In the recently concluded Monsoon Session of Parliament , the Parliamentary Standing Committee on Rural Development released a report on the implementation of the Mahatma Gandhi National Rural Development Act, 2005 (MGNREGA).  This blog provides a brief introduction to the key provisions of MGNREGA , followed by an overview of the major findings and recommendations of the Standing Committee.

I. MGNREGA: A brief introduction

A. Objectives: MGNREGA, which is the largest work guarantee programme in the world, was enacted in 2005 with the primary objective of guaranteeing 100 days of wage employment per year to rural households.  Secondly, it aims at addressing causes of chronic poverty through the 'works' (projects) that are undertaken, and thus ensuring sustainable development.  Finally, there is an emphasis on strengthening the process of decentralisation through giving a significant role to Panchayati Raj Institutions (PRIs) in planning and implementing these works.

B. Key features:

  • Legal right to work: Unlike earlier employment guarantee schemes, the Act provides a legal right to employment for adult members of rural households.  At least one third beneficiaries have to be women.  Wages must be paid according to the wages specified for agricultural labourers in the state under the  Minimum Wages Act, 1948, unless the central government notifies a wage rate (this should not be less than Rs 60 per day).  At present, wage rates are determined by the central government but vary across states, ranging from Rs 135 per day to Rs 214 per day.
  • Time bound guarantee of work and unemployment allowance: Employment must be provided with 15 days of being demanded failing which an ‘unemployment allowance’ must be given.
  • Decentralised planning: Gram sabhas must recommend the works that are to be undertaken and at least 50% of the works must be executed by them.  PRIs are primarily responsible for planning, implementation and monitoring of the works that are undertaken.
  • Work site facilities: All work sites should have facilities such as crèches, drinking water and first aid.
  • Transparency and accountability: There are provisions for proactive disclosure through wall writings, citizen information boards, Management Information Systems and social audits.  Social audits are conducted by gram sabhas to enable the community to monitor the implementation of the scheme.
  • Funding:  Funding is shared between the centre and the states.  There are three major items of expenditure – wages (for unskilled, semi-skilled and skilled labour), material and administrative costs.  The central government bears 100% of the cost of unskilled labour, 75% of the cost of semi-skilled and skilled labour, 75% of the cost of materials and 6% of the administrative costs.

MGNREGA was implemented in phases, starting from February 2006, and at present it covers all districts of the country with the exception of those that have a 100% urban population.  The Act provides a list of works that can be undertaken to generate employment related to water conservation, drought proofing, land development, and flood control and protection works.  Table 1 provides information regarding employment generation and expenditure under MGNREGA.

Table 1: MGNREGA: Key indicators

Year

Number of households provided employment (in crore)

Average number of person days of work per household

Total Expenditure (in lakh)

2006-07

2.10

43

8823.35

2007-08

3.39

42

15856.88

2008-09

4.51

48

27250.10

2009-10

5.25

54

37905.23

2010-11

5.49

47

39377.27

2011-12*

4.99

43

 38034.69

2012-13**

4.25

36

 28073.51

Source: Standing Committee on Rural Development; PRS. Note: *Provisional ** As on 31.01.2013

II. Findings and Recommendations of the Standing Committee on Rural Development

A. Achievements: The Standing Committee highlighted several achievements of MGNREGA in the seven years of its implementation, especially:

  • Ensuring livelihood for people in rural areas.
  • Large scale participation of women, Scheduled Castes and Scheduled Tribes (SCs/STs) and other traditionally marginalised sections of society.  SCs/STs account for 51% of the total person-days generated and women account for 47% of the total person-days generated.
  • Increasing the wage rate in rural areas and strengthening the rural economy through the creation of infrastructure assets.
  • Facilitating sustainable development, and
  • Strengthening PRIs by involving them in the planning and monitoring of the scheme.

