There has been much discussion about bringing the GDP growth on track and the need for expediting infrastructure projects in this regard. At the Planning Commission Meeting to approve the Twelfth Five Year Plan, last month, there were concerns about the implementation of such projects because of the delay in the grant of environment and forest clearances. In this context, there has been talk of setting up a singular body that will grant approvals for large infrastructure projects. News reports suggest that the government is considering forming a National Investment Approval Board (NIAB). The NIAB will be responsible for expediting the clearances for mega project proposals above a certain financial threshold. The Board would be headed by the Prime Minister and will have the authority to provide the ‘final decision’ on investment projects. According to news reports, the NIAB will be the final decision making body. The Ministry of Environment & Forests (MoEF) has raised concerns that this would create ambiguity in the current process of granting clearance for projects. While the formation of the NIAB is still being deliberated and discussed, it would be relevant to understand the process that the MoEF follows before granting clearance to a project and look at data on number of clearances granted and pending. The MoEF has developed certain processes to examine the potential environmental impact of new projects or expansion of existing projects. These are contained in the Environment Impact Assessment Notification, 2006. This notification empowers the Expert Appraisal Committees (EAC) to review the environmental impact of projects. The EAC carries out a combination of these steps depending on the classification of the project:
The MoEF considers the grant of environmental clearance to development projects in terms of the provisions of EIA Notification, 2006. From July 13, 2011 to July 12, 2012 the MoEF has given environmental clearances to 209 development projects. For a sector wise break up see Table 1. Table 1: Number of Environment Clearances Accorded
Sector | No. of projects accorded EC |
Industry (Steel & Cement) |
88 |
Thermal Power |
29 |
River Valley and Hydro-electric |
6 |
Coal Mining |
29 |
Non-Coal Mining |
25 |
National Highways |
32 |
Total |
209 |
Source: “Environmental Clearance accorded from 13.07.2011 to 12.07.2012”, MoEF A total of 593 proposals are pending for environmental clearance as on August 13, 2012.[i] It remains to be seen how the process of granting clearances as established by the MoEF will be reconciled with the expedited process of the NIAB.
[i] MoEF, Lok Sabha, Unstarred Question no. 637, August 13, 2012,
The Finance Minister, Ms. Nirmala Sitharaman, presented the Union Budget for the financial year 2019-20 in Parliament on July 5, 2019. In the 2019-20 budget, the government presented the estimates of its expenditure and receipts for the year 2019-20. The budget also gave an account of how much money the government raised or spent in 2017-18. In addition, the budget also presented the revised estimates made by the government for the year 2018-19 in comparison to the estimates it had given to Parliament in the previous year’s budget.
What are revised estimates?
Some of the estimates made by the government might change during the course of the year. For instance, once the year gets underway, some ministries may need more funds than what was actually allocated to them in the budget, or the receipts expected from certain sources might change. Such deviations from the budget estimates get reflected in the figures released by the government at later stages as part of the subsequent budgets. Once the year ends, the actual numbers are audited by the Comptroller and Auditor General of India (CAG), post which they are presented to Parliament with the upcoming budget, i.e. two years after the estimates are made.
For instance, estimates for the year 2018-19 were presented as part of the 2018-19 budget in February 2018. In the 2019-20 interim budget presented in February 2019 (10 months after the financial year 2018-19 got underway), the government revised these estimates based on the actual receipts and expenditure accounted so far during the year and incorporated estimates for the remaining two months.
The actual receipts and expenditure accounts of the central government are maintained by the Controller General of Accounts (CGA), Ministry of Finance on a monthly basis. In addition to the monthly accounts, the CGA also publishes the provisional unaudited figures for the financial year by the end of the month of May. Once these provisional figures are audited by the CAG, they are presented as actuals in next year’s budget. The CGA reported the figures for 2018-19 on May 31, 2019.[1] The Economic Survey 2018-19 presented on July 4, 2019 uses these figures.[2]
The budget presented on July 5 replicates the revised estimates reported as part of the interim budget (February 1, 2019). Thus, it did not take into account the updated figures for the year 2018-19 from the CGA.
Table 1 gives a comparison of the 2018-19 revised estimates presented by the central government in the budget with the provisional unaudited figures maintained by the CGA for the year 2018-19.[3]
Table 1: Budget at a Glance: Comparison of 2018-19 revised estimates with CGA figures (unaudited) (Rs crore)
Actuals |
Budgeted |
Revised |
Provisional |
Difference |
|
Revenue Expenditure |
18,78,833 |
21,41,772 |
21,40,612 |
20,08,463 |
-1,32,149 |
Capital Expenditure |
2,63,140 |
3,00,441 |
3,16,623 |
3,02,959 |
-13,664 |
Total Expenditure |
21,41,973 |
24,42,213 |
24,57,235 |
23,11,422 |
-1,45,813 |
Revenue Receipts |
14,35,233 |
17,25,738 |
17,29,682 |
15,63,170 |
-1,66,512 |
Capital Receipts |
1,15,678 |
92,199 |
93,155 |
1,02,885 |
9,730 |
of which: |
|
|
|
|
|
Recoveries of Loans |
15,633 |
12,199 |
13,155 |
17,840 |
4,685 |
Other receipts (including disinvestments) |
1,00,045 |
80,000 |
80,000 |
85,045 |
5,045 |
Total Receipts (without borrowings) |
15,50,911 |
18,17,937 |
18,22,837 |
16,66,055 |
-1,56,782 |
Revenue Deficit |
4,43,600 |
4,16,034 |
4,10,930 |
4,45,293 |
34,363 |
% of GDP |
2.6 |
2.2 |
2.2 |
2.4 |
|
Fiscal Deficit |
5,91,062 |
6,24,276 |
6,34,398 |
6,45,367 |
10,969 |
% of GDP |
3.5 |
3.3 |
3.4 |
3.4 |
|
Primary Deficit |
62,110 |
48,481 |
46,828 |
62,692 |
15,864 |
% of GDP |
0.4 |
0.3 |
0.2 |
0.3 |
|
Sources: Budget at a Glance, Union Budget 2019-20; Controller General of Accounts, Ministry of Finance; PRS.
