In recent news reports there have been deliberations on whether there is a possibility of appealing a central government decision on forest clearances.  In this context, the National Green Tribunal (NGT) has directed states to comply with the statutory requirement of passing an order notifying diversion of forest land for non-forest purposes.  It has also held that it can hear appeals from the orders of state governments and other authorities on forest clearances. The NGT was established in 2010 to deal with cases relating to environmental protection, and conservation of forests and other natural resources.  The need was felt to have a mechanism to hear appeals filed by aggrieved citizens against government orders on forest clearances.  For instance, the NGT can hear appeals against an order of the appellate authority, state government or pollution control board under the Water (Prevention and Control of Pollution) Act, 1974. How is a forest clearance obtained? Obtaining a forest clearance is a key step in the process of setting up a project.  Recently the Chhatrasal coal mine allotted to Reliance Power's 4,000 MW Sasan thermal power project in Madhya Pradesh has received forest clearance.  The Ministry of Environment and Forests (MoEF) first gives ‘in-principle’ approval to divert forest land for non-forest purposes based on the recommendations of the Forest Advisory Committee.  This approval is subject to the project developer complying with certain conditions.  Once these conditions are complied with, the central government issues the final clearance.  It is only after this clearance that the state government passes an order notifying the diversion of forest land.  The NGT’s decision deals with this point in the process during which an appeal can be filed against the order of forest clearance.  For the flowchart put out by the MoEF on the procedure for obtaining a forest clearance, see here. What was the NGT’s ruling on forest clearances? The NGT was hearing an appeal against a forest clearance given by the MoEF to divert 61 hectares of forest land for a hydroelectric project by GMR in Uttarakhand.  The NGT has ruled  that it does not have the jurisdiction to hear appeals against forest clearances given to projects by the MoEF.  However, the NGT has the power to hear appeals on an order or decision made by a state government or other authorities under the Forest (Conservation) Act, 1980.  The judgment observed that though Section 2 of the Forest (Conservation) Act, 1980 requires that state governments pass separate orders notifying the diversion of land, this requirement is not being followed.  The NGT has directed that state governments pass a reasoned order notifying the diversion of the forest land for non-forest purposes, immediately after the central government has given its clearance.  This will allow aggrieved citizens to challenge the forest clearance of a project after the state government has passed an order.  Additionally, the NGT has also directed the MoEF to issue a notification streamlining the procedure to be adopted by state governments and other authorities for passing orders granting forest clearance under section 2 of the Forest (Conservation) Act, 1980. There are some concerns that an appeal to the NGT can only be made after the state government has passed an order notifying the diversion of forest land and significant resources have been invested in the project. What is the status of applications for forest clearances made to the MoEF? The MoEF has given approval to 1126 proposals that involve the diversion of 15,639 hectares of forest land from July 13, 2011 to July 12, 2012.  The category of projects accorded the most number of approvals was road projects (308) followed by transmission lines (137).  Some of the other categories of projects that received clearance for a significant number of projects were mining, hydel and irrigation projects.  However, most land was diverted for mining related projects i.e., 40% of the total forest land diverted in this period.  Figure 1 shows a break up of the extent of forest land diverted for various categories of projects.  The number of forest clearances pending for decision by the MoEF for applications made in the years 2012, 2011 and 2010 are 197, 129 and 48 respectively. [i]

Source: “Environmental Clearance accorded from 13.07.2011 to 12.07.2012”, October 12, 2012, MoEF.

