The ongoing Monsoon Session of Parliament is being widely viewed as the 'make or break' session for passing legislation before the end of the 15th Lok Sabha in 2014. Hanging in balance are numerous important Bills, which will lapse if not passed before the upcoming 2014 national elections. Data indicates that the current Lok Sabha has passed the least number of Bills in comparison to other comparable Lok Sabhas. The allocated time to be spent on legislation in the Monsoon Session is also below the time recommended for discussion and passing of Bills by the Business Advisory Committee of the Lok Sabha. Eight out of a total of 16 sittings of the Monsoon Session have finished with only 15 percent of the total time spent productively. Success rate of the 15th Lok Sabha in passing legislation India’s first Lok Sabha (1952-1957)  passed a total of 333 Bills in its five year tenure. Since then, every Lok Sabha which has completed over three years of its full term has passed an average of 317 Bills. Where a Lok Sabha has lasted for less than 3 years, it has passed an average of 77 Bills. This includes the 6th, 9th, 11th and 12th Lok Sabhas. The ongoing 15th Lok Sabha, which is in the fifth year of its tenure, has passed only 151 Bills (This includes the two Bills passed in the Monsoon Session as of August 18, 2013). In terms of parliamentary sessions, Lok Sabhas that have lasted over three years have had an average of fifteen sessions. The 15th Lok Sabha has finished thirteen parliamentary sessions with the fourteenth (Monsoon Session) currently underway. Bills Passed by Lok Sabhas Legislative business accomplished in the 15th Lok Sabha For the 15th Lok Sabha, a comparison of the government's legislative agenda at the beginning of a parliamentary session with the actual number of Bills introduced and passed at the end of the session shows that: (i) on average, government has a success rate of getting 39 percent of Bills passed; and (ii) on average, 60 percent success rate in getting Bills introduced. final2.2 final2.3 The Monsoon Session of Parliament was scheduled to have a total of 16 sitting days between August 5-30, 2013. Of the 43 Bills listed for consideration and passage, 32 are Bills pending from previous sessions. As of August 18, 2013, the Rajya Sabha had passed a total of five Bills while the Lok Sabha had passed none. Of the 25 Bills listed for introduction, ten have been introduced so far. The Budget Session of Parliament earlier this year saw the passage of only two Bills, apart from the appropriation Bills,  of the 38 listed for passing. These were the Protection of Women Against Sexual Harassment at Workplace Bill and the Criminal Law (Amendment) Bill. Time allocated for legislation in the Monsoon Session The Lok Sabha is scheduled to meet for six hours and the Rajya Sabha for five hours every day.  Both houses have a question hour and a zero hour at the beginning of the day, which leaves four hours for legislative business in the Lok Sabha and three hours in the Rajya Sabha. However, both Houses can decide to meet for a longer duration. For example, Rajya Sabha has decided to meet till 6:00 PM every day in the Monsoon Session as against the normal working hours of the House until 5:00 PM. The Business Advisory Committee (BAC) of both Houses recommends the time that should be allocated for discussion on each Bill. This session's legislative agenda includes a total of 43 Bills to be passed by Parliament.  So far, 30 of the Bills have been allocated time by the BAC, adding up to a total of 78 hours of discussion before passing. If the Lok Sabha was to discuss and debate the 30 Bills for roughly the same time as was recommended by the BAC, it would need a minimum of 20 working days.  In addition, extra working days would need to be allocated to discuss and debate the remaining 13 Bills. With eight sitting days left and not a single Bill being passed by the Lok Sabha, it is unclear how the Lok Sabha will be able to make up the time to pass Bills with thorough debate.  

Recently, the central government launched the Pradhan Mantri Sahaj Bijli Har Ghar Yojana (or Saubhagya).[i],[ii]  The scheme seeks to ensure universal household electrification (in both rural and urban areas) by providing last mile connectivity.  The scheme is expected to cover three crore households.  Note that currently about four crore households are un-electrified.  A rural electrification scheme has also been under implementation since 2005.  In light of this, we discuss the current situation of, and key issues related to rural electrification in the country.

Regulatory and policy framework

Under the Electricity Act, 2003, the central and state governments have the joint responsibility of providing electricity to rural areas.  The 2003 Act also mandates that the central government should, in consultation with the state governments, provide for a national policy on (i) stand-alone power systems for rural areas (systems that are not connected to the electricity grid), and (ii) electrification and local distribution in rural areas.  Consequently, the Rural Electrification Policy was notified in August 2006.[iii]

The Rajiv Gandhi Grameen Vidyutikaran Yojana (RGGVY), launched in 2005, was the first scheme on rural electrification.  In December 2014, Ministry of Power launched the Deendayal Upadhyaya Gram Jyoti Yojana (DDUGJY), which subsumed the RGGVY.[iv]  Components of DDUGJY include: (i) separation of agricultural and non-agricultural electricity feeders to improve supply for consumers in rural areas, (ii) improving sub-transmission and distribution infrastructure in rural areas, and (iii) rural electrification by carrying forward targets specified under the RGGVY.

The total financial outlay for DDUGJY over the implementation period (until 2021-22) is Rs 82,300 crore which includes budgetary support of Rs 68,900 crore.  The central government provides 60% of the project cost as grant, the state power distribution companies (discoms) raise 10% of the funds, and 30% is borrowed from financial institutions and banks.

