The Monsoon Session of Parliament begins tomorrow and will continue till August 10, 2018.  It is scheduled to have 18 sittings during this period.  This post outlines what is in store in the upcoming session.

The session has a packed legislative agenda.  Presently, there are 68 Bills pending in Parliament.  Of these, 25 have been listed for consideration and passage.  In addition, 18 new Bills have been listed for introduction, consideration, and passage.  This implies that Parliament has the task of discussing and deliberating 43 Bills listed for passage in an 18-day sitting period.  Key among them include the Bills that are going to replace the six Ordinances currently in force.  The government is going to prioritize the passage of these six Bills to ensure that the Ordinances do not lapse.

Besides the heavy legislative agenda, the session will also witness the election of a new Deputy Chairman for the Upper House.  Former Deputy Chairman, P.J. Kurien’s term ended on July 1, 2018.  The upcoming election has generated keen interest, and will be closely watched.  The role of the Deputy Chairman is significant, as he quite frequently oversees the proceedings of the House.  The Deputy Chairman is responsible for maintaining order in the house and ensuring its smooth functioning.  The preceding Budget Session was the least productive since 2000 due to disruptions.  Rajya Sabha spent only 2 hours and 31 minutes discussing legislative business, of which 3 minutes were spent on government Bills.  In this context, the role of the Deputy Chairman is important in ensuring productivity of the house.

Another key player in ensuring productivity of Parliament is the Speaker of the Lower House.  In Budget Session 2018, the Speaker was unable to admit a no confidence motion.  This failure was based on her inability to bring the house in order.  Repeated disruptions led to the passage of only two Bills in Lok Sabha.  The same session also saw disruptions by certain MPs demanding special category status for Andhra Pradesh.  Between the last session and the upcoming session, a key development includes the resignation of five YRSC members, reducing the strength of MPs from Andhra Pradesh to 20.  In light of this, one has to wait to see whether the demand for special category status for Andhra Pradesh will be raised again.

Coming to the legislative agenda, of the six Bills that aim to replace Ordinances, key include: (i) the Fugitive Economic Offenders Bill, 2018, (ii) the Criminal Law (Amendment) Bill, 2018, (iii) the Insolvency and Bankruptcy Code (Amendment) Bill, 2018, and (iv) the Commercial Courts (Amendment) Bill, 2018.  The Fugitive Economic Offenders Bill aims to confiscate the properties of people who have absconded the country in order to avoid facing prosecution for economic offences.  The Fugitive Economic Offenders Bill, 2018 was introduced in Lok Sabha in March 2018.  Subsequently, an Ordinance was promulgated on April 21, 2018.  The Criminal Law (Amendment) Bill increases the punishment for rape of women, and introduces death penalty for rape of minor girls below the age of 12.  The Insolvency and Bankruptcy (Amendment) Bill aims to address existing challenges in the Insolvency and Bankruptcy Code.  It amends the Code to include homebuyers as financial creditors in the insolvency resolution process.

There are some Bills that have been passed by one house but are pending in the other, and some that are pending in both the houses.  These cut across various sectors, including social reform, education, health, consumer affairs, and transport.  Some key reformative legislation currently pending include the Transgender Persons (Protection of Rights) Bill, 2016, and the Triple Talaq Bill.  The Triple Talaq Bill, passed on the day of introduction in Lok Sabha, is pending in Rajya Sabha.  When introduced in Rajya Sabha, the opposition introduced a motion to refer the Bill to a Select Committee.  In the forthcoming session, it remains to be seen whether the Bill will be sent to a Select Committee for detailed scrutiny or will be passed without reference to a Committee.  Other pending legislation include the the National Medical Commission Bill, 2017, the RTE (Second Amendment) Bill, 2017, the Consumer Protection Bill, 2018 and the Specific Relief (Amendment) Bill, 2017.

Of the 18 new Bills listed for introduction, all have been listed for consideration and passage as well.  These include the Trafficking of Persons Bill, 2018, the DNA Technology (Use and Application) Regulation Bill, and amendments to the RTI Act.  Since they have been listed for passage, it remains to be seen whether these Bills are scheduled to be scrutinized by a Parliamentary Committee.  In the 16th Lok Sabha, only 28% of the Bills introduced in Lok Sabha have been referred to Committees.  This number is low in comparison to 60% and 71% of the introduced Bills being referred to Committees in the 14th and 15th Lok Sabha, respectively.  Committees ensure that Bills are closely examined.  This facilitates informed deliberation on the Bill, and strengthens the legislative process.