B. Challenges: However, the Committee found several issues with the implementation of the scheme. As Table 1 (above) shows, the average number of days of employment provided to households has been lower than the mandated 100 days, and has been decreasing since 2010-11. Key issues that the Committee raised include

  • Fabrication of job cards: While as many as 12.5 crore households have been issued job cards out of an estimated 13.8 crore rural households ( as per the 2001 census), there are several issues related to existence of fake job cards, inclusion of fictitious names, missing entries and delays in making entries in job cards.
  • Delay in payment of wages: Most states have failed to disburse wages within 15 days as mandated by MGNREGA.  In addition, workers are not compensated for a delay in payment of wages.
  • Non payment of unemployment allowances: Most states do not pay an unemployment allowance when work is not given on demand.  The non-issuance of dated receipts of demanded work prevents workers from claiming an unemployment allowance.
  • Large number of incomplete works: There has been a delay in the completion of works under MGNREGA and inspection of projects has been irregular.  Implementing agencies were able to complete only 98 lakh works out of 296 lakh works.  As Table 2 shows, a large percentage of works remain incomplete under MGNREGA and the work completion rate appears to be decreasing in recent years.

Table 2: Work completion rate

Year

Work completion rate (%)

2006-07

46.34

2007-08

45.99

2008-09

43.76

2009-10

48.94

2010-11

50.86

2011-12*

20.25

2012-13*

15.02

Total                  33.22

Source: Standing Committee on Rural Development. Note: * As on 30.01.2013

  • Other key challenges include poor quality of assets created, several instances of corruption in the implementation of MGNREGA, and insufficient involvement of PRIs.

C. Recommendations: The Committee made the following recommendations, based on its findings:

  • Regulation of job cards: Offences such as not recording employment related information in job cards and unlawful possession of job cards with elected PRI representatives and MGNREGA functionaries should be made punishable under the Act.
  • Participation of women: Since the income of female workers typically raises the standard of living of their households to a greater extent than their male counterparts, the participation of women must be increased through raising awareness about MGNREGA.
  • Participation of people with disabilities: Special works (projects) must be identified for people with disabilities; and  special job cards must be issued and personnel must be employed to ensure their participation.
  • Utilisation of funds:  The Committee found that a large amount of funds allocated for MGNREGA have remained unutilised.  For example, in 2010-11, 27.31% of the funds remained unutilised.  The Committee recommends that the Department of Rural Development should analyse reasons for poor utilisation of funds and take steps to improve the same.  In addition, it should initiate action against officers found guilty of misappropriating funds under MGNREGA.
  • Context specific projects and convergence: Since states are at various stages of socio-economic development, they have varied requirements for development.  Therefore, state governments should be allowed to undertake works that are pertinent to their context.  There should be more emphasis on skilled and semi-skilled work under MGNREGA.  In addition, the Committee recommends a greater emphasis on convergence with other schemes such as the National Rural Livelihoods Mission, National Rural Health Mission, etc.
  • Payment of unemployment allowance: Dated receipts for demanded work should be issued so that workers can claim unemployment allowance.  Funds for unemployment allowance should be met by the central government.
  • Regular monitoring: National Level Monitors (NLMs) are deployed by the Ministry of Rural Development for regular and special monitoring of MGNREGA and to enquire into complaints regarding mis-utilisation of funds, etc.  The Committee recommends that the frequency of monitoring by NLMs should increase and appropriate measures should be taken by states based on their recommendations.  Additionally, social audits must mandatorily be held every six months.  The Committee observes that the performance of MGNREGA is better in states with effective social audit mechanisms.
  • Training of functionaries: Training and capacity building of elected representatives and other functionaries of PRIs must be done regularly as it will facilitate their involvement in the implementation of MGNREGA.

