All stakeholders, including citizens, NGOs, etc. have an important role in the law making process. But for many stakeholders, the process is not obvious or easily explained. In PRS, we often receive a number of requests from NGOs about how it is that they can get Parliament to make changes in legislation and what would be productive ways in which citizens can make a difference in the law making process. To address this, PRS has developed a short Primer on "Engaging with Policy Makers: Ideas on Contributing to the Law Making Process", in which we have tried to explain the process of how a Bill becomes an Act and some of the opportunities for citizen groups to become part of the process. Sometimes, large parts of a Bill that is introduced in Parliament may not be agreeable to some groups. In such cases there is a tendency among NGOs to sometimes decide to redraft the Bill. To the extent that NGOs think of redrafting a Bill as a tactical negotiating position, they may have a point in trying to redraft legislation. To the extent that NGOs think of such redrafting as a way to keep the discourse alive on the most important issues in any legislation, such efforts are welcome and useful. But if there is a belief that the Bill introduced in Parliiament will be withdrawn to introduce another Bill on the same subject as drafted by NGOs, then history suggests that the probability of that happening is close to zero. This is not a comment on the quality of the Bill that may be drafted by the group of NGOs, but rather a result of a complex set of issues about lawmaking in India. Despite the odds, there are some recent examples in which NGOs were able to bring about significant changes to Bills in Parliament. The Right to Information Act stands out as one of the best examples in recent times. On the recently passed Right to Education Bill, NGOs were able to exert sufficient pressure to bring about changes in the Bill, and also get the government to bring in an amendment Bill to make further changes. In the Seeds Bill which was introduced in 2004, the Government appears to have agreed to bring about important changes thanks to the efforts of a number of farmer groups approaching the government directly, and through their local MPs and political parties. It would be useful if we can get more examples/ comments/ suggestions about how some NGOs were able to bring about these changes in Bills. This will help more people understand how their voices can be heard in the corridors of power.

Recently, the government issued letters de-allocating coal blocks of various companies, based on the recommendations of the  Inter Ministerial Group (IMG).  This post discusses the history behind the de-allocations, the parameters the IMG used while examining the progress of various coal blocks and the action that has been taken by the government. The Comptroller and Auditor General (CAG) released a performance audit report on 'Allocation of Coal Blocks and Augmentation of Coal Production' on August 17, 2012.  Some of the key findings of the Report were:

  • The government failed to conduct competitive bids for the allocation of coal blocks.  This resulted in a benefit of  Rs 1.86 lakh crore (approx.) to private allottees.  The government could have tapped some of this financial benefit by expediting the decision on competitive bidding for allocation of coal blocks.
  • The implementation schedule of a number of coal blocks has been delayed by one to ten years.  This schedule relates to the time frame within which the Mining Plan for the block has to be approved, various clearances have to be submitted, land acquired, etc.
  • From 2005, the Ministry of Coal (MoC) required the allottees to provide bank guarantees which would be encashed if they failed to meet the above mentioned milestones.  The CAG observed that there was a delay in introducing the bank guarantee and linking it with milestones.

The IMG on Coal was constituted for the periodic review of the development of coal blocks and end use plants.  The IMG had requested a status paper from the Coal Controller, MoC.  This has been submitted to the IMG but is not available.  The IMG will decide if private allottees have made substantial progress based on certain parameters.  The parameters used by IMG are:  approval of Mining Plan, status of environment and forest clearance, grant of mining lease and progress made in land acquisition. They are also examining the physical status of End Use Plant (EUP), investment made and the expected date of opening of the mine and commissioning of EUP. The IMG has made the following recommendations:

  • The coal blocks of companies that have not made substantial progress should be de-allocated.  Additionally, they have recommended the deduction of bank guarantee in the cases where the private companies have not reached the milestones as per the time line decided upon.  As of November 22, 2012, the IMG has recommended the de-allocation of the coal blocks listed in Table 1 and the deduction of bank guarantees for the coal blocks in Table 2.
  • Since, the system of bank guarantee was only introduced in March 2005, not all coal blocks had submitted a bank guarantee.  Where a bank guarantee has not been provided but there is substantial progress in meeting the milestones, the IMG may require the allottee to submit a bank guarantee.

[table id=1 /]

 

[table id=5 /]

 

Of the coal blocks that the IMG has recommended for de-allocation, until now the government has accepted the de-allocation of the following: Bramhadih block, Gourangdih, New Patrapara, Chinora block, Warora (Southern Part) block, Lalgarh (North) block, Bhaskarpara block, Dahegaon/Makardhokra-IV block, Gondkhari block and Ramanwara North block.  The government has accepted the deduction of bank guarantees for blocks such as Moitra, Jitpur, Bhaskarpara, Durgapur II/Sariya, Dahegaon/Makardhokra-IV, Marki Mangli II, III and IV, Gondhkari, Lohari, Radhikapur East, Bijahan and Nerad Malegaon. The letters issued by the government de-allocating coal blocks and deducting bank guarantees are available here.

For a detailed summary of the CAG Report, click here.