The 2018-19 provisional figures for revenue receipts is Rs 15,63,170 crore, which is Rs 1,66,512 crore less than the revised estimates. This is largely due to Rs 1,67,455 crore shortfall in centre’s net tax revenue between the revised estimates and the provisional estimates (Table 2).
Major taxes which see a shortfall between the gross tax revenue presented in the revised estimates vis-à-vis the provisional figures are income tax (Rs 67,346 crore) and GST (Rs 59,930 crore). Non-tax revenue and disinvestment receipts as per the provisional figures are higher than the revised estimates.
Table 2: Break up of central government receipts: Comparison of 2018-19 RE with CGA figures (unaudited) (Rs crore)
|
Actuals |
Budgeted |
Revised |
Provisional |
Difference |
Gross Tax Revenue |
19,19,009 |
22,71,242 |
22,48,175 |
20,80,203 |
-1,67,972 |
of which: |
|
|
|
|
|
Corporation Tax |
5,71,202 |
6,21,000 |
6,71,000 |
6,63,572 |
-7,428 |
Taxes on Income |
4,30,772 |
5,29,000 |
5,29,000 |
4,61,654 |
-67,346 |
Goods and Services Tax |
4,42,562 |
7,43,900 |
6,43,900 |
5,83,970 |
-59,930 |
Customs |
1,29,030 |
1,12,500 |
1,30,038 |
1,17,930 |
-12,108 |
Union Excise Duties |
2,59,431 |
2,59,600 |
2,59,612 |
2,30,998 |
-28,614 |
A. Centre's Net Tax Revenue |
12,42,488 |
14,80,649 |
14,84,406 |
13,16,951 |
-1,67,455 |
B. Non Tax Revenue |
1,92,745 |
2,45,089 |
2,45,276 |
2,46,219 |
943 |
of which: |
|
|
|
|
|
Interest Receipts |
13,574 |
15,162 |
12,047 |
12,815 |
768 |
Dividend and Profits |
91,361 |
1,07,312 |
1,19,264 |
1,13,424 |
-5,840 |
Other Non-Tax Revenue |
87,810 |
1,22,615 |
1,13,965 |
1,19,980 |
6,015 |
C. Capital Receipts (without borrowings) |
1,15,678 |
92,199 |
93,155 |
1,02,885 |
9,730 |
of which: |
|
|
|
|
|
Disinvestment |
1,00,045 |
80,000 |
80,000 |
85,045 |
5,045 |
Receipts (without borrowings) (A+B+C) |
15,50,911 |
18,17,937 |
18,22,837 |
16,66,055 |
-1,56,782 |
Borrowings |
5,91,062 |
6,24,276 |
6,34,398 |
6,45,367 |
10,969 |
Total Receipts (including borrowings) |
21,41,973 |
24,42,213 |
24,57,235 |
23,11,422 |
-1,45,813 |
Note: Centre’s net tax revenue is gross tax revenue less share of states in central taxes. Figures for GST include receipts from the GST compensation cess. Note that GST was levied for a nine-month period during the year 2017-18, starting July 2017.
Sources: Receipts Budget, Union Budget 2019-20; Controller General of Accounts, Ministry of Finance; PRS.
While the provisional figures show a considerable decrease in receipts (Rs 1,56,782 crore) as compared to the revised estimates, fiscal deficit has not shown a comparable increase. Fiscal deficit is estimated to be Rs 10,969 crore higher than the revised estimates as per the provisional accounts.
On the expenditure side, the total expenditure as per the provisional figures show a decrease of Rs 1,45,813 crore as compared to the revised estimates. Certain Ministries and expenditure items have seen a decrease in expenditure as compared to the revised estimates made by the government. As per the provisional accounts, the expenditure of the Ministry of Agriculture and Farmers’ Welfare and the Ministry of Consumer Affairs, Food and Public Distribution are Rs 22,133 crore and Rs 70,712 crore lower than the revised estimates, respectively. The decrease in the Ministries’ expenditure as a percentage of the revised estimates are 29% and 39%, respectively. The food subsidy according to CGA was Rs 1,01,904 crore, which was Rs 69,394 crore lower than the revised estimates for the year 2018-19 given in the budget documents.
[1] “Accounts of the Union Government of India (Provisional/Unaudited) for the Financial Year 2018-19”, Press Information Bureau, Ministry of Finance, May 31, 2019.
[2] Fiscal Developments, Economic Survey 2018-19, https://www.indiabudget.gov.in/economicsurvey/doc/vol2chapter/echap02_vol2.pdf.
[3] Controller General of Accounts, Ministry of Finance, March 2018-19, http://www.cga.nic.in/MonthlyReport/Published/3/2018-2019.aspx.