Recently the Chairman of Rajya Sabha issued a direction to extend the sitting hours and change the timing of Question Hour in the Upper House. Beginning with the Winter Session, which starts on November 24, Rajya Sabha will meet from 11 am to 6 pm, an hour more than its typical sitting hours. Question Hour will be scheduled from 12 pm to 1 pm, which was earlier held in the first hour of meeting. Members of Parliament (MPs), in addition to their legislative capacity, play an important role to keep the government accountable. One mechanism for them to hold the government responsible for its policies and actions is Question Hour in Parliament. During Question Hour, MPs raise questions to Ministers on various policy matters and decisions. Currently, all MPs can submit up to ten questions for every day that Parliament is in Session. Of these, 250 Questions are picked up by a random ballot to be answered each day that Parliament meets. While 230 Questions are answered in writing by Ministries, 20 Questions are scheduled to be answered orally by Ministers on the floor of the House. When a Question is answered orally by a Minister, MPs are also able to ask him/her two Supplementary Questions as a follow up to the response given. Therefore the proper functioning of Question Hour allows Parliament to be effective in its accountability function. Over the years Question Hour has become a major casualty to disruptions in Parliament. The last decade has seen a decline in the number of questions answered orally on the floor of the House. Rajya Sabha had tried to address this problem in 2011, when Question Hour was shifted to be held from 2 pm to 3 pm, but this was discontinued within a few days. Percentage of Questions Answered Orally The 2014 Budget Session saw both Houses of Parliament work for over hundred percent of their scheduled sitting time. However, while Question Hour functioned for 87% of its scheduled time in Lok Sabha, it functioned for only 40% of its scheduled time in Rajya Sabha. In 13 of the 27 sittings of the 2014 Budget Session, Question Hour in Rajya Sabha was adjourned within a few minutes due to disruptions. It was as a result of these increasing disruptions in the Upper House that the change in timing of the Question Hour and extension of its hours of sitting were proposed. While the Rules of Procedures of Rajya Sabha designate the first hour of sitting for Question Hour, they also allow the Chairman of the House to direct otherwise. It is using this Rule that the Chairman of Rajya Sabha, Mr. Hamid Ansari, issued directions for the Question Hour to be shifted to noon. It now remains to be seen whether this change in timing of Question Hour in the Upper House will be sufficient to allow for its smoother functioning. Sources: M.N. Kaul and S.L. Shakdher, Practice and Procedure of Parliament, Lok Sabha Secretariat, 6th Edition, 2009 Rajya Sabha Rules of Procedure, Rajya Sabha Secretariat, 2010  

In law, the addition or deletion a single punctuation or a single word can have a major impact on the effect of that law.  One such example can be seen from the recommended changes in the Civil Liability for Nuclear Damage Bill, 2010 by Parliament’s Standing Committee. The Civil Liability for Nuclear Damage Bill, 2010 was introduced in the Lok Sabha on May 7, 2010.  The Bill was referred to the Parliamentary Committee on Science and Technology, Environment and Forests, which submitted its report on the Bill yesterday (August 18, 2010).  The Committee has made a number of recommendations regarding certain clauses in the Bill (See summary here).  One of these may have the effect of diluting the provision currently in the Bill.  The main recommendations pertain to:

  • Preventing the entry of private operators.
  • Allowing the government to increase the total liability for a nuclear incident by notification, but not decrease it.
  • Increasing the liability of the operator to Rs 1,500 crore from Rs 500 crore.
  • Increasing the time limit for claiming compensation to 20 years from 10 years.
  • Changing the provision giving operators a right of recourse against persons actually responsible for causing damage.

Clause 17 of the Bill which gives operators a right of recourse against those actually causing damage had been opposed as it was felt that it was not strong enough to hold suppliers liable in case the damage was caused by them.  Clause 17 gave a right of recourse under three conditions.  The exact clause is reproduced below: The operator of a nuclear installation shall have a right of recourse where — (a) such right is expressly provided for in a contract in writing; (b) the nuclear incident has resulted from the wilful act or gross negligence on the part of the supplier of the material, equipment or services, or of his employee; (c) the nuclear incident has resulted from the act of commission or omission of a person done with the intent to cause nuclear damage. Under this clause, a right of recourse exists when (a) there is a contract giving such a right, or (b) the supplier acts deliberately or in a grossly negligent manner to cause nuclear damage, or (c) a person causes nuclear damage with the intent to do so.  If any of the three cases can be proved by the operator, he has a right of recourse. The Committee has stated that “Clause 17(b) gives escape route to the suppliers of nuclear materials, equipments, services of his employees as their willful act or gross negligence would be difficult to establish in a civil nuclear compensation case.” It recommended that Clause 17(b) should be modified to cover consequences “of latent or patent defect, supply of sub-standard material, defective equipment or services or from the gross negligence on the part of the supplier of the material, equipment or service.” The Committee also recommended another change in Clause 17.  It recommended that clause 17(a) may end with “and”. This provision may dilute the right of recourse available to operators.  The modified clause 17 would read as: The operator of a nuclear installation shall have a right of recourse where — (a) such right is expressly provided for in a contract in writing; and, (b) the nuclear incident has resulted as a consequence of latent or patent defect, supply of sub-standard material, defective equipment or services or from the gross negligence on the part of the supplier of the material, equipment or services.; (c) the nuclear incident has resulted from the act of commission or omission of a person done with the intent to cause nuclear damage. This implies that for Clauses 17(b) or (c) to be applicable, the condition specified in clause 17(a) has to be compulsorily satisfied.  Two examples highlight the consequence of the recommended change in Clause 17(a) of the Bill:

  1. A person X deliberately commits sabotage in a nuclear plant and causes damage.  Under the Bill, the operator has recourse under Clause 17(c).  If the recommendation regarding clause 17 is accepted, the operator may also have to also prove the existence of a pre-existing contract with X in addition to clause 17(c).
  2. If a supplier supplies defective equipment, but does not have a contract in writing stating that he will be liable for damage caused by defective equipment, the operator may not have a right of recourse against the supplier under 17(b).

The effect of the changes recommended by the committee may thus dilute the provision as it exists in the Bill.  The table below compares the position in the Bill and the position as per the Standing Committee’s recommendations:

Right of recourse - The Bill gives operators a right to recourse under three conditions:  (a) if there is a clear contract; (b) if the damage is caused by someone with intent to cause damage; (c) against suppliers if damage is caused by their wilful act or negligence. In the Bill the three conditions are separated by a semi-colon.  The Committee recommended that the semi-colon in clause 17(a) should be replaced by “and”. This might imply that all three conditions mentioned need to exist for an operator to have recourse.
Right to recourse against suppliers exists in cases of “willful act or gross negligence on the part of the supplier”. (Clause 17) The Committee felt that the right of recourse against suppliers is vague.  It recommended that recourse against the supplier should be strengthened.  The supplier is liable if an incident has occurred due to (i) defects, or (ii) sub-standard material, or (iii) gross negligence of the supplier of the material, equipment or services. The variance with the Convention continues to exist.