By Rohit & Anirudh A modified 'Modernization of State Police Forces' scheme was started by the central government in 2000-01. One of the objectives was to help police forces in meeting the emerging challenges to internal security in the form of terrorism, naxalism etc. The scheme aims to modernize police forces in terms of:

  • Mobility (including purchase of bullet proof and mine proof vehicles)
  • Weaponry
  • Communication Systems
  • Training
  • Forensic Science Laboratory/ Finger Printing Bureau
  • Equipments
  • Buildings

Under this scheme, States have been clubbed into different categories and Centre-State cost sharing is category specific. Since 2005-06, States have been categorized as category ‘A’ and ‘B’ with 100% and 75% Central funding respectively. All the North Eastern States, namely Arunachal Pradesh, Assam, Manipur, Meghalaya, Mizoram, Nagaland, Tripura and Sikkim have been placed in category ‘A’ and thus, are entitled to receive 100% Central assistance for implementation of their annual approved plans. Recently, CAG decided to evaluate the working of the scheme and commissioned ‘performance audit’ reviews covering select general category and special category States. Each review covers a contiguous five year period between 2000 and 2007, but varies across selected states. For the periods under review, each state had a plan outlay (the total amount proposed to be spent in modernizing the state's police forces). However, in most cases, the actual release of funds fell significantly short of this outlay - in some cases the Centre did not contribute its share, in others the States lagged behind. For instance, in the case of Bihar, the Centre released only 56% of its share; while in the case of Rajasthan and West Bengal, the States did not release any funds at all. The graph below shows the actual releases by the Centre and the States (as percentages of their share in the proposed outlays): Further, even the funds that were released were not fully utilized. Thus, the amount finally spent fell significantly short of the initial proposal. The graph below shows the actual expenditure by State: Following are some of the other main findings from the CAG report:

Table 1: Summary of main findings in the CAG audit for different states for Modernisation of State Police Forces

Purpose for which money was sanctioned

Summary of CAG Findings

Planning

(Every state has to propose an Annual Action Plan every year. The plan is approved by the Ministry of Home Affairs and money is released as per the plan.)

§ Submissions by the states to the MHA were delayed.

§ There were also delays in the clearance granted by the MHA.

§ In various states such as,

a) Andhra Pradesh – the government spent money on works not covered by the Annual Action Plan.

b) Bihar – Persistent delays in preparation of the Plan by the state police.

c) West Bengal – the plans drawn up by the state did not include items covered under the scheme.

Mobility

§ Overall shortage of vehicles was observed. Most of the new vehicles replaced the old ones.

§ The police response time was too long in some states.

§ To give examples from some states:

a) Andhra Pradesh – 58 percent of vehicles procured were utilised for replacing old vehicles.

b) Bihar – the shortage of vehicles was 43 percent.

c) Uttar Pradesh – 2400 vehicles were procured against a shortage of nearly 10,000 vehicles.

Residential and non-residential buildings

§ There were considerable delays in construction of buildings in most states. Consequently, police forces’ own security was in jeopardy.

§ In states such as:

a) Andhra Pradesh – 53 percent of staff quarters and 43 percent of official buildings were not completed (2007).

b) Bihar – The total requirement of housing was nearly 60,000. Only six percent of this were included in the Plan.

c) Jharkhand – District Control rooms remained non-functional because of shortage of manpower.

Weapons

§ Police force in states continue to depend on outdated weapons.

§ Shortages of weapons also happened as acquisition from ordnance factories was very slow.

§ The weapons that were procured were mostly kept in the district headquarters.

§ In some states such as,

a) Bihar – AK-47s were kept at the disposal of bodyguards of VIPs.

b) West Bengal – Adequate weapons were not supplied to extremist prone police stations.

Communication

§ Police Telecommunication Networks were not set up successfully in some states. In others, network was functional only up to the district level.

§ Shortages of various communication equipments were also observed.

§ In some states such as,

a) Bihar - The Police Telecommunication Network system (costing Rs. 4.96 crore) remained non-functional due to non-construction of tower.

b) Maharashtra – Of the 850 purchased Remote Station Units, 452 were lying in stores.

Forensic Science Laboratory/ Finger Printing Bureau

§ In most States the Forensic Science Laboratories lacked adequate infrastructure.

§ In the absence of automatic finger print identification systems, investigation was being done manually in some States.

§ In some states such as,

a) Maharashtra - There were significant delays in receipt and installation. There was also shortage (284 vacant posts) of technical manpower.

b) West Bengal - Performance of the Forensic Science Laboratory was poor and in some cases, the delay in issue of investigation reports was as high as 45 months.

