On November 28, 2012, the Comptroller and Auditor General submitted its report on the implementation of the Jawaharlal Nehru National Urban Renewal Mission (JNNURM).  According to the report most of the projects initiated under JNNURM have not been completed.  For instance with respect to urban infrastructure projects, only 231 projects out of the 1298 sanctioned projects have been completed.  Similarly, with respect to housing projects, only 22 of the 1517 projects have been completed.  Some of the other key recommendations of the report are:

  •  Some of the reasons for the delay in completing the projects include: (i) delay in acquiring land; (ii) deficiency in preparation of projects; and (iii) non-identification of beneficiaries which increased the risk of ineligible beneficiaries getting the benefits.
  •  A total allocation of Rs 66,084 crore had been made by the Planning Commission.  However, against this total allocation, the central government had made an allocation of only Rs 37,070 out of which until March 30, 2011 only Rs 32,934 had been released.
  • There was a delay in releasing these funds to the states.  A large portion of the funds was released only in the last quarter and more particularly in March.
  • The JNNURM guidelines were deficient as they did not provide adequate guidance to the states on the method of parking the funds and utilization of interest.

The need and objectives of JNNURM According to the 2011 census India’s urban population has increased from 286 million in 2001 to 377 million in 2011 .  With the increase in urban population, there is a requirement to improve the urban infrastructure and improve the service delivery mechanisms.  With these specific objectives in mind, the central government launched the Jawaharlal Nehru National Urban Renewal Mission 2005-2006.  The aim of the Mission is to encourage reforms and fast track planned development of identified cities (such as cities with a population of more than 1 million as per the 2001 census).  JNNURM has two main components namely : (i) Urban Infrastructure and Governance  and (ii) Urban Infrastructure Development for Small and Medium Towns. The duration of JNNURM was from 2005-06 to 2011-12. However, as the projects have not been completed the Government has extended its duration until March 2014. Funds for JNNURM The funds for JNNURM are provided through the Additional Central Assistance.  This implies that the funds are provided as grants to the states directly from the centre.   In the 2012 Union Budget, the central government has allocated Rs 12,522 crore for JNNURM. This represents around 10 % of the total central assistance through the different schemes to states and union territories in 2012-13. As on June 30 2012, 554 projects at a total cost of Rs 62,253 crore have been sanctioned under the Urban Infrastructure and Governance sub-mission of JNNURM.   The table below shows the status of the sanctioned JNNURM  projects in the different states. State wise status of the projects under JNNURM                 (as on August 6, 2012)

Name of State Total Allocation (Rs Lakh) Number of sanctioned projects Completed Projects
Andhra Pradesh 2,11,845 52 18
Arunachal Pradesh 10,740 3 NA
Assam 27,320 2 NA
Bihar 59,241 8 NA
Chandigarh 27,087 3 NA
Chattisgarh 24,803 1 NA
Delhi 2,82,318 23 4
Goa 12,094 2 NA
Gujarat 2,57,881 72 40
Haryana 32,332 4 NA
Himachal Pradesh 13,066 5 NA
Jammu & Kashmir 48,836 5 NA
Jharkhand 94,120 5 NA
Karnataka 1,52,459 47 22
Kerala 67,476 11 NA
Madhya Pradesh 1,32,850 23 7
Maharashtra 5,50,555 80 21
Manipur 15,287 3 NA
Meghalaya 15,668 2 NA
Mizoram 14,822 4 NA
Nagaland 11,628 3 NA
Orissa 32,235 5 NA
Punjab 70,775 6 1
Puducherry 20,680 2 NA
Rajasthan 74,869 13 2
Sikkim 10,613 2 NA
Tamil Nadu 2,25,066 48 12
Tripura 14,018 2 NA
Uttar Pradesh 2,76,941 33 4
Uttarakhand 40,534 14 NA
West Bengal 3,21,840 69 15

Source: Jawaharlal Nehru National Urban Renewal Mission; PRS.

  • Gujarat at 55.55% has the highest number of completed projects, while Uttar Pradesh at 12.24% has the lowest number of completed projects.
  • Out of the larger states, Delhi and Maharashtra at 17% and 26% have a comparatively low rate of completed projects.
  • Maharashtra has the highest number of sanctioned projects, while the North Eastern states, Chattisgarh and Puducherry have the lowest number of sanctioned projects.

In recent public discourse over lobbying, two issues that have underscored the debate are:

  1. Greater transparency in the policymaking process, and
  2. Equality of access for all stakeholders in engaging with the process.

There is a need to build linkages between citizens and the policy making process, especially by strengthening scrutiny before a Bill is introduced in Parliament. Currently, there is no process established to ensure pre-legislative scrutiny by the citizenry. Other democracies incorporate several measures to enhance public engagement in the pre-legislative process. These include:

  • Making all Bills available in the public domain for a stipulated period before introducing them in the legislature. This includes, publishing these Bills in forms (language, medium etc) that are accessible to the general public.
  • Making a report or Green paper on the legislative priorities addressed by the Bill available for citizens.
  • Forming adhoc committees to scrutinise the Bill before it is piloted in the House.
  • Having Standing Committees examine the Bill before introducing it in the House.
  • Providing a financial memorandum for each Bill, which specifies the budgetary allocation for the process/bodies created by the Bill.
  • Creating online fora for discussion. For the sections of the stakeholders who have limited access to the internet, efforts are made to proactively consult them through other media.
  • Expanding the purview of citizens’ right to petition their representatives with legislative proposals.

There are several instances, in the last few years itself, wherein civil society groups have played an active role in the development of pre-legislative scrutiny in India.

  • Public consultation with cross-section of stakeholders when drafting a Bill: The Right to Information Act is seen as a landmark legislation when highlighting the role of civil society actors in the drafting of a Bill.  It also serves as a prime example for how it the movement mobilised widespread public opinion for the Bill, bringing together different sections of the citizenry.
  • Public feedback on draft Bills: In several cases, after a Bill has been drafted the concerned ministry or public body publishes the Bill, inviting public comments. The Right to Education Bill, the National Identification Authority Bill and the Draft Direct Taxes Code Bill 2009 are recent cases in point. These announcements are made through advertisements published in newspapers and other media. For instance, the government has recently proposed to amend the rules of the RTI and has invited public feedback on the rules by December 27.
  • Engaging with legislators: It is important to expand engagement with lawmakers after the Bill has been introduced in Parliament, as they will determine what the law will finally contain.  This is done by approaching individual legislators or members of the committee which is likely to examine the legislation. Standing Committees invite feedback on the Bill through newspaper advertisements.  For instance, the Standing Committee examining the Civil Nuclear Liability Bill heard testimonies from journalists, civil society groups, thinktanks, public bodies and government departments.

The role of the media and channelising the potential of the internet are other key approaches that need to be explored. Other examples and channels of engagement with the legislative process are illustrated in the PRS Primer on Engaging with Policymakers