The Minister of Railways, Dinesh Trivedi, presented the Railways Budget 2012 to Parliament on 14th March. While commenting on the financial position of Railways, the Minister said that 'the Indian Railways are passing through a difficult phase'. The Operating Ratio for the closing year is now estimated to equal 95%. This is significantly higher than the 91.1% figure budgeted last year. Operating Ratio is a metric that compares operating expenses to revenues. A higher ratio indicates lower ability to generate surplus. Surplus is used for capital investments such as laying of new lines, deploying more coaches etc. Therefore, a smaller surplus affects the Railway’s capability to make such investments. Budget v/s Revised estimates 2011-12 Budget 2011-12 had estimated the performance of Railways for the financial year. Revised estimates have now been submitted. Taken together, these two figures help in comparing actual performance against targets. Some observations are enumerated below:
Budget estimates 2012-13 In 2012-13, Railways plan to improve Operating Ratio to 84.9% and to increase surplus to Rs 15,557 crore. This is more than 10 times the surplus generated in 2011-12 (Revised Estimates). The effective increase in freight rates is estimated to average 23%. During this time, passenger fares are also estimated to increase by an effective average rate of 19%. [1] Infrastructure Performance during the 11th Plan Under the 11th Five Year Plan, the total plan expenditure for Railways had been approved at Rs 2,33,289 crore. The Outcome Budget shows that the actual expenditure is only likely to be Rs 1,92,291 crore. Thus, expenditure will fall short by Rs 40,998 crore. This gaps exists despite a significant increase in the Gross Budgetary Support approved by Parliament. Plan expenditure during 2007-12 (In Rs Crore)
Approved Expenditure |
Actual Expenditure |
|
Gross Budgetary Support |
63,635 |
75,979 |
Internal Resources |
90,000 |
67,763 |
Extra Budgetary Support |
79,654 |
48,549 |
Total |
2,33,289 |
1,92,291 |
The Standing Committee on Railways, in its 11th report presented in August 2011, had sought an explanation from the Ministry. According to the Ministry, lower mobilization of internal resources and lack of extra budgetary support are the main reasons for the shortfall. Internal resource mobilization has been low because of (i) impact of the 6th Pay Commission; and (ii) slow growth in freight earnings due to the economic slowdown. Extra budgetary resources have been low due to non-materialization of funds through the Public-Private Partnership route. Proposals for the 12th Plan Two recent committees – Kakodkar Committee on Railway Safety and the Pitroda Committee on Railway Modernization – have called for large investments in the next five years. The Kakodkar Committee has recommended an investment of Rs 1,00,000 crore in the next five years to improve safety; the Pitroda Committee has recommended an expenditure of Rs 3,96,000 crore in the next five years on modernization. The Railway sub-group of the 12th Five Year Plan has also estimated a requirement of Rs 4,42,744 crore for various other investments proposed to be undertaken during the Plan period. [2] All three groups have called for significant investments in infrastructure augmentation in the next five years. Budget proposals 2012-13 According to the Minister’s speech, the Annual Plan outlay for the year 2012-13 has been set at Rs 60,100 crore. The plan would be financed through:
What happens now? The Budget is likely to be discussed in the two Houses within the next few days. Post the discussion, the Ministry's proposals will be put to vote. Once passed, the Ministry can put its proposals into action. For more details on the Railway Budget, including the projects proposed this year and the status of proposals made last year, please see our analysis here. To understand some of the challenges faced by the Indian Railways, see our blog post from last year. Notes: [1] The ‘effective average fare’ has been calculated by dividing the total income from the segment (freight/ passenger) by the total traffic (in NTKM/ PKM). This would vary with changes in fares as well as the usage by different categories of users (including the proportion of tickets booked through Tatkal). [2] Source: Report of the Expert Group on Railway Modernization (Chairman: Sam Pitroda)
According to news reports, the Supreme Court stayed a Calcutta High Court judgement on the Singur Land Rehabilitation and Development Act, 2011 [Singur Act] on August 24, 2012. The apex court also issued a notice to Tata Motors seeking its response within four weeks, on the West Bengal government's petition challenging the High Court order. In 2008, the Left Front government acquired land in Singur under the Land Acquisition Act, 1894, for Tata Motors to build a Nano car factory. In its first year of coming to power in West Bengal, the Trinamool Congress (TMC) led government notified the Singur Act through which it sought to reclaim this land to return a portion of it to farmers. On June 22, 2012, a Division bench of the Calcutta High Court struck down the Singur Act terming it unconstitutional and void. In its judgment, the Court found some sections of the Singur Act to be in conflict with the central Land Acquisition Act, 1894. As land acquisition is a Concurrent List subject under the Constitution, both Parliament and state legislatures have the power to make laws on it. However, if provisions in the state law conflict with provisions in the central law, then the state law cannot prevail unless it receives Presidential assent. The Calcutta High Court held the Singur Act to be unconstitutional because: (a) it was in conflict with the central Land Acquisition Act, 1894, and (b) Presidential assent was not obtained for the Act to prevail in West Bengal. The central Act mentions that for the government to acquire land, it has to demonstrate: (1) that land is being acquired for a public purpose,[i] and (2) that the government will provide compensation to persons from whom land is being acquired. Provisions in the Singur Act that relate to public purpose and compensation were found to be in conflict with the corresponding provisions in the central Act. The Court was of the opinion that transfer of land to the farmers does not constitute ‘public purpose’ as defined in the central Act. As argued by the Tata Motors’ counsel, return of land to unwilling owners is a ‘private purpose’ or in ‘particular interest of individuals’ rather than in the ‘general interest of the community’. Second, clauses pertaining to compensation to Tata Motors for their investment in the Nano project were found to be vague. The Singur Act only provides for the refund of the amount paid by Tata Motors and the vendors to the state government for leasing the land. It does not provide for the payment of any other amount of money for acquiring the Tata Motors’ land nor the principles for the determination of such an amount. The High Court ordered that these provisions tantamount to ‘no compensation’ and struck down the related provisions. The matter will come up for consideration in the Supreme Court next on October 15, 2012.
[i] According to Section 3 of the Land Acquisition Act, 1894, acquisition of land for ‘public purpose’ includes, among others: provision or planned development of village sites; provision of land for town or rural planning; the provision of land for planned development of land from public funds in pursuance of a scheme or policy of the Government; and the provision of land for a corporation owned or controlled by the State.