
On November 28, 2012, the Comptroller and Auditor General submitted its report on the implementation of the Jawaharlal Nehru National Urban Renewal Mission (JNNURM). According to the report most of the projects initiated under JNNURM have not been completed. For instance with respect to urban infrastructure projects, only 231 projects out of the 1298 sanctioned projects have been completed. Similarly, with respect to housing projects, only 22 of the 1517 projects have been completed. Some of the other key recommendations of the report are:
The need and objectives of JNNURM According to the 2011 census India’s urban population has increased from 286 million in 2001 to 377 million in 2011 . With the increase in urban population, there is a requirement to improve the urban infrastructure and improve the service delivery mechanisms. With these specific objectives in mind, the central government launched the Jawaharlal Nehru National Urban Renewal Mission 2005-2006. The aim of the Mission is to encourage reforms and fast track planned development of identified cities (such as cities with a population of more than 1 million as per the 2001 census). JNNURM has two main components namely : (i) Urban Infrastructure and Governance and (ii) Urban Infrastructure Development for Small and Medium Towns. The duration of JNNURM was from 2005-06 to 2011-12. However, as the projects have not been completed the Government has extended its duration until March 2014. Funds for JNNURM The funds for JNNURM are provided through the Additional Central Assistance. This implies that the funds are provided as grants to the states directly from the centre. In the 2012 Union Budget, the central government has allocated Rs 12,522 crore for JNNURM. This represents around 10 % of the total central assistance through the different schemes to states and union territories in 2012-13. As on June 30 2012, 554 projects at a total cost of Rs 62,253 crore have been sanctioned under the Urban Infrastructure and Governance sub-mission of JNNURM. The table below shows the status of the sanctioned JNNURM projects in the different states. State wise status of the projects under JNNURM (as on August 6, 2012)
Name of State | Total Allocation (Rs Lakh) | Number of sanctioned projects | Completed Projects |
Andhra Pradesh | 2,11,845 | 52 | 18 |
Arunachal Pradesh | 10,740 | 3 | NA |
Assam | 27,320 | 2 | NA |
Bihar | 59,241 | 8 | NA |
Chandigarh | 27,087 | 3 | NA |
Chattisgarh | 24,803 | 1 | NA |
Delhi | 2,82,318 | 23 | 4 |
Goa | 12,094 | 2 | NA |
Gujarat | 2,57,881 | 72 | 40 |
Haryana | 32,332 | 4 | NA |
Himachal Pradesh | 13,066 | 5 | NA |
Jammu & Kashmir | 48,836 | 5 | NA |
Jharkhand | 94,120 | 5 | NA |
Karnataka | 1,52,459 | 47 | 22 |
Kerala | 67,476 | 11 | NA |
Madhya Pradesh | 1,32,850 | 23 | 7 |
Maharashtra | 5,50,555 | 80 | 21 |
Manipur | 15,287 | 3 | NA |
Meghalaya | 15,668 | 2 | NA |
Mizoram | 14,822 | 4 | NA |
Nagaland | 11,628 | 3 | NA |
Orissa | 32,235 | 5 | NA |
Punjab | 70,775 | 6 | 1 |
Puducherry | 20,680 | 2 | NA |
Rajasthan | 74,869 | 13 | 2 |
Sikkim | 10,613 | 2 | NA |
Tamil Nadu | 2,25,066 | 48 | 12 |
Tripura | 14,018 | 2 | NA |
Uttar Pradesh | 2,76,941 | 33 | 4 |
Uttarakhand | 40,534 | 14 | NA |
West Bengal | 3,21,840 | 69 | 15 |
Source: Jawaharlal Nehru National Urban Renewal Mission; PRS.
The Lok Pal (anti-corruption body) Bill has generated widespread interest in the past few days.
The Bill is an attempt by the government, under massive pressure due to corruption charges, to gain some of its lost ground. However, civil rights activists, including Anna Hazare, Swami Agnivesh, Kiran Bedi and Arvind Kejriwal, have termed the draft legislation as weak and demanded that fifty per cent of the members in the committee drafting the bill should be from the public.
But the common man appears to be in the dark about the scope of the proposed bill.
Here's an FAQ on the controversial bill.
What is the controversy between the government and Anna Hazare about?
Anna Hazare and other civil society activists have proposed a draft Lok Pal Bill to tackle the menace of corruption. The Prime Minister formed a sub-committee of the Group of Ministers to discuss the issue with these activists. However, these two groups were unable to reach an agreement on the provisions of the Lok Pal Bill. According to the government, the activists demanded that the government should accept the Bill drafted by them without any changes.
What steps has the government taken to enact the Lok Pal Bill?
In January 2011, the government has formed a Group of Ministers chaired by Shri Pranab Mukherjee to suggest measures to tackle corruption, including examination of the proposal of a Lok Pal Bill.
What is the purpose of the office of Lok Pal?
The office of the Lok Pal is the Indian version of the office of an Ombudsman who is appointed to inquire into complaints made by citizens against public officials. The Lok Pal is a forum where the citizen can send a complaint against a public official, which would then be inquired into and the citizen would be provided some redressal.
What are issues that have generated debate on the Lok Pal Bill?
There are diverging views on issues such as the inclusion of the office of the Prime Minister, Ministers and Members of Parliament, inclusion of judges, and powers of the Lok Pal. Some experts contend that all public officials should be accountable while others feel that the autonomy and privilege of Parliament require the Prime Minister, Ministers, and Members of Parliament to be accountable only to Parliament.
Have there been other attempts to establish the institution of Lok Pal at the central level?
Yes. The Lok Pal Bill has been introduced eight times in the Lok Sabha (1968, 1971, 1977, 1985, 1989, 1996, 1998 and 2001). However, each time the Lok Sabha was dissolved before the Bill could be passed, except in 1985 when it was withdrawn.
Have any expert commissions made recommendations on the office of Lok Pal?
Yes, a number of commissions have made various recommendations regarding the necessity of the office of the Lok Pal, its composition, powers and functions, and jurisdiction. The commissions, which dealt with the Lok Pal include the First Administrative Reforms Commission of 1966, the National Commission to Review the Working of the Constitution of 2002 and the Second Administrative Reforms Commission of 2007. The Lok Pal Bills that were introduced were referred to various Parliamentary committees (the last three Bills were referred to the Standing Committee on Home Affairs).
What are the present laws that deal with corruption of public officials in India?
Public servants (such as government employees, judges, armed forces, and Members of Parliament) can be prosecuted for corruption under the Indian Penal Code, 1860 and the Prevention of Corruption Act, 1988. However, the Code of Criminal Procedure and the 1988 Act require the investigating agency (such as the CBI) to get prior sanction of the central or state government before it can initiate the prosecution process in a court.
Have the state governments been more successful in setting up bodies to redress public grievances against administrative acts?
So far 18 state governments have enacted legislation to set up the office of Lokayukta and Uplokayukta (deputy Lokayukta). The 18 states are: Andhra Pradesh, Assam, Bihar, Chhattisgarh, Delhi, Gujarat, Jharkhand, Haryana, Himachal Pradesh, Karnataka, Kerala, Madhya Pradesh, Maharashtra, Orissa, Punjab, Rajasthan, Uttarakhand, and Uttar Pradesh.
Which other countries have the office of the Ombudsman for grievances?
Sweden, Finland, Denmark, the Netherlands, Austria, Portugal, Spain, New Zealand, Burkina Faso and the United Kingdom are some of the countries which have the office of an Ombudsman.
The article was published on rediff.com on April 5, 2011