Besides taking up the legislative agenda, an important function of Parliament is to discuss issues of national importance and hold the government accountable.  In the previous session, the issue of irregularities in the banking sector was repeatedly listed for discussion.  However, due to disruptions, it was not taken up.  Budget Session 2018 saw the lowest number of non- legislative debates since the beginning of the 16th Lok Sabha.  In the upcoming session, it is likely that members will raise various issues for discussion.  It remains to be seen whether Parliament will function smoothly in order to power through its agenda, and fulfil its obligation to hold the government accountable.

In the recently concluded Monsoon Session of Parliament , the Parliamentary Standing Committee on Rural Development released a report on the implementation of the Mahatma Gandhi National Rural Development Act, 2005 (MGNREGA).  This blog provides a brief introduction to the key provisions of MGNREGA , followed by an overview of the major findings and recommendations of the Standing Committee.

I. MGNREGA: A brief introduction

A. Objectives: MGNREGA, which is the largest work guarantee programme in the world, was enacted in 2005 with the primary objective of guaranteeing 100 days of wage employment per year to rural households.  Secondly, it aims at addressing causes of chronic poverty through the 'works' (projects) that are undertaken, and thus ensuring sustainable development.  Finally, there is an emphasis on strengthening the process of decentralisation through giving a significant role to Panchayati Raj Institutions (PRIs) in planning and implementing these works.

B. Key features:

  • Legal right to work: Unlike earlier employment guarantee schemes, the Act provides a legal right to employment for adult members of rural households.  At least one third beneficiaries have to be women.  Wages must be paid according to the wages specified for agricultural labourers in the state under the  Minimum Wages Act, 1948, unless the central government notifies a wage rate (this should not be less than Rs 60 per day).  At present, wage rates are determined by the central government but vary across states, ranging from Rs 135 per day to Rs 214 per day.
  • Time bound guarantee of work and unemployment allowance: Employment must be provided with 15 days of being demanded failing which an ‘unemployment allowance’ must be given.
  • Decentralised planning: Gram sabhas must recommend the works that are to be undertaken and at least 50% of the works must be executed by them.  PRIs are primarily responsible for planning, implementation and monitoring of the works that are undertaken.
  • Work site facilities: All work sites should have facilities such as crèches, drinking water and first aid.
  • Transparency and accountability: There are provisions for proactive disclosure through wall writings, citizen information boards, Management Information Systems and social audits.  Social audits are conducted by gram sabhas to enable the community to monitor the implementation of the scheme.
  • Funding:  Funding is shared between the centre and the states.  There are three major items of expenditure – wages (for unskilled, semi-skilled and skilled labour), material and administrative costs.  The central government bears 100% of the cost of unskilled labour, 75% of the cost of semi-skilled and skilled labour, 75% of the cost of materials and 6% of the administrative costs.

MGNREGA was implemented in phases, starting from February 2006, and at present it covers all districts of the country with the exception of those that have a 100% urban population.  The Act provides a list of works that can be undertaken to generate employment related to water conservation, drought proofing, land development, and flood control and protection works.  Table 1 provides information regarding employment generation and expenditure under MGNREGA.

Table 1: MGNREGA: Key indicators

Year

Number of households provided employment (in crore)

Average number of person days of work per household

Total Expenditure (in lakh)

2006-07

2.10

43

8823.35

2007-08

3.39

42

15856.88

2008-09

4.51

48

27250.10

2009-10

5.25

54

37905.23

2010-11

5.49

47

39377.27

2011-12*

4.99

43

 38034.69

2012-13**

4.25

36

 28073.51

Source: Standing Committee on Rural Development; PRS. Note: *Provisional ** As on 31.01.2013

II. Findings and Recommendations of the Standing Committee on Rural Development

A. Achievements: The Standing Committee highlighted several achievements of MGNREGA in the seven years of its implementation, especially:

  • Ensuring livelihood for people in rural areas.
  • Large scale participation of women, Scheduled Castes and Scheduled Tribes (SCs/STs) and other traditionally marginalised sections of society.  SCs/STs account for 51% of the total person-days generated and women account for 47% of the total person-days generated.
  • Increasing the wage rate in rural areas and strengthening the rural economy through the creation of infrastructure assets.
  • Facilitating sustainable development, and
  • Strengthening PRIs by involving them in the planning and monitoring of the scheme.

