The ongoing Monsoon Session of Parliament is being widely viewed as the 'make or break' session for passing legislation before the end of the 15th Lok Sabha in 2014. Hanging in balance are numerous important Bills, which will lapse if not passed before the upcoming 2014 national elections. Data indicates that the current Lok Sabha has passed the least number of Bills in comparison to other comparable Lok Sabhas. The allocated time to be spent on legislation in the Monsoon Session is also below the time recommended for discussion and passing of Bills by the Business Advisory Committee of the Lok Sabha. Eight out of a total of 16 sittings of the Monsoon Session have finished with only 15 percent of the total time spent productively. Success rate of the 15th Lok Sabha in passing legislation India’s first Lok Sabha (1952-1957)  passed a total of 333 Bills in its five year tenure. Since then, every Lok Sabha which has completed over three years of its full term has passed an average of 317 Bills. Where a Lok Sabha has lasted for less than 3 years, it has passed an average of 77 Bills. This includes the 6th, 9th, 11th and 12th Lok Sabhas. The ongoing 15th Lok Sabha, which is in the fifth year of its tenure, has passed only 151 Bills (This includes the two Bills passed in the Monsoon Session as of August 18, 2013). In terms of parliamentary sessions, Lok Sabhas that have lasted over three years have had an average of fifteen sessions. The 15th Lok Sabha has finished thirteen parliamentary sessions with the fourteenth (Monsoon Session) currently underway. Bills Passed by Lok Sabhas Legislative business accomplished in the 15th Lok Sabha For the 15th Lok Sabha, a comparison of the government's legislative agenda at the beginning of a parliamentary session with the actual number of Bills introduced and passed at the end of the session shows that: (i) on average, government has a success rate of getting 39 percent of Bills passed; and (ii) on average, 60 percent success rate in getting Bills introduced. final2.2 final2.3 The Monsoon Session of Parliament was scheduled to have a total of 16 sitting days between August 5-30, 2013. Of the 43 Bills listed for consideration and passage, 32 are Bills pending from previous sessions. As of August 18, 2013, the Rajya Sabha had passed a total of five Bills while the Lok Sabha had passed none. Of the 25 Bills listed for introduction, ten have been introduced so far. The Budget Session of Parliament earlier this year saw the passage of only two Bills, apart from the appropriation Bills,  of the 38 listed for passing. These were the Protection of Women Against Sexual Harassment at Workplace Bill and the Criminal Law (Amendment) Bill. Time allocated for legislation in the Monsoon Session The Lok Sabha is scheduled to meet for six hours and the Rajya Sabha for five hours every day.  Both houses have a question hour and a zero hour at the beginning of the day, which leaves four hours for legislative business in the Lok Sabha and three hours in the Rajya Sabha. However, both Houses can decide to meet for a longer duration. For example, Rajya Sabha has decided to meet till 6:00 PM every day in the Monsoon Session as against the normal working hours of the House until 5:00 PM. The Business Advisory Committee (BAC) of both Houses recommends the time that should be allocated for discussion on each Bill. This session's legislative agenda includes a total of 43 Bills to be passed by Parliament.  So far, 30 of the Bills have been allocated time by the BAC, adding up to a total of 78 hours of discussion before passing. If the Lok Sabha was to discuss and debate the 30 Bills for roughly the same time as was recommended by the BAC, it would need a minimum of 20 working days.  In addition, extra working days would need to be allocated to discuss and debate the remaining 13 Bills. With eight sitting days left and not a single Bill being passed by the Lok Sabha, it is unclear how the Lok Sabha will be able to make up the time to pass Bills with thorough debate.  

Recently, the government issued letters de-allocating coal blocks of various companies, based on the recommendations of the  Inter Ministerial Group (IMG).  This post discusses the history behind the de-allocations, the parameters the IMG used while examining the progress of various coal blocks and the action that has been taken by the government. The Comptroller and Auditor General (CAG) released a performance audit report on 'Allocation of Coal Blocks and Augmentation of Coal Production' on August 17, 2012.  Some of the key findings of the Report were:

  • The government failed to conduct competitive bids for the allocation of coal blocks.  This resulted in a benefit of  Rs 1.86 lakh crore (approx.) to private allottees.  The government could have tapped some of this financial benefit by expediting the decision on competitive bidding for allocation of coal blocks.
  • The implementation schedule of a number of coal blocks has been delayed by one to ten years.  This schedule relates to the time frame within which the Mining Plan for the block has to be approved, various clearances have to be submitted, land acquired, etc.
  • From 2005, the Ministry of Coal (MoC) required the allottees to provide bank guarantees which would be encashed if they failed to meet the above mentioned milestones.  The CAG observed that there was a delay in introducing the bank guarantee and linking it with milestones.

The IMG on Coal was constituted for the periodic review of the development of coal blocks and end use plants.  The IMG had requested a status paper from the Coal Controller, MoC.  This has been submitted to the IMG but is not available.  The IMG will decide if private allottees have made substantial progress based on certain parameters.  The parameters used by IMG are:  approval of Mining Plan, status of environment and forest clearance, grant of mining lease and progress made in land acquisition. They are also examining the physical status of End Use Plant (EUP), investment made and the expected date of opening of the mine and commissioning of EUP. The IMG has made the following recommendations:

  • The coal blocks of companies that have not made substantial progress should be de-allocated.  Additionally, they have recommended the deduction of bank guarantee in the cases where the private companies have not reached the milestones as per the time line decided upon.  As of November 22, 2012, the IMG has recommended the de-allocation of the coal blocks listed in Table 1 and the deduction of bank guarantees for the coal blocks in Table 2.
  • Since, the system of bank guarantee was only introduced in March 2005, not all coal blocks had submitted a bank guarantee.  Where a bank guarantee has not been provided but there is substantial progress in meeting the milestones, the IMG may require the allottee to submit a bank guarantee.

[table id=1 /]

 

[table id=5 /]

 

Of the coal blocks that the IMG has recommended for de-allocation, until now the government has accepted the de-allocation of the following: Bramhadih block, Gourangdih, New Patrapara, Chinora block, Warora (Southern Part) block, Lalgarh (North) block, Bhaskarpara block, Dahegaon/Makardhokra-IV block, Gondkhari block and Ramanwara North block.  The government has accepted the deduction of bank guarantees for blocks such as Moitra, Jitpur, Bhaskarpara, Durgapur II/Sariya, Dahegaon/Makardhokra-IV, Marki Mangli II, III and IV, Gondhkari, Lohari, Radhikapur East, Bijahan and Nerad Malegaon. The letters issued by the government de-allocating coal blocks and deducting bank guarantees are available here.

For a detailed summary of the CAG Report, click here.