On November 28, 2012, the Comptroller and Auditor General submitted its report on the implementation of the Jawaharlal Nehru National Urban Renewal Mission (JNNURM).  According to the report most of the projects initiated under JNNURM have not been completed.  For instance with respect to urban infrastructure projects, only 231 projects out of the 1298 sanctioned projects have been completed.  Similarly, with respect to housing projects, only 22 of the 1517 projects have been completed.  Some of the other key recommendations of the report are:

  •  Some of the reasons for the delay in completing the projects include: (i) delay in acquiring land; (ii) deficiency in preparation of projects; and (iii) non-identification of beneficiaries which increased the risk of ineligible beneficiaries getting the benefits.
  •  A total allocation of Rs 66,084 crore had been made by the Planning Commission.  However, against this total allocation, the central government had made an allocation of only Rs 37,070 out of which until March 30, 2011 only Rs 32,934 had been released.
  • There was a delay in releasing these funds to the states.  A large portion of the funds was released only in the last quarter and more particularly in March.
  • The JNNURM guidelines were deficient as they did not provide adequate guidance to the states on the method of parking the funds and utilization of interest.

The need and objectives of JNNURM According to the 2011 census India’s urban population has increased from 286 million in 2001 to 377 million in 2011 .  With the increase in urban population, there is a requirement to improve the urban infrastructure and improve the service delivery mechanisms.  With these specific objectives in mind, the central government launched the Jawaharlal Nehru National Urban Renewal Mission 2005-2006.  The aim of the Mission is to encourage reforms and fast track planned development of identified cities (such as cities with a population of more than 1 million as per the 2001 census).  JNNURM has two main components namely : (i) Urban Infrastructure and Governance  and (ii) Urban Infrastructure Development for Small and Medium Towns. The duration of JNNURM was from 2005-06 to 2011-12. However, as the projects have not been completed the Government has extended its duration until March 2014. Funds for JNNURM The funds for JNNURM are provided through the Additional Central Assistance.  This implies that the funds are provided as grants to the states directly from the centre.   In the 2012 Union Budget, the central government has allocated Rs 12,522 crore for JNNURM. This represents around 10 % of the total central assistance through the different schemes to states and union territories in 2012-13. As on June 30 2012, 554 projects at a total cost of Rs 62,253 crore have been sanctioned under the Urban Infrastructure and Governance sub-mission of JNNURM.   The table below shows the status of the sanctioned JNNURM  projects in the different states. State wise status of the projects under JNNURM                 (as on August 6, 2012)

Name of State Total Allocation (Rs Lakh) Number of sanctioned projects Completed Projects
Andhra Pradesh 2,11,845 52 18
Arunachal Pradesh 10,740 3 NA
Assam 27,320 2 NA
Bihar 59,241 8 NA
Chandigarh 27,087 3 NA
Chattisgarh 24,803 1 NA
Delhi 2,82,318 23 4
Goa 12,094 2 NA
Gujarat 2,57,881 72 40
Haryana 32,332 4 NA
Himachal Pradesh 13,066 5 NA
Jammu & Kashmir 48,836 5 NA
Jharkhand 94,120 5 NA
Karnataka 1,52,459 47 22
Kerala 67,476 11 NA
Madhya Pradesh 1,32,850 23 7
Maharashtra 5,50,555 80 21
Manipur 15,287 3 NA
Meghalaya 15,668 2 NA
Mizoram 14,822 4 NA
Nagaland 11,628 3 NA
Orissa 32,235 5 NA
Punjab 70,775 6 1
Puducherry 20,680 2 NA
Rajasthan 74,869 13 2
Sikkim 10,613 2 NA
Tamil Nadu 2,25,066 48 12
Tripura 14,018 2 NA
Uttar Pradesh 2,76,941 33 4
Uttarakhand 40,534 14 NA
West Bengal 3,21,840 69 15

Source: Jawaharlal Nehru National Urban Renewal Mission; PRS.

