may be made by a Special Bench of the High Court. The Bill bars civil courts from having jurisdiction to entertain proceedings in respect to matters that the TRO, District Land Titling Tribunal, and State Land Titling Appellate Tribunal are empowered to determine. IV. Completion of Records and Notification When preparation of the Record for whole or part of a specific are is complete, it will be notified. Any person aggrieved by the notified entry in the Register of Titles may file an objection before the District Land Titling Tribunal within three years of the notification. Additionally, the person may file an application with the TRO for an entry to be made in the Register of Titles. The TRO shall do so when the application has been admitted to the Tribunal. Minor errors in the Title of Registers can be rectified through an application to the TRO. V. Register of Titles After completion of records is notified by the Authority, the Register of Titles is prepared and maintained by the Authority. For each property, the Register will include: (a) general description, map, and locational details of the immovable property; (b) descriptive data such as a unique identification number, plot number, total area, built up and vacant area, address, site area, and undivided share in the land; (c) detail of survey entry, provisional title record, conclusive title record and status, mortgage, charges, other rights and interests in the property; (d) details of transfer of the property and past transactions; and (e) disputes pertaining to the property. Entries in the Register of Titles will serve as conclusive evidence of ownership. These entries shall be maintained in electronic form, indemnified, and kept in the public domain.
On November 28, 2012, the Comptroller and Auditor General submitted its report on the implementation of the Jawaharlal Nehru National Urban Renewal Mission (JNNURM). According to the report most of the projects initiated under JNNURM have not been completed. For instance with respect to urban infrastructure projects, only 231 projects out of the 1298 sanctioned projects have been completed. Similarly, with respect to housing projects, only 22 of the 1517 projects have been completed. Some of the other key recommendations of the report are:
The need and objectives of JNNURM According to the 2011 census India’s urban population has increased from 286 million in 2001 to 377 million in 2011 . With the increase in urban population, there is a requirement to improve the urban infrastructure and improve the service delivery mechanisms. With these specific objectives in mind, the central government launched the Jawaharlal Nehru National Urban Renewal Mission 2005-2006. The aim of the Mission is to encourage reforms and fast track planned development of identified cities (such as cities with a population of more than 1 million as per the 2001 census). JNNURM has two main components namely : (i) Urban Infrastructure and Governance and (ii) Urban Infrastructure Development for Small and Medium Towns. The duration of JNNURM was from 2005-06 to 2011-12. However, as the projects have not been completed the Government has extended its duration until March 2014. Funds for JNNURM The funds for JNNURM are provided through the Additional Central Assistance. This implies that the funds are provided as grants to the states directly from the centre. In the 2012 Union Budget, the central government has allocated Rs 12,522 crore for JNNURM. This represents around 10 % of the total central assistance through the different schemes to states and union territories in 2012-13. As on June 30 2012, 554 projects at a total cost of Rs 62,253 crore have been sanctioned under the Urban Infrastructure and Governance sub-mission of JNNURM. The table below shows the status of the sanctioned JNNURM projects in the different states. State wise status of the projects under JNNURM (as on August 6, 2012)
Name of State | Total Allocation (Rs Lakh) | Number of sanctioned projects | Completed Projects |
Andhra Pradesh | 2,11,845 | 52 | 18 |
Arunachal Pradesh | 10,740 | 3 | NA |
Assam | 27,320 | 2 | NA |
Bihar | 59,241 | 8 | NA |
Chandigarh | 27,087 | 3 | NA |
Chattisgarh | 24,803 | 1 | NA |
Delhi | 2,82,318 | 23 | 4 |
Goa | 12,094 | 2 | NA |
Gujarat | 2,57,881 | 72 | 40 |
Haryana | 32,332 | 4 | NA |
Himachal Pradesh | 13,066 | 5 | NA |
Jammu & Kashmir | 48,836 | 5 | NA |
Jharkhand | 94,120 | 5 | NA |
Karnataka | 1,52,459 | 47 | 22 |
Kerala | 67,476 | 11 | NA |
Madhya Pradesh | 1,32,850 | 23 | 7 |
Maharashtra | 5,50,555 | 80 | 21 |
Manipur | 15,287 | 3 | NA |
Meghalaya | 15,668 | 2 | NA |
Mizoram | 14,822 | 4 | NA |
Nagaland | 11,628 | 3 | NA |
Orissa | 32,235 | 5 | NA |
Punjab | 70,775 | 6 | 1 |
Puducherry | 20,680 | 2 | NA |
Rajasthan | 74,869 | 13 | 2 |
Sikkim | 10,613 | 2 | NA |
Tamil Nadu | 2,25,066 | 48 | 12 |
Tripura | 14,018 | 2 | NA |
Uttar Pradesh | 2,76,941 | 33 | 4 |
Uttarakhand | 40,534 | 14 | NA |
West Bengal | 3,21,840 | 69 | 15 |
Source: Jawaharlal Nehru National Urban Renewal Mission; PRS.