Status of rural electrification

As of August 2017, about 1% of the villages in India remain un-electrified (3,146 villages).  However, with regard to households, around 23% (4.1 crore households) are yet to be electrified.  Table 1 at the end of this post shows the status of rural electrification across all states.

Issues with rural electrification

Definition of an electrified village

An electrified village is defined as one that has the following: (i) provision of basic infrastructure such as distribution transformers and lines in the inhabited locality, (ii) provision of electricity in public places like schools, panchayat office, health centers, dispensaries, and community centers, and (iii) at least 10% of the total number of households in the village are electrified.[iv]

Therefore, a village is considered to be electrified if 10% of the total number of households in the village have been electrified.  This is apart from the basic infrastructure and electrification of certain public centers in the village.  The Standing Committee on Energy (2013) had observed that according to this definition, a village would be called electrified even if up to 90% of households in it do not have an electricity connection.[v]  It also noted that the infrastructure being provided under the scheme is highly inadequate, unreliable and unsustainable.  The Committee recommended that the actual electrification requirement of villages must be assessed, and it should be ensured that the state discoms provide electricity to the remaining households in the village.

Supply of electricity

The Standing Committee had also noted that while the rural electrification scheme looks at creating infrastructure, the actual supply of electricity to households rests with the state discoms.[v]  These discoms are already facing huge financial losses and hence are unable to supply electricity to the villages.  Discoms continue to supply subsidised power to agricultural and residential consumers, resulting in revenue losses.  Further, the average technical and commercial losses (theft and pilferage of electricity) (AT&C losses) are at around 25%.  While the Ujjwal Discom Assurance Yojana (UDAY) has eased off some of the financial losses of the discoms, it remains to be seen whether discoms are able to reduce the cost-tariff gap and AT&C losses in the future.

It has been recommended that generation capacity should be augmented so that states can meet the additional demand under the rural electrification schemes. Further, the assistance to financially weaker states should be increased so that they can better implement the scheme.[v]

Electricity to below poverty line (BPL) households

Under the rural electrification scheme, the cost for providing free electricity connection per BPL household is Rs 3,000.  It has been observed that this cost per household may be inadequate.[v]  Due to the low cost, the quantity and the quality of work has been getting compromised leading to poor implementation of the scheme.  It has been recommended that the Ministry should revisit the cost provided under the scheme.[v]

The new electrification scheme: Pradhan Mantri Sahaj Bijli Har Ghar Yojana (or Saubhagya)

The new scheme, Saubhagya, seeks to ensure universal household electrification, that is, in both rural and urban areas.  Under Saubhagya, beneficiaries will be identified using the Socio Economic and Caste Census (SECC) 2011 data.  The identified poor households will get free electricity connections.  Other households not covered under the SECC, will be provided electricity connections at a cost of Rs 500.  This amount will be collected by the electricity distribution companies in 10 instalments.

The total outlay of the scheme will be Rs 16,320 crore, of which the central government will provide Rs 12,320 crore.  The outlay for the rural households will be Rs 14,025 crore, of which the centre will provide Rs 10,588 crore.  For urban households the outlay will be Rs 2,295 crore of which the centre will provide Rs. 1,733 crore.

The state discoms will execute the electrification works through contractors or other suitable agencies.  Information technology (mobile apps, web portals) will be used to organise camps in villages to identify beneficiaries.  In order to accelerate the process, applications for electricity connections will be completed on the spot.

So far the focus of electrification schemes has been on rural areas, where typically last mile connectivity has been difficult to provide.  Saubhagya extends the ambit of electrification projects to urban areas as well.  While DDUGJY has focused on the village as the principal unit to measure electrification, the new scheme shifts the targets to household electrification.  While the target for ensuring electricity connection in each household will be a significant step towards ensuring 24×7 power, the question of continuous and quality supply to these households will still rest on the ability of the discoms to provide electricity.  Further, while the scheme provides for free connections, the ability of these households to pay for the electricity they consume may be a concern.

Table 1: Status of rural electrification across states (as of August 2017)

Fig 1 edit

* all villages in Telangana were declared electrified before the bifurcation of the state.
Sources:  Ministry of Power; PRS.

 

[i] “PM launches Pradhan Mantri Sahaj Bijli Har Ghar Yojana “Saubhagya””, Press Information Bureau, Ministry of Power, September 25, 2017.

[ii] “FAQs on Pradhan Mantri Sahaj Bijli Har Ghar Yojana “Saubhagya””, Press Information Bureau, Ministry of Power, September 27, 2017.

[iii].  Rural Electrification Policy, Ministry of Power, August 23, 2006, http://powermin.nic.in/sites/default/files/uploads/RE%20Policy_1.pdf.

[iv].  “Office memorandum: Deendayal Upadhyaya Gram Jyoti Yojana”, Ministry of Power, December 3, 2014, http://powermin.nic.in/rural_electrification/pdf/Deendayal_Upadhyaya_Gram_Jyoti_Yojana.pdf.

[v].  “41st Report: Implementation of Rajiv Gandhi Grameen Vidyutikaran Yojana”, Standing Committee on Energy, December 13, 2013, http://164.100.47.134/lsscommittee/Energy/15_Energy_41.pdf.