The Lok Sabha adjourns today for a three-week recess. The Rajya Sabha is scheduled to adjourned on March 18. Here’s a brief look at the activity of Parliament this session (data till March 15): Productive Hours: The session has witnessed more than its fair share of disruptions. In the 14 sitting days, over 22 hours has been lost to interruptions in the Lok Sabha and over 26 hours in the Rajya Sabha. The number of productive hours so far is 53 and 50 hours in the Lok Sabha and Rajya Sabha respectively. [Click here to compare with previous sessions.] The session began with protests by the Opposition, putting pressure on the Government to schedule a debate on price rise. After the presentation of the Budget, the protests revolved around the petroleum price hike. The disruptions in the Rajya Sabha were on account of the Women’s Reservation Bill, which resulted in the suspension of seven MPs. On March 9 the Rajya Sabha was adjourned five times, before the passage of the Bill. Legislative business: This session, the government had listed 63 Bills for introduction, 16 pending Bills for consideration and passing and 10 pending Bills for consideration and passing if their Standing Committee reports are submitted. Other than financial business transacted, which includes passage of Demand for Grants and Appropriation Bills, the only legislation that has been passed so far is the Women’s Reservation Bill in the Rajya Sabha. The Lok Sabha also has passed one Bill that replaces an Ordinance - the Ancient Monuments and Archaeological Sites and Remains Bill. In the 14 sitting days, the House has spent 6 hours on legislative business. Question Hour: Another important aspect of parliamentary business is the Question Hour. Interestingly, the Lok Sabha rules were amended before the start of this session to ensure that the absence of MPs does not result in the collapse of Question Hour. However, the amount of time spent on questions in both Houses this session has remained under 5 hours.
On November 28, 2012, the Comptroller and Auditor General submitted its report on the implementation of the Jawaharlal Nehru National Urban Renewal Mission (JNNURM). According to the report most of the projects initiated under JNNURM have not been completed. For instance with respect to urban infrastructure projects, only 231 projects out of the 1298 sanctioned projects have been completed. Similarly, with respect to housing projects, only 22 of the 1517 projects have been completed. Some of the other key recommendations of the report are:
The need and objectives of JNNURM According to the 2011 census India’s urban population has increased from 286 million in 2001 to 377 million in 2011 . With the increase in urban population, there is a requirement to improve the urban infrastructure and improve the service delivery mechanisms. With these specific objectives in mind, the central government launched the Jawaharlal Nehru National Urban Renewal Mission 2005-2006. The aim of the Mission is to encourage reforms and fast track planned development of identified cities (such as cities with a population of more than 1 million as per the 2001 census). JNNURM has two main components namely : (i) Urban Infrastructure and Governance and (ii) Urban Infrastructure Development for Small and Medium Towns. The duration of JNNURM was from 2005-06 to 2011-12. However, as the projects have not been completed the Government has extended its duration until March 2014. Funds for JNNURM The funds for JNNURM are provided through the Additional Central Assistance. This implies that the funds are provided as grants to the states directly from the centre. In the 2012 Union Budget, the central government has allocated Rs 12,522 crore for JNNURM. This represents around 10 % of the total central assistance through the different schemes to states and union territories in 2012-13. As on June 30 2012, 554 projects at a total cost of Rs 62,253 crore have been sanctioned under the Urban Infrastructure and Governance sub-mission of JNNURM. The table below shows the status of the sanctioned JNNURM projects in the different states. State wise status of the projects under JNNURM (as on August 6, 2012)
Name of State | Total Allocation (Rs Lakh) | Number of sanctioned projects | Completed Projects |
Andhra Pradesh | 2,11,845 | 52 | 18 |
Arunachal Pradesh | 10,740 | 3 | NA |
Assam | 27,320 | 2 | NA |
Bihar | 59,241 | 8 | NA |
Chandigarh | 27,087 | 3 | NA |
Chattisgarh | 24,803 | 1 | NA |
Delhi | 2,82,318 | 23 | 4 |
Goa | 12,094 | 2 | NA |
Gujarat | 2,57,881 | 72 | 40 |
Haryana | 32,332 | 4 | NA |
Himachal Pradesh | 13,066 | 5 | NA |
Jammu & Kashmir | 48,836 | 5 | NA |
Jharkhand | 94,120 | 5 | NA |
Karnataka | 1,52,459 | 47 | 22 |
Kerala | 67,476 | 11 | NA |
Madhya Pradesh | 1,32,850 | 23 | 7 |
Maharashtra | 5,50,555 | 80 | 21 |
Manipur | 15,287 | 3 | NA |
Meghalaya | 15,668 | 2 | NA |
Mizoram | 14,822 | 4 | NA |
Nagaland | 11,628 | 3 | NA |
Orissa | 32,235 | 5 | NA |
Punjab | 70,775 | 6 | 1 |
Puducherry | 20,680 | 2 | NA |
Rajasthan | 74,869 | 13 | 2 |
Sikkim | 10,613 | 2 | NA |
Tamil Nadu | 2,25,066 | 48 | 12 |
Tripura | 14,018 | 2 | NA |
Uttar Pradesh | 2,76,941 | 33 | 4 |
Uttarakhand | 40,534 | 14 | NA |
West Bengal | 3,21,840 | 69 | 15 |
Source: Jawaharlal Nehru National Urban Renewal Mission; PRS.