  • Gujarat at 55.55% has the highest number of completed projects, while Uttar Pradesh at 12.24% has the lowest number of completed projects.
  • Out of the larger states, Delhi and Maharashtra at 17% and 26% have a comparatively low rate of completed projects.
  • Maharashtra has the highest number of sanctioned projects, while the North Eastern states, Chattisgarh and Puducherry have the lowest number of sanctioned projects.

The general discussion on the Railway Budget concluded in Parliament this week. During the discussion, several MPs made a reference to two important documents tabled by the Railway Minister in 2009 - the ‘White Paper' on Indian Railways and the 2020 Vision document. The documents provide good insight into the operational and financial performance of Railways over the previous five years. They also throw light on the challenges that confront the Railways today. It emerges that Railways has relied heavily on increasing utilization of existing assets to manage the increase in demand. The system is otherwise severely constrained by lack of adequate capacity. Scenario so far (2004-09) Growth in traffic and earnings Rail transport demand is linked to the growth in GDP. As a result, the two main businesses of Railways – Passenger and Freight – have both seen significant increases in traffic in recent years. Passenger traffic has grown at an average rate of 10% each year. Earnings have increased at a slightly higher pace, implying that most passengers have been spared increases in fare. Standalone, passenger operations have continued to be loss making. Freight traffic has grown too, but at a lower rate of about 7% and unlike the passenger segment, freight fares have increased significantly over these years. Freight forms the backbone of Railways' revenues. Even today, it continues to account for almost two-thirds of total earnings. However, Railways’ market share in freight has decreased steadily over the past few decades - it dropped from 90% in 1950-51 to less than 30% in 2007-08. The main reasons for this decline are high pricing (to subsidize passenger travel) and lack of sufficient infrastructure. Railways are unable to provide time-tabled freight services. In addition, there are no multi-modal logistics parks that could have provided door-to-door cargo services. Infrastructure constraints Since 1950-51, route-kms have increased by just 18% and track-kms by 41%, even though freight and passenger output has gone up almost 12 times. Specific issues include:

  • Common corridor for both freight and passenger traffic - With freight trains on the same corridor, operating fast passenger trains becomes extremely difficult.
  • Concentration of traffic - More than half the total traffic moves on the golden quadrilateral and its diagonals; large parts of these sections are now already saturated.
  • Limited capacity for production of rolling stock, particularly locomotives and EMUs.

The above constraints require investment in network and capacity augmentation, including dedicated freight corridors. Hence, a substantial increase in funding is necessary. The Vision 2020 document planned to deploy Rs 14 lakh crore in the next 10 years towards development of rail infrastructure. Recent trends (as presented in the Budget 2011) This year's budget presented the actual financial performance in 2009-10, the provisional performance in 2010-11 and the targets for 2011-12 (Details can be accessed here). It also highlighted achievements on other metrics, including growth in traffic and augmentation of infrastructure (See 'Status of some key projects proposed in 2010-11'). On financials, 2009-10 was a bad year for Railways. Figures show a high Operating Ratio of 95.3%. Operating Ratio is a metric that compares operating expenses to revenues. A higher ratio indicates lower ability to generate surplus. The 2009-10 Operating Ratio is the highest since 2002. According to the Railways Minister, this can be partly attributed to higher payout in salaries and pension due to implementation of Sixth Pay Commission recommendations. Growth in passenger traffic remained high in 2010-11, at 11%. However, growth in freight traffic slowed down to 2%. Again, passenger fares remained untouched, but freight fares were increased. Railways, in 2011-12, targets an increase of 8% in both passenger and freight traffic. Financials are expected to improve. An amount of Rs. 57,630 crore has been budgeted as net plan outlay for investment in infrastructure. Last year, this figure was Rs 41,426 crore. In her opening remarks during the Budget speech in Parliament, the Minister commented that Railways forms an important backbone of any country. Lets hope it is headed in the right direction!