On November 28, 2012, the Comptroller and Auditor General submitted its report on the implementation of the Jawaharlal Nehru National Urban Renewal Mission (JNNURM). According to the report most of the projects initiated under JNNURM have not been completed. For instance with respect to urban infrastructure projects, only 231 projects out of the 1298 sanctioned projects have been completed. Similarly, with respect to housing projects, only 22 of the 1517 projects have been completed. Some of the other key recommendations of the report are:
The need and objectives of JNNURM According to the 2011 census India’s urban population has increased from 286 million in 2001 to 377 million in 2011 . With the increase in urban population, there is a requirement to improve the urban infrastructure and improve the service delivery mechanisms. With these specific objectives in mind, the central government launched the Jawaharlal Nehru National Urban Renewal Mission 2005-2006. The aim of the Mission is to encourage reforms and fast track planned development of identified cities (such as cities with a population of more than 1 million as per the 2001 census). JNNURM has two main components namely : (i) Urban Infrastructure and Governance and (ii) Urban Infrastructure Development for Small and Medium Towns. The duration of JNNURM was from 2005-06 to 2011-12. However, as the projects have not been completed the Government has extended its duration until March 2014. Funds for JNNURM The funds for JNNURM are provided through the Additional Central Assistance. This implies that the funds are provided as grants to the states directly from the centre. In the 2012 Union Budget, the central government has allocated Rs 12,522 crore for JNNURM. This represents around 10 % of the total central assistance through the different schemes to states and union territories in 2012-13. As on June 30 2012, 554 projects at a total cost of Rs 62,253 crore have been sanctioned under the Urban Infrastructure and Governance sub-mission of JNNURM. The table below shows the status of the sanctioned JNNURM projects in the different states. State wise status of the projects under JNNURM (as on August 6, 2012)
Name of State | Total Allocation (Rs Lakh) | Number of sanctioned projects | Completed Projects |
Andhra Pradesh | 2,11,845 | 52 | 18 |
Arunachal Pradesh | 10,740 | 3 | NA |
Assam | 27,320 | 2 | NA |
Bihar | 59,241 | 8 | NA |
Chandigarh | 27,087 | 3 | NA |
Chattisgarh | 24,803 | 1 | NA |
Delhi | 2,82,318 | 23 | 4 |
Goa | 12,094 | 2 | NA |
Gujarat | 2,57,881 | 72 | 40 |
Haryana | 32,332 | 4 | NA |
Himachal Pradesh | 13,066 | 5 | NA |
Jammu & Kashmir | 48,836 | 5 | NA |
Jharkhand | 94,120 | 5 | NA |
Karnataka | 1,52,459 | 47 | 22 |
Kerala | 67,476 | 11 | NA |
Madhya Pradesh | 1,32,850 | 23 | 7 |
Maharashtra | 5,50,555 | 80 | 21 |
Manipur | 15,287 | 3 | NA |
Meghalaya | 15,668 | 2 | NA |
Mizoram | 14,822 | 4 | NA |
Nagaland | 11,628 | 3 | NA |
Orissa | 32,235 | 5 | NA |
Punjab | 70,775 | 6 | 1 |
Puducherry | 20,680 | 2 | NA |
Rajasthan | 74,869 | 13 | 2 |
Sikkim | 10,613 | 2 | NA |
Tamil Nadu | 2,25,066 | 48 | 12 |
Tripura | 14,018 | 2 | NA |
Uttar Pradesh | 2,76,941 | 33 | 4 |
Uttarakhand | 40,534 | 14 | NA |
West Bengal | 3,21,840 | 69 | 15 |
Source: Jawaharlal Nehru National Urban Renewal Mission; PRS.
Reports suggest that a debt restructuring plan is being prepared for power distribution companies (discoms) in seven states - Uttar Pradesh, Punjab, Rajasthan, Haryana, Andhra Pradesh, Tamil Nadu and Madhya Pradesh. According to some estimates, the combined outstanding debt for discoms is Rs 2 lakh crore. Discoms have been facing heavy losses. According to a Planning Commission Report, the cost of supplying electricity increased at a rate of 7.4 per cent annually between 1998-99 and 2009-10. The average tariff has also increased at an annual rate of 7.1 per cent over the same period. However, the report shows that the average tariff per unit of electricity has consistently been much lower than average cost of supply per unit. Between 2007-08 and 2011-12, the gap between average cost and average tariff per unit of electricity was between 20 and 30 per cent of costs.
Average cost and average tariff per unit of electricity (Rs per kWh)
Year |
Unit cost |
Average tariff per unit |
Gap between cost and tariff |
Gap as percentage of unit cost |
2007-08 |
4.04 |
3.06 |
0.98 |
24% |
2008-09 |
4.6 |
3.26 |
1.34 |
29% |
2009-10 |
4.76 |
3.33 |
1.43 |
30% |
2010-11 |
4.84 |
3.57 |
1.27 |
26% |
2011-12 |
4.87 |
3.8 |
1.07 |
22% |
Source: “Annual Report 2011-12 on the Working of State Power Utilities and Electricity Departments”, Planning Commission State discoms have been losing money due to higher costs than revenues, as well as high transmission and distribution (T&D) losses. The commercial losses for discoms in India (after including subsidies) increased from Rs 16,666 crore in 2007-08 to Rs 37,836 crore in 2011-12. Reports suggest that the restructuring plan being prepared will be worth Rs 1.2 lakh crore in short-term liabilities. Half of the proposed amount would be issued as bonds by the discoms, backed by a state government guarantee. Banks and financial institutions would reschedule the remaining Rs 60,000 crore of debt, with a moratorium of three years on payment of the principal amount. State governments that adopt the financial restructuring plan would not recover any loans given to discoms before they start showing profits. Under a proposed transition finance mechanism, the central government would reimburse 25 per cent of the principal amount of bonds to states that fully implement the plan. Also, states that achieve a reduction in T&D losses above a targeted level in three years may be given grants. Newspaper reports also suggest that states will have to prepare plans for eliminating the gap between the average cost and average tariff per unit of electricity.