One of the main tasks of the Parliament is to frame laws through debate and discussion on the floor of the House.  However, there have been repeated instances where Bills introduced by the government have been passed without substantive discussion (For news reports, click here and here).  Even where Bills are debated extensively, occasions where the government introduces changes in the Bill directly as a response to Parliamentary debate are hard to find.

One recent exception is the list of amendments introduced to the National Green Tribunal Bill, 2010 by the Minister for Environment and Forests directly in response to issues raised on the floor of the House.

The Bill

The National Green Tribunal Bill, 2009 aims to set up specialised environmental courts in the country.  It will hear initial complaints as well as appeals from decisions of authorities under various environmental laws.  The Tribunal shall consist of both judicial and expert members.  Expert members have to possess technical qualifications and expertise, and also practical experience.

The Tribunal shall hear only ‘substantial question relating to the environment’.  Substantial questions are those which (a) affect the community at large, and not just individuals or groups of individuals, or (b) cause significant damage to the environment and property, or (c) cause harm to public health which is broadly measurable.

PRS in its analysis of the original (unamended) Bill, had raised the following issues (for detailed analysis, clickhere) :

  • The criteria to determine what a ‘substantial question related to the
    environment’ are open to interpretation.
  • The Bill may reduce access to justice in environmental matters by taking away the jurisdiction of civil courts.  All cases under laws mentioned in the Bill will now be handled by the Tribunal which will initially have benches at only five locations.
  • The Bill does not give the Tribunal jurisdiction over some laws related
    to the environment.
  • The qualifications of judicial members of the Tribunal are similar to that of the existing National Environment Appellate Authority (NEAA).  The government has been unable to find qualified members for the NEAA for the past three years.  The Green Tribunal Bill gives an explicit option to the government to appoint members with administrative experience as expert members.
  • The Bill does not specify the minimum number of members the Tribunal and also does not mention of the composition of the Selection Committee for selecting members.

The Debate

In the debate on the Bill in the Lok Sabha on April 21, 2010 a number of MPs raised substantive issues with respect to the Bill.  Some of the issues raised were (From the news article quoted above):

1. The Bill fell short on parameters of “scope, efficiency, and access to justice”.

2. Setting up five benches while barring the jurisdiction of courts will “create huge distance for the poor community members and tribals to seek justice”.

3. Offenses under the Wildlife Protection Act and the Wildlife Protection Act will not be heard by the Tribunal.

4. “Section 15 puts an embargo against [persons] other than retired Judge of Supreme Court or Chief Justices of High Court. The other clause puts 15 years of administrative experience, which would open the path for packing the Tribunal with bureaucrats of the kind who did not enforce the environment related laws in their time in service.”

The Minister acknowledged the contribution of the members by stating that: “The members have made important suggestions. Even though their exact demands may not be part of the official amendments moved by the government… but I am open to their suggestions…I will remove all objectionable clauses or sections in the proposed law and keep the window of discussion open.”

The Minister’s response

In response to these issues, the Minister Mr. Jairam Ramesh introduced 10 amendments to the Bill on April 30, 2010.  Though not all the issues raised were addressed, a number of changes were made.  In addition, the Minister also assured the House that issues regarding access would be addressed by the government by following a “circuit” approach for the benches of the Tribunal i.e. the benches would travel around the area within their jurisdiction to hear complaints. (To read the response, click here, page 15250)

Some of the main amendments are:

1.  Now any aggrieved person can can approach the Tribunal.  Earlier limited access was provided.

2. The whole Act will be operational by notification at the same time.  Different provisions will not be enforced separately at different points of time.

3. There is a procedure for direct appeal to the Supreme Court from the judgement of the Tribunal.

4. The number of expert and judicial members is clearly specified.

In addition, the Minister also assured that the Selection Committee for picking the members of the Tribunal will be transparent and will ensure that members are not “a parking place for retired civil servants”.

Recently, the central government launched the Pradhan Mantri Sahaj Bijli Har Ghar Yojana (or Saubhagya).[i],[ii]  The scheme seeks to ensure universal household electrification (in both rural and urban areas) by providing last mile connectivity.  The scheme is expected to cover three crore households.  Note that currently about four crore households are un-electrified.  A rural electrification scheme has also been under implementation since 2005.  In light of this, we discuss the current situation of, and key issues related to rural electrification in the country.

Regulatory and policy framework

Under the Electricity Act, 2003, the central and state governments have the joint responsibility of providing electricity to rural areas.  The 2003 Act also mandates that the central government should, in consultation with the state governments, provide for a national policy on (i) stand-alone power systems for rural areas (systems that are not connected to the electricity grid), and (ii) electrification and local distribution in rural areas.  Consequently, the Rural Electrification Policy was notified in August 2006.[iii]

The Rajiv Gandhi Grameen Vidyutikaran Yojana (RGGVY), launched in 2005, was the first scheme on rural electrification.  In December 2014, Ministry of Power launched the Deendayal Upadhyaya Gram Jyoti Yojana (DDUGJY), which subsumed the RGGVY.[iv]  Components of DDUGJY include: (i) separation of agricultural and non-agricultural electricity feeders to improve supply for consumers in rural areas, (ii) improving sub-transmission and distribution infrastructure in rural areas, and (iii) rural electrification by carrying forward targets specified under the RGGVY.

The total financial outlay for DDUGJY over the implementation period (until 2021-22) is Rs 82,300 crore which includes budgetary support of Rs 68,900 crore.  The central government provides 60% of the project cost as grant, the state power distribution companies (discoms) raise 10% of the funds, and 30% is borrowed from financial institutions and banks.

Status of rural electrification

As of August 2017, about 1% of the villages in India remain un-electrified (3,146 villages).  However, with regard to households, around 23% (4.1 crore households) are yet to be electrified.  Table 1 at the end of this post shows the status of rural electrification across all states.

Issues with rural electrification

Definition of an electrified village

An electrified village is defined as one that has the following: (i) provision of basic infrastructure such as distribution transformers and lines in the inhabited locality, (ii) provision of electricity in public places like schools, panchayat office, health centers, dispensaries, and community centers, and (iii) at least 10% of the total number of households in the village are electrified.[iv]

Therefore, a village is considered to be electrified if 10% of the total number of households in the village have been electrified.  This is apart from the basic infrastructure and electrification of certain public centers in the village.  The Standing Committee on Energy (2013) had observed that according to this definition, a village would be called electrified even if up to 90% of households in it do not have an electricity connection.[v]  It also noted that the infrastructure being provided under the scheme is highly inadequate, unreliable and unsustainable.  The Committee recommended that the actual electrification requirement of villages must be assessed, and it should be ensured that the state discoms provide electricity to the remaining households in the village.

Supply of electricity

The Standing Committee had also noted that while the rural electrification scheme looks at creating infrastructure, the actual supply of electricity to households rests with the state discoms.[v]  These discoms are already facing huge financial losses and hence are unable to supply electricity to the villages.  Discoms continue to supply subsidised power to agricultural and residential consumers, resulting in revenue losses.  Further, the average technical and commercial losses (theft and pilferage of electricity) (AT&C losses) are at around 25%.  While the Ujjwal Discom Assurance Yojana (UDAY) has eased off some of the financial losses of the discoms, it remains to be seen whether discoms are able to reduce the cost-tariff gap and AT&C losses in the future.

It has been recommended that generation capacity should be augmented so that states can meet the additional demand under the rural electrification schemes. Further, the assistance to financially weaker states should be increased so that they can better implement the scheme.[v]

Electricity to below poverty line (BPL) households

Under the rural electrification scheme, the cost for providing free electricity connection per BPL household is Rs 3,000.  It has been observed that this cost per household may be inadequate.[v]  Due to the low cost, the quantity and the quality of work has been getting compromised leading to poor implementation of the scheme.  It has been recommended that the Ministry should revisit the cost provided under the scheme.[v]

The new electrification scheme: Pradhan Mantri Sahaj Bijli Har Ghar Yojana (or Saubhagya)

The new scheme, Saubhagya, seeks to ensure universal household electrification, that is, in both rural and urban areas.  Under Saubhagya, beneficiaries will be identified using the Socio Economic and Caste Census (SECC) 2011 data.  The identified poor households will get free electricity connections.  Other households not covered under the SECC, will be provided electricity connections at a cost of Rs 500.  This amount will be collected by the electricity distribution companies in 10 instalments.

The total outlay of the scheme will be Rs 16,320 crore, of which the central government will provide Rs 12,320 crore.  The outlay for the rural households will be Rs 14,025 crore, of which the centre will provide Rs 10,588 crore.  For urban households the outlay will be Rs 2,295 crore of which the centre will provide Rs. 1,733 crore.

The state discoms will execute the electrification works through contractors or other suitable agencies.  Information technology (mobile apps, web portals) will be used to organise camps in villages to identify beneficiaries.  In order to accelerate the process, applications for electricity connections will be completed on the spot.

So far the focus of electrification schemes has been on rural areas, where typically last mile connectivity has been difficult to provide.  Saubhagya extends the ambit of electrification projects to urban areas as well.  While DDUGJY has focused on the village as the principal unit to measure electrification, the new scheme shifts the targets to household electrification.  While the target for ensuring electricity connection in each household will be a significant step towards ensuring 24×7 power, the question of continuous and quality supply to these households will still rest on the ability of the discoms to provide electricity.  Further, while the scheme provides for free connections, the ability of these households to pay for the electricity they consume may be a concern.

Table 1: Status of rural electrification across states (as of August 2017)

Fig 1 edit

* all villages in Telangana were declared electrified before the bifurcation of the state.
Sources:  Ministry of Power; PRS.

 

[i] “PM launches Pradhan Mantri Sahaj Bijli Har Ghar Yojana “Saubhagya””, Press Information Bureau, Ministry of Power, September 25, 2017.

[ii] “FAQs on Pradhan Mantri Sahaj Bijli Har Ghar Yojana “Saubhagya””, Press Information Bureau, Ministry of Power, September 27, 2017.

[iii].  Rural Electrification Policy, Ministry of Power, August 23, 2006, http://powermin.nic.in/sites/default/files/uploads/RE%20Policy_1.pdf.

[iv].  “Office memorandum: Deendayal Upadhyaya Gram Jyoti Yojana”, Ministry of Power, December 3, 2014, http://powermin.nic.in/rural_electrification/pdf/Deendayal_Upadhyaya_Gram_Jyoti_Yojana.pdf.

[v].  “41st Report: Implementation of Rajiv Gandhi Grameen Vidyutikaran Yojana”, Standing Committee on Energy, December 13, 2013, http://164.100.47.134/lsscommittee/Energy/15_Energy_41.pdf.