 

  [1] MoEF,  Rajya Sabha, Unstarred Question no. 2520, September 4, 2012

On November 28, 2012, the Comptroller and Auditor General submitted its report on the implementation of the Jawaharlal Nehru National Urban Renewal Mission (JNNURM).  According to the report most of the projects initiated under JNNURM have not been completed.  For instance with respect to urban infrastructure projects, only 231 projects out of the 1298 sanctioned projects have been completed.  Similarly, with respect to housing projects, only 22 of the 1517 projects have been completed.  Some of the other key recommendations of the report are:

  •  Some of the reasons for the delay in completing the projects include: (i) delay in acquiring land; (ii) deficiency in preparation of projects; and (iii) non-identification of beneficiaries which increased the risk of ineligible beneficiaries getting the benefits.
  •  A total allocation of Rs 66,084 crore had been made by the Planning Commission.  However, against this total allocation, the central government had made an allocation of only Rs 37,070 out of which until March 30, 2011 only Rs 32,934 had been released.
  • There was a delay in releasing these funds to the states.  A large portion of the funds was released only in the last quarter and more particularly in March.
  • The JNNURM guidelines were deficient as they did not provide adequate guidance to the states on the method of parking the funds and utilization of interest.

The need and objectives of JNNURM According to the 2011 census India’s urban population has increased from 286 million in 2001 to 377 million in 2011 .  With the increase in urban population, there is a requirement to improve the urban infrastructure and improve the service delivery mechanisms.  With these specific objectives in mind, the central government launched the Jawaharlal Nehru National Urban Renewal Mission 2005-2006.  The aim of the Mission is to encourage reforms and fast track planned development of identified cities (such as cities with a population of more than 1 million as per the 2001 census).  JNNURM has two main components namely : (i) Urban Infrastructure and Governance  and (ii) Urban Infrastructure Development for Small and Medium Towns. The duration of JNNURM was from 2005-06 to 2011-12. However, as the projects have not been completed the Government has extended its duration until March 2014. Funds for JNNURM The funds for JNNURM are provided through the Additional Central Assistance.  This implies that the funds are provided as grants to the states directly from the centre.   In the 2012 Union Budget, the central government has allocated Rs 12,522 crore for JNNURM. This represents around 10 % of the total central assistance through the different schemes to states and union territories in 2012-13. As on June 30 2012, 554 projects at a total cost of Rs 62,253 crore have been sanctioned under the Urban Infrastructure and Governance sub-mission of JNNURM.   The table below shows the status of the sanctioned JNNURM  projects in the different states. State wise status of the projects under JNNURM                 (as on August 6, 2012)

Name of State Total Allocation (Rs Lakh) Number of sanctioned projects Completed Projects
Andhra Pradesh 2,11,845 52 18
Arunachal Pradesh 10,740 3 NA
Assam 27,320 2 NA
Bihar 59,241 8 NA
Chandigarh 27,087 3 NA
Chattisgarh 24,803 1 NA
Delhi 2,82,318 23 4
Goa 12,094 2 NA
Gujarat 2,57,881 72 40
Haryana 32,332 4 NA
Himachal Pradesh 13,066 5 NA
Jammu & Kashmir 48,836 5 NA
Jharkhand 94,120 5 NA
Karnataka 1,52,459 47 22
Kerala 67,476 11 NA
Madhya Pradesh 1,32,850 23 7
Maharashtra 5,50,555 80 21
Manipur 15,287 3 NA
Meghalaya 15,668 2 NA
Mizoram 14,822 4 NA
Nagaland 11,628 3 NA
Orissa 32,235 5 NA
Punjab 70,775 6 1
Puducherry 20,680 2 NA
Rajasthan 74,869 13 2
Sikkim 10,613 2 NA
Tamil Nadu 2,25,066 48 12
Tripura 14,018 2 NA
Uttar Pradesh 2,76,941 33 4
Uttarakhand 40,534 14 NA
West Bengal 3,21,840 69 15

Source: Jawaharlal Nehru National Urban Renewal Mission; PRS.

  • Gujarat at 55.55% has the highest number of completed projects, while Uttar Pradesh at 12.24% has the lowest number of completed projects.
  • Out of the larger states, Delhi and Maharashtra at 17% and 26% have a comparatively low rate of completed projects.
  • Maharashtra has the highest number of sanctioned projects, while the North Eastern states, Chattisgarh and Puducherry have the lowest number of sanctioned projects.