Training

§ It was observed that the percentage of police personnel trained was very low.

§ Training infrastructure was also inadequate.

§ In some states such as,

a) Bihar - Only 10 per cent of total force was trained.

b) West Bengal - Live training was not imparted for handling useful weapons and this severely affected the performance of police forces.

Sources: CAG Compendium of Performance Audit Reviews on Modernisation of Police Force; PRS.

Note: The audit has been done broadly from 2000 to 2007. Consequently, the period of audit for different states may vary.

Table 1: Summary of main findings in the CAG audit for different states for Modernisation of State Police Forces

Purpose for which money was sanctioned

Summary of CAG Findings

Planning

(Every state has to propose an Annual Action Plan every year. The plan is approved by the Ministry of Home Affairs and money is released as per the plan.)

§ Submissions by the states to the Ministry of Home Affairs (MHA) were delayed.

§ There were also delays in the clearance granted by the MHA.

§ In various states such as,

a) Andhra Pradesh – the government spent Rs 32 crore on works not covered by the Annual Action Plan.

b) Bihar – Persistent delays in preparation of the Plan by the state police.

c) West Bengal – the plans drawn up by the state did not include items covered under the scheme.

Mobility

§ Overall shortage of vehicles was observed. Most of the new vehicles replaced the old ones, and no additions were made.

§ The police response time was too long in some states.

§ To give examples from some states:

a) Andhra Pradesh – 58 percent of vehicles procured were utilised for replacing old vehicles.

b) Bihar – the shortage of vehicles was 43 percent.

c) Uttar Pradesh – 2400 vehicles were procured against a shortage of nearly 10,000 vehicles. 203 ambassador cars were procured, though only 55 were approved by the MHA.

Residential and non-residential buildings

§ There were considerable delays in construction of buildings in most states. Consequently, police forces’ own security was in jeopardy. Satisfaction levels with the housing provided were also very low.

§ In states such as:

a) Andhra Pradesh – 53 percent of staff quarters and 43 percent of official buildings were not completed (2007).

b) Bihar – The total requirement of housing was nearly 60,000. Only six percent of this were included in the Plan, and only 1045 units were completed by 2006.

c) Jharkhand – District Control rooms remained non-functional even after spending Rs 2 crore because of shortage of manpower.

Weapons

§ It was observed that the police force in states continue to depend on outdated weapons.

§ Shortages of weapons also happened as acquisition from ordnance factories was very slow.

§ The weapons that were procured were mostly kept in the district headquarters.

§ In some states such as,

a) Bihar – AK-47s were kept at the disposal of bodyguards of VIPs.

b) West Bengal – Adequate weapons were not supplied to extremist prone police stations.

Communication

§ Police Telecommunication Networks were not set up successfully in some states. In others, network was functional only up to the district level.

§ Shortages of various communication equipments were also observed.

§ In some states such as,

a) Bihar - The Police Telecommunication Network system (costing Rs. 4.96 crore) remained non-functional due to non-construction of tower.

b) Maharashtra – Of the 850 purchased Remote Station Units, 452 were lying in stores.

Forensic Science Laboratory/ Finger Printing Bureau

§ In most States the Forensic Science Laboratories lacked adequate infrastructure.

§ In the absence of automatic finger print identification systems, investigation was being done manually in some States.

§ In some states such as,

a) Maharashtra - There were significant delays in receipt and installation. There was also shortage (284 vacant posts) of technical manpower.

b) West Bengal - Performance of the Forensic Science Laboratory was poor and in some cases, the delay in issue of investigation reports was as high as 45 months.

Training

§ It was observed that the percentage of police personnel trained was very low.

§ Training infrastructure was also inadequate.

§ In some states such as,

a) Bihar - Only 10 per cent of total force was trained.

b) West Bengal - Live training was not imparted for handling useful weapons and this severely affected the performance of police forces.

Sources: CAG Compendium of Performance Audit Reviews on Modernisation of Police Force; PRS.

Note: The audit has been done broadly from 2000 to 2007. Consequently, the period of audit for different states may vary.