B. Challenges: However, the Committee found several issues with the implementation of the scheme. As Table 1 (above) shows, the average number of days of employment provided to households has been lower than the mandated 100 days, and has been decreasing since 2010-11. Key issues that the Committee raised include

  • Fabrication of job cards: While as many as 12.5 crore households have been issued job cards out of an estimated 13.8 crore rural households ( as per the 2001 census), there are several issues related to existence of fake job cards, inclusion of fictitious names, missing entries and delays in making entries in job cards.
  • Delay in payment of wages: Most states have failed to disburse wages within 15 days as mandated by MGNREGA.  In addition, workers are not compensated for a delay in payment of wages.
  • Non payment of unemployment allowances: Most states do not pay an unemployment allowance when work is not given on demand.  The non-issuance of dated receipts of demanded work prevents workers from claiming an unemployment allowance.
  • Large number of incomplete works: There has been a delay in the completion of works under MGNREGA and inspection of projects has been irregular.  Implementing agencies were able to complete only 98 lakh works out of 296 lakh works.  As Table 2 shows, a large percentage of works remain incomplete under MGNREGA and the work completion rate appears to be decreasing in recent years.

Table 2: Work completion rate

Year

Work completion rate (%)

2006-07

46.34

2007-08

45.99

2008-09

43.76

2009-10

48.94

2010-11

50.86

2011-12*

20.25

2012-13*

15.02

Total                  33.22

Source: Standing Committee on Rural Development. Note: * As on 30.01.2013

  • Other key challenges include poor quality of assets created, several instances of corruption in the implementation of MGNREGA, and insufficient involvement of PRIs.

C. Recommendations: The Committee made the following recommendations, based on its findings:

  • Regulation of job cards: Offences such as not recording employment related information in job cards and unlawful possession of job cards with elected PRI representatives and MGNREGA functionaries should be made punishable under the Act.
  • Participation of women: Since the income of female workers typically raises the standard of living of their households to a greater extent than their male counterparts, the participation of women must be increased through raising awareness about MGNREGA.
  • Participation of people with disabilities: Special works (projects) must be identified for people with disabilities; and  special job cards must be issued and personnel must be employed to ensure their participation.
  • Utilisation of funds:  The Committee found that a large amount of funds allocated for MGNREGA have remained unutilised.  For example, in 2010-11, 27.31% of the funds remained unutilised.  The Committee recommends that the Department of Rural Development should analyse reasons for poor utilisation of funds and take steps to improve the same.  In addition, it should initiate action against officers found guilty of misappropriating funds under MGNREGA.
  • Context specific projects and convergence: Since states are at various stages of socio-economic development, they have varied requirements for development.  Therefore, state governments should be allowed to undertake works that are pertinent to their context.  There should be more emphasis on skilled and semi-skilled work under MGNREGA.  In addition, the Committee recommends a greater emphasis on convergence with other schemes such as the National Rural Livelihoods Mission, National Rural Health Mission, etc.
  • Payment of unemployment allowance: Dated receipts for demanded work should be issued so that workers can claim unemployment allowance.  Funds for unemployment allowance should be met by the central government.
  • Regular monitoring: National Level Monitors (NLMs) are deployed by the Ministry of Rural Development for regular and special monitoring of MGNREGA and to enquire into complaints regarding mis-utilisation of funds, etc.  The Committee recommends that the frequency of monitoring by NLMs should increase and appropriate measures should be taken by states based on their recommendations.  Additionally, social audits must mandatorily be held every six months.  The Committee observes that the performance of MGNREGA is better in states with effective social audit mechanisms.
  • Training of functionaries: Training and capacity building of elected representatives and other functionaries of PRIs must be done regularly as it will facilitate their involvement in the implementation of MGNREGA.