One of the main tasks of the Parliament is to frame laws through debate and discussion on the floor of the House. However, there have been repeated instances where Bills introduced by the government have been passed without substantive discussion (For news reports, click here and here). Even where Bills are debated extensively, occasions where the government introduces changes in the Bill directly as a response to Parliamentary debate are hard to find.
One recent exception is the list of amendments introduced to the National Green Tribunal Bill, 2010 by the Minister for Environment and Forests directly in response to issues raised on the floor of the House.
The Bill
The National Green Tribunal Bill, 2009 aims to set up specialised environmental courts in the country. It will hear initial complaints as well as appeals from decisions of authorities under various environmental laws. The Tribunal shall consist of both judicial and expert members. Expert members have to possess technical qualifications and expertise, and also practical experience.
The Tribunal shall hear only ‘substantial question relating to the environment’. Substantial questions are those which (a) affect the community at large, and not just individuals or groups of individuals, or (b) cause significant damage to the environment and property, or (c) cause harm to public health which is broadly measurable.
PRS in its analysis of the original (unamended) Bill, had raised the following issues (for detailed analysis, clickhere) :
The Debate
In the debate on the Bill in the Lok Sabha on April 21, 2010 a number of MPs raised substantive issues with respect to the Bill. Some of the issues raised were (From the news article quoted above):
1. The Bill fell short on parameters of “scope, efficiency, and access to justice”.
2. Setting up five benches while barring the jurisdiction of courts will “create huge distance for the poor community members and tribals to seek justice”.
3. Offenses under the Wildlife Protection Act and the Wildlife Protection Act will not be heard by the Tribunal.
4. “Section 15 puts an embargo against [persons] other than retired Judge of Supreme Court or Chief Justices of High Court. The other clause puts 15 years of administrative experience, which would open the path for packing the Tribunal with bureaucrats of the kind who did not enforce the environment related laws in their time in service.”
The Minister acknowledged the contribution of the members by stating that: “The members have made important suggestions. Even though their exact demands may not be part of the official amendments moved by the government… but I am open to their suggestions…I will remove all objectionable clauses or sections in the proposed law and keep the window of discussion open.”
The Minister’s response
In response to these issues, the Minister Mr. Jairam Ramesh introduced 10 amendments to the Bill on April 30, 2010. Though not all the issues raised were addressed, a number of changes were made. In addition, the Minister also assured the House that issues regarding access would be addressed by the government by following a “circuit” approach for the benches of the Tribunal i.e. the benches would travel around the area within their jurisdiction to hear complaints. (To read the response, click here, page 15250)
Some of the main amendments are:
1. Now any aggrieved person can can approach the Tribunal. Earlier limited access was provided.
2. The whole Act will be operational by notification at the same time. Different provisions will not be enforced separately at different points of time.
3. There is a procedure for direct appeal to the Supreme Court from the judgement of the Tribunal.
4. The number of expert and judicial members is clearly specified.
In addition, the Minister also assured that the Selection Committee for picking the members of the Tribunal will be transparent and will ensure that members are not “a parking place for retired civil servants”.
