Applications for the LAMP Fellowship 2025-26 will open on December 1, 2024. Sign up here to be notified when applications open.

Miscellaneous

RTI rejections

Sachin - November 1, 2011

The Right to Information Act, 2005, contains several exemptions which enable public authorities to deny requests for information. RTI Annual Return Reports for 2005-2010 give detailed information on use of these exemptions to reject RTI requests. Exemptions to requests for information under the Act are primarily embodied in three sections – section 8, section 11, and section 24. Section 8 lists nine specific exemptions ranging from sovereignty of India to trade secrets. Sec 11 provides protection to confidential third party information. Sec 24 exempts certain security and intelligence organizations from the purview of the Act. Of these, sections 8(1)(j), 8(1)(d) and 8(1)(e) are respectively the three most frequently invoked exemptions for the period 2005-2010, cumulatively amounting to almost three-fourths of all exemptions invoked.   orange Section 8(1)(j) provides protection to personal information of individuals from disclosure in the absence of larger public interest. This exemption was invoked over 30,000 times during 2005-2010, which amounts to almost 40% of all invocations of exemptions. Among ministries, the Finance Ministry has invoked this sub-section the most, followed by the Ministry of Communications and Information Technology. Section 8(1)(d) provides protection to trade secrets and intellectual property from disclosure in the absence of larger public interest. This exemption was invoked almost 15,000 times during 2005-2010, which constitutes 18% of all invocations of exemptions. As with sec 8(1)(j), the Finance Ministry has utilized this exemption the most, followed by the Ministry of Petroleum and Natural Gas. Section 8(1)(e) provides protection to information available to a person in his fiduciary relationship from disclosure in the absence of larger public interest. This exemption was invoked 11,639 times during 2005-2010, which accounts for almost 15% of all invocations of exemptions. The Finance Ministry has invoked this exemption more than any other ministry, both overall and for each individual year during 2005-2010. The Finance Ministry accounts for more than 50% of all invocations of this exemption, having invoked it over 6000 times. The Ministry of Petroleum and Natural Gas is second, with a little over 1000 invocations of this exemption. Ministry-wise Rejections As discussed above, Finance Ministry has a large number of rejections, perhaps because of the larger number of requests that it receives.  It is also possible that the Finance Ministry receives a larger number of requests related to private and confidential information (such as Income Tax returns) as well as those which are held in a fiduciary capacity (such as details of accounts in nationalised banks).  Adjusted for the number of requests received, the Finance Ministry tops the rejection rate at 24%, followed by the Prime Minister's Office (12%) and the Ministry of Petroleum and Natural Gas (11%). blue

There has been no resolution so far to the issue of assured fuel supply from Coal India Limited (CIL) to power producers.  According to reports, while CIL released a model supply agreement in April 2012, so far only around 13 Fuel Supply Agreements (FSAs) have been signed.  Originally around 50 power units were expected to sign FSAs with CIL.  Power producers have objected to the model FSA released by CIL, particularly its force majeure provisions and the dilution of financial penalties in case of lower than contracted supply. Background The adverse power supply situation has attracted greater attention in the past few months.  According to Central Electricity Authority's data, the gap between peak demand and peak supply of power in March 2012 was 11 per cent.  The decreasing availability of fuel has emerged as a critical component of the worsening power supply situation.  As of March 31, 2012, there were 32 critical thermal power stations that had a coal stock of less than 7 days.  The gap between demand and supply of coal in the past three years is highlighted below: Table 1: Coal demand/Supply gap (In millions of tonnes)

 

2009-10

2010-11

2011-12

Demand

604

656

696

Supply

514

523

535

Gap

90

133

161

Source: PIB News Release dated May 7, 2012 Coal accounts for around 56 per cent of total installed power generation capacity in India.  Increased capacity in thermal power has also accounted for almost 81 per cent of the additional 62,374 MW added during the 11th Plan period.  Given the importance of coal in meeting national energy needs, the inability of CIL to meet its supply targets has become a major issue.  While the production target for CIL was 486 MT for 2011-12, its actual coal production was 436 MT. Fuel Supply Agreements In March 2012, the government asked CIL to sign FSAs with power plants that have been or would be commissioned by March 31, 2015.  These power plants should also have entered into long term Power Purchase Agreements with distribution companies.  After CIL did not sign FSAs by the deadline of March 31, 2012 the government issued a Presidential Directive to CIL on April 4, 2012 directing it to sign the FSAs.  The CIL board approved a model FSA in April 2012, which has not found acceptance by power producers. According to newspaper reports, many power producers have expressed their dissatisfaction with the model FSA released by CIL.  They have argued that it differs from the 2009 version of FSAs in some major ways.  These include:

  • The penalty for supplying coal below 80 per cent of the contracted amount has been reduced from 10 per cent to 0.01 per cent.  The penalty will be applicable only after three years.
  • The new FSA has extensive force majeure provisions that absolve CIL of non-supply in case of multiple contingencies – including equipment breakdown, power cuts, obstruction in transport, riots, failure to import coal due to “global shortage or delays… or no response to enquiries (by CIL) for supply of coal.”
  • CIL would have the discretion to annually review the supply level that would trigger a financial penalty.  There was no provision for such a review in the earlier FSA.

Most power producers, including NTPC, the country’s biggest power producer, have refused to sign the new FSA.  Reports suggest that the Power Minister has asked the Prime Minister’s Office to mandate CIL to sign FSAs within a month based on the 2009 format.  CIL has received a request from NTPC to consider signing FSAs based on the same parameters as their existing plants, but with the revised trigger point of 80 per cent (down from 90 per cent earlier). Underlying this situation is CIL’s own stagnating production.  Various experts have pointed to the prohibition on private sector participation in coal mining (apart from captive projects) and the backlog in granting environment and forest clearances as having exacerbated the coal supply situation.