The ongoing Monsoon Session of Parliament is being widely viewed as the 'make or break' session for passing legislation before the end of the 15th Lok Sabha in 2014. Hanging in balance are numerous important Bills, which will lapse if not passed before the upcoming 2014 national elections. Data indicates that the current Lok Sabha has passed the least number of Bills in comparison to other comparable Lok Sabhas. The allocated time to be spent on legislation in the Monsoon Session is also below the time recommended for discussion and passing of Bills by the Business Advisory Committee of the Lok Sabha. Eight out of a total of 16 sittings of the Monsoon Session have finished with only 15 percent of the total time spent productively. Success rate of the 15th Lok Sabha in passing legislation India’s first Lok Sabha (1952-1957)  passed a total of 333 Bills in its five year tenure. Since then, every Lok Sabha which has completed over three years of its full term has passed an average of 317 Bills. Where a Lok Sabha has lasted for less than 3 years, it has passed an average of 77 Bills. This includes the 6th, 9th, 11th and 12th Lok Sabhas. The ongoing 15th Lok Sabha, which is in the fifth year of its tenure, has passed only 151 Bills (This includes the two Bills passed in the Monsoon Session as of August 18, 2013). In terms of parliamentary sessions, Lok Sabhas that have lasted over three years have had an average of fifteen sessions. The 15th Lok Sabha has finished thirteen parliamentary sessions with the fourteenth (Monsoon Session) currently underway. Bills Passed by Lok Sabhas Legislative business accomplished in the 15th Lok Sabha For the 15th Lok Sabha, a comparison of the government's legislative agenda at the beginning of a parliamentary session with the actual number of Bills introduced and passed at the end of the session shows that: (i) on average, government has a success rate of getting 39 percent of Bills passed; and (ii) on average, 60 percent success rate in getting Bills introduced. final2.2 final2.3 The Monsoon Session of Parliament was scheduled to have a total of 16 sitting days between August 5-30, 2013. Of the 43 Bills listed for consideration and passage, 32 are Bills pending from previous sessions. As of August 18, 2013, the Rajya Sabha had passed a total of five Bills while the Lok Sabha had passed none. Of the 25 Bills listed for introduction, ten have been introduced so far. The Budget Session of Parliament earlier this year saw the passage of only two Bills, apart from the appropriation Bills,  of the 38 listed for passing. These were the Protection of Women Against Sexual Harassment at Workplace Bill and the Criminal Law (Amendment) Bill. Time allocated for legislation in the Monsoon Session The Lok Sabha is scheduled to meet for six hours and the Rajya Sabha for five hours every day.  Both houses have a question hour and a zero hour at the beginning of the day, which leaves four hours for legislative business in the Lok Sabha and three hours in the Rajya Sabha. However, both Houses can decide to meet for a longer duration. For example, Rajya Sabha has decided to meet till 6:00 PM every day in the Monsoon Session as against the normal working hours of the House until 5:00 PM. The Business Advisory Committee (BAC) of both Houses recommends the time that should be allocated for discussion on each Bill. This session's legislative agenda includes a total of 43 Bills to be passed by Parliament.  So far, 30 of the Bills have been allocated time by the BAC, adding up to a total of 78 hours of discussion before passing. If the Lok Sabha was to discuss and debate the 30 Bills for roughly the same time as was recommended by the BAC, it would need a minimum of 20 working days.  In addition, extra working days would need to be allocated to discuss and debate the remaining 13 Bills. With eight sitting days left and not a single Bill being passed by the Lok Sabha, it is unclear how the Lok Sabha will be able to make up the time to pass Bills with thorough debate.  

On November 28, 2012, the Comptroller and Auditor General submitted its report on the implementation of the Jawaharlal Nehru National Urban Renewal Mission (JNNURM).  According to the report most of the projects initiated under JNNURM have not been completed.  For instance with respect to urban infrastructure projects, only 231 projects out of the 1298 sanctioned projects have been completed.  Similarly, with respect to housing projects, only 22 of the 1517 projects have been completed.  Some of the other key recommendations of the report are:

  •  Some of the reasons for the delay in completing the projects include: (i) delay in acquiring land; (ii) deficiency in preparation of projects; and (iii) non-identification of beneficiaries which increased the risk of ineligible beneficiaries getting the benefits.
  •  A total allocation of Rs 66,084 crore had been made by the Planning Commission.  However, against this total allocation, the central government had made an allocation of only Rs 37,070 out of which until March 30, 2011 only Rs 32,934 had been released.
  • There was a delay in releasing these funds to the states.  A large portion of the funds was released only in the last quarter and more particularly in March.
  • The JNNURM guidelines were deficient as they did not provide adequate guidance to the states on the method of parking the funds and utilization of interest.

The need and objectives of JNNURM According to the 2011 census India’s urban population has increased from 286 million in 2001 to 377 million in 2011 .  With the increase in urban population, there is a requirement to improve the urban infrastructure and improve the service delivery mechanisms.  With these specific objectives in mind, the central government launched the Jawaharlal Nehru National Urban Renewal Mission 2005-2006.  The aim of the Mission is to encourage reforms and fast track planned development of identified cities (such as cities with a population of more than 1 million as per the 2001 census).  JNNURM has two main components namely : (i) Urban Infrastructure and Governance  and (ii) Urban Infrastructure Development for Small and Medium Towns. The duration of JNNURM was from 2005-06 to 2011-12. However, as the projects have not been completed the Government has extended its duration until March 2014. Funds for JNNURM The funds for JNNURM are provided through the Additional Central Assistance.  This implies that the funds are provided as grants to the states directly from the centre.   In the 2012 Union Budget, the central government has allocated Rs 12,522 crore for JNNURM. This represents around 10 % of the total central assistance through the different schemes to states and union territories in 2012-13. As on June 30 2012, 554 projects at a total cost of Rs 62,253 crore have been sanctioned under the Urban Infrastructure and Governance sub-mission of JNNURM.   The table below shows the status of the sanctioned JNNURM  projects in the different states. State wise status of the projects under JNNURM                 (as on August 6, 2012)

Name of State Total Allocation (Rs Lakh) Number of sanctioned projects Completed Projects
Andhra Pradesh 2,11,845 52 18
Arunachal Pradesh 10,740 3 NA
Assam 27,320 2 NA
Bihar 59,241 8 NA
Chandigarh 27,087 3 NA
Chattisgarh 24,803 1 NA
Delhi 2,82,318 23 4
Goa 12,094 2 NA
Gujarat 2,57,881 72 40
Haryana 32,332 4 NA
Himachal Pradesh 13,066 5 NA
Jammu & Kashmir 48,836 5 NA
Jharkhand 94,120 5 NA
Karnataka 1,52,459 47 22
Kerala 67,476 11 NA
Madhya Pradesh 1,32,850 23 7
Maharashtra 5,50,555 80 21
Manipur 15,287 3 NA
Meghalaya 15,668 2 NA
Mizoram 14,822 4 NA
Nagaland 11,628 3 NA
Orissa 32,235 5 NA
Punjab 70,775 6 1
Puducherry 20,680 2 NA
Rajasthan 74,869 13 2
Sikkim 10,613 2 NA
Tamil Nadu 2,25,066 48 12
Tripura 14,018 2 NA
Uttar Pradesh 2,76,941 33 4
Uttarakhand 40,534 14 NA
West Bengal 3,21,840 69 15

Source: Jawaharlal Nehru National Urban Renewal Mission; PRS.

  • Gujarat at 55.55% has the highest number of completed projects, while Uttar Pradesh at 12.24% has the lowest number of completed projects.
  • Out of the larger states, Delhi and Maharashtra at 17% and 26% have a comparatively low rate of completed projects.
  • Maharashtra has the highest number of sanctioned projects, while the North Eastern states, Chattisgarh and Puducherry have the lowest number of sanctioned projects.