Earlier this month, guidelines for the Swachh Bharat Mission (Gramin) were released by the Ministry of Drinking Water and Sanitation. Key features of the Swachh Bharat Mission (Gramin), as outlined in the guidelines, are detailed below. In addition, a brief overview of sanitation levels in the country is provided, along with major schemes of the central government to improve rural sanitation. The Swachh Bharat Mission, launched in October 2014, consists of two sub-missions – the Swachh Bharat Mission (Gramin) (SBM-G), which will be implemented in rural areas, and the Swachh Bharat Mission (Urban), which will be implemented in urban areas. SBM-G seeks to eliminate open defecation in rural areas by 2019 through improving access to sanitation. It also seeks to generate awareness to motivate communities to adopt sustainable sanitation practices, and encourage the use of appropriate technologies for sanitation. I. Context Data from the last three Census’, in Table 1, shows that while there has been some improvement in the number of households with toilets; this number remains low in the country, especially in rural areas. Table 1: Percentage of households with toilets (national)
Year | Rural | Urban | Total |
1991 | 9% | 64% | 24% |
2001 | 22% | 74% | 36% |
2011 | 31% | 81% | 47% |
In addition, there is significant variation across states in terms of availability of household toilets in rural areas, as shown in Table 2. Table 2 also shows the change in percentage of rural households with toilets from 2001 to 2011. It is evident that the pace of this change has varied across states over the decade. Table 2: Percentage of rural households with toilets
State |
2001 |
2011 |
% Change |
Andhra Pradesh |
18 |
32 |
14 |
Arunachal Pradesh |
47 |
53 |
5 |
Assam |
60 |
60 |
0 |
Bihar |
14 |
18 |
4 |
Chhattisgarh |
5 |
15 |
9 |
Goa |
48 |
71 |
23 |
Gujarat |
22 |
33 |
11 |
Haryana |
29 |
56 |
27 |
Himachal Pradesh |
28 |
67 |
39 |
Jammu and Kashmir |
42 |
39 |
-3 |
Jharkhand |
7 |
8 |
1 |
Karnataka |
17 |
28 |
11 |
Kerala |
81 |
93 |
12 |
Madhya Pradesh |
9 |
13 |
4 |
Maharashtra |
18 |
38 |
20 |
Manipur |
78 |
86 |
9 |
Meghalaya |
40 |
54 |
14 |
Mizoram |
80 |
85 |
5 |
Nagaland |
65 |
69 |
5 |
Odisha |
8 |
14 |
6 |
Punjab |
41 |
70 |
30 |
Rajasthan |
15 |
20 |
5 |
Sikkim |
59 |
84 |
25 |
Tamil Nadu |
14 |
23 |
9 |
Tripura |
78 |
82 |
4 |
Uttar Pradesh |
19 |
22 |
3 |
Uttarakhand |
32 |
54 |
23 |
West Bengal |
27 |
47 |
20 |
All India |
22 |
31 |
9 |
II. Major schemes of the central government to improve rural sanitation The central government has been implementing schemes to improve access to sanitation in rural areas from the Ist Five Year Plan (1951-56) onwards. Major schemes of the central government dealing with rural sanitation are outlined below.
Central Rural Sanitation Programme (1986): The Central Rural Sanitation Programme was one of the first schemes of the central government which focussed solely on rural sanitation. The programme sought to construct household toilets, construct sanitary complexes for women, establish sanitary marts, and ensure solid and liquid waste management. |
Total Sanitation Campaign (1999): The Total Sanitation Campaign was launched in 1999 with a greater focus on Information, Education and Communication (IEC) activities in order to make the creation of sanitation facilities demand driven rather than supply driven. Key components of the Total Sanitation Campaign included: (i) financial assistance to rural families below the poverty line for the construction of household toilets, (ii) construction of community sanitary complexes, (iii) construction of toilets in government schools and aganwadis, (iv) funds for IEC activities, (v) assistance to rural sanitary marts, and (vi) solid and liquid waste management. |
Nirmal Bharat Abhiyan (2012): In 2012, the Total Sanitation Campaign was replaced by the Nirmal Bharat Abhiyan (NBA), which also focused on the previous elements. According to the Ministry of Drinking Water and Sanitation, the key shifts in NBA were: (i) a greater focus on coverage for the whole community instead of a focus on individual houses, (ii) the inclusion of certain households which were above the poverty line, and (iii) more funds for IEC activities, with 15% of funds at the district level earmarked for IEC. |
Swachh Bharat Mission (Gramin) (2014): Earlier this year, in October, NBA was replaced by Swachh Bharat Mission (Gramin) (SBM-G) which is a sub-mission under Swachh Bharat Mission. SBM-G also includes the key components of the earlier sanitation schemes such as the funding for the construction of individual household toilets, construction of community sanitary complexes, waste management, and IEC. Key features of SBM-G, and major departures from earlier sanitation schemes, are outlined in the next section. |
III. Guidelines for Swachh Bharat Mission (Gramin) The guidelines for SBM-G, released earlier this month, outline the strategy to be adopted for its implementation, funding, and monitoring. Objectives: Key objectives of SBM-G include: (i) improving the quality of life in rural areas through promoting cleanliness and eliminating open defecation by 2019, (ii) motivating communities and panchayati raj institutions to adopt sustainable sanitation practices, (iii) encouraging appropriate technologies for sustainable sanitation, and (iv) developing community managed solid and liquid waste management systems. Institutional framework: While NBA had a four tier implementation mechanism at the state, district, village, and block level, an additional tier has been added for SBM-G, at the national level. Thus, the implementation mechanisms at the five levels will consist of: (i) National Swachh Bharat Mission (Gramin), (ii) State Swachh Bharat Mission (Gramin), (iii) District Swachh Bharat Mission (Gramin), (iv) Block Programme Management Unit, and (v) Gram Panchayat/Village and Water Sanitation Committee. At the Gram Panchayat level, Swachhta Doots may be hired to assist with activities such as identification of beneficiaries, IEC, and maintenance of records. Planning: As was done under NBA, each state must prepare an Annual State Implementation Plan. Gram Panchayats must prepare implementation plans, which will be consolidated into Block Implementation Plans. These Block Implementation Plans will further be consolidated into District Implementation Plans. Finally, District Implementation Plans will be consolidated in a State Implementation Plan by the State Swachh Bharat Mission (Gramin). A Plan Approval Committee in Ministry of Drinking Water and Sanitation will review the State Implementation Plans. The final State Implementation Plan will be prepared by states based on the allocation of funds, and then approved by National Scheme Sanctioning Committee of the Ministry. Funding: Funding for SBM-G will be through budgetary allocations of the central and state governments, the Swachh Bharat Kosh, and multilateral agencies. The Swachh Bharat Kosh has been established to collect funds from non-governmental sources. Table 3, below, details the fund sharing pattern for SBM-G between the central and state government, as provided for in the SBM-G guidelines. Table 3: Funding for SBM-G across components
Component | Centre | State | Beneficiary | Amount as a % of SBM-G outlay |
IEC, start-up activities, etc | 75% | 25% | - | 8% |
Revolving fund | 80% | 20% | - | Up to 5% |
Construction of household toilets | 75%(Rs 9000)90% for J&K, NE states, special category states | 25%(Rs 3000)10% for J&K, NE states, special category states | -- | Amount required for full coverage |
Community sanitary complexes | 60% | 30% | 10% | Amount required for full coverage |
Solid/Liquid Waste Management | 75% | 25% | - | Amount required within limits permitted |
Administrative charges | 75% | 25% | - | Up to 2% of the project cost |
One of the changes from NBA, in terms of funding, is that funds for IEC will be up to 8% of the total outlay under SBM-G, as opposed to up to 15% (calculated at the district level) under NBA. Secondly, the amount provided for the construction of household toilets has increased from Rs 10,000 to Rs 12,000. Thirdly, while earlier funding for household toilets was partly through NBA and partly though the Mahatma Gandhi National Rural Employment Guarantee Scheme (MGNREGS), the provision for MGNREGS funding has been done away with under SBM-G. This implies that the central government’s share will be met entirely through SBM-G. Implementation: The key components of the implementation of SBM-G will include: (i) start up activities including preparation of state plans, (ii) IEC activities, (iii) capacity building of functionaries, (iv) construction of household toilets, (v) construction of community sanitary complexes, (vi) a revolving fund at the district level to assist Self Help Groups and others in providing cheap finance to their members (vii) funds for rural sanitary marts, where materials for the construction of toilets, etc., may be purchased, and (viii) funds for solid and liquid waste management. Under SBM-G, construction of toilets in government schools and aganwadis will be done by the Ministry of Human Resource Development and Ministry of Women and Child Development, respectively. Previously, the Ministry of Drinking Water and Sanitation was responsible for this. Monitoring: Swachh Bharat Missions (Gramin) at the national, state, and district levels will each have monitoring units. Annual monitoring will be done at the national level by third party independent agencies. In addition, concurrent monitoring will be done, ideally at the community level, through the use of Information and Communications Technology. More information on SBM-G is available in the SBM-G guidelines, here.