The last few months saw a number of allegations of corruption in issues such as contracts for the Commonwealth Games, allocation of 2G Spectrum, and the building of the Adarsh housing society. Professor Kaushik Basu, the Chief Economic Adviser to the Ministry of Finance, has proposed a modification in order to make the anti-corruption law in the country more effective. The Prevention of Corruption Act, 1988 penalizes both bribe giving and taking. Bribe giving is punishable under the Act with imprisonment ranging between six months to five years. He argues that bribe giving should be legalized. Professor Basu distinguishes “harassment bribes”, which he defines as “bribes that people often have to give to get what they are legally entitled to” from the remaining, “Non-Harassment Bribes” which would involve illegal benefits accruing to the bribe giver at a potential cost to the public interest. He argues that legalization of harassment bribes would reduce the nexus between the giver (victim) and the taker of a bribe. Giving complete immunity to the bribe-giver would ensure higher reporting and co-operation of the giver in bringing to justice the bribe taker. The present law acts as a deterrent to reporting of bribery. Courts have also highlighted this issue. The High Court of Delhi in the Bharadwaaj Media Case (2007) observed that a “bribe giver is normally on the mercy of the officials and babus who compel him to pay bribe even for lawful work.” The Court further observed that “Instead of expressing gratefulness to the persons who expose corruption, if the institutions start taking action against those who expose corruption, corruption is bound to progress day and night.” It can be inferred from the judgement that steps ought to be taken to provide protection to those exposing bribery. The proposed legalization of bribe-giving may result in increased reporting of bribery and co-operation of the victim during prosecution. The fear that a bribe giver may report the public official could reduce corruption, at least in terms of harassment bribes. However, this proposal may reduce the stigma attached to bribe-giving and result in corrosion of morality. Much of the recent debate around corruption and the Lok Pal Bill revolve around effective prosecution. This paper looks at the incentive structure for reporting bribe-giving, and merits public debate.
In the recently concluded Monsoon Session of Parliament , the Parliamentary Standing Committee on Rural Development released a report on the implementation of the Mahatma Gandhi National Rural Development Act, 2005 (MGNREGA). This blog provides a brief introduction to the key provisions of MGNREGA , followed by an overview of the major findings and recommendations of the Standing Committee.
I. MGNREGA: A brief introduction
A. Objectives: MGNREGA, which is the largest work guarantee programme in the world, was enacted in 2005 with the primary objective of guaranteeing 100 days of wage employment per year to rural households. Secondly, it aims at addressing causes of chronic poverty through the 'works' (projects) that are undertaken, and thus ensuring sustainable development. Finally, there is an emphasis on strengthening the process of decentralisation through giving a significant role to Panchayati Raj Institutions (PRIs) in planning and implementing these works.
B. Key features:
MGNREGA was implemented in phases, starting from February 2006, and at present it covers all districts of the country with the exception of those that have a 100% urban population. The Act provides a list of works that can be undertaken to generate employment related to water conservation, drought proofing, land development, and flood control and protection works. Table 1 provides information regarding employment generation and expenditure under MGNREGA.
Table 1: MGNREGA: Key indicators
Year |
Number of households provided employment (in crore) |
Average number of person days of work per household |
Total Expenditure (in lakh) |
2006-07 |
2.10 |
43 |
8823.35 |
2007-08 |
3.39 |
42 |
15856.88 |
2008-09 |
4.51 |
48 |
27250.10 |
2009-10 |
5.25 |
54 |
37905.23 |
2010-11 |
5.49 |
47 |
39377.27 |
2011-12* |
4.99 |
43 |
38034.69 |
2012-13** |
4.25 |
36 |
28073.51 |
Source: Standing Committee on Rural Development; PRS. Note: *Provisional ** As on 31.01.2013
II. Findings and Recommendations of the Standing Committee on Rural Development
A. Achievements: The Standing Committee highlighted several achievements of MGNREGA in the seven years of its implementation, especially:
B. Challenges: However, the Committee found several issues with the implementation of the scheme. As Table 1 (above) shows, the average number of days of employment provided to households has been lower than the mandated 100 days, and has been decreasing since 2010-11. Key issues that the Committee raised include
Table 2: Work completion rate
Year |
Work completion rate (%) |
2006-07 |
46.34 |
2007-08 |
45.99 |
2008-09 |
43.76 |
2009-10 |
48.94 |
2010-11 |
50.86 |
2011-12* |
20.25 |
2012-13* |
15.02 |
Total | 33.22 |
Source: Standing Committee on Rural Development. Note: * As on 30.01.2013
C. Recommendations: The Committee made the following recommendations, based on its findings: