One of the most politically contentious issues in recent times has been the government’s right to acquire land for ‘public purpose’.  Increasingly, farmers are refusing to part with their land without adequate compensation, the most recent example being the agitation in Uttar Pradesh over the acquisition of land for the Yamuna Express Highway. Presently, land acquisition in India is governed by the Land Acquisition Act, an archaic law passed more than a century ago in 1894.  According to the Act, the government has the right to acquire private land without the consent of the land owners if the land is acquired for a “public purpose” project (such as development of towns and village sites, building of schools, hospitals and housing and state run corporations).  The land owners get only the current price value of the land as compensation.  The key provision that has triggered most of the discontent is the one that allows the government to acquire land for private companies if it is for a “public purpose” project.  This has led to conflict over issues of compensation, rehabilitation of displaced people and the type of land that is being acquired. The UPA government introduced the Land Acquisition (Amendment) Bill in conjunction with the Rehabilitation and Resettlement Bill on December 6, 2007 in the Lok Sabha and referred them to the Standing Committee on Rural Development for scrutiny.  The Committee submitted its report on October 21, 2008 but the Bills lapsed at the end of the 14th Lok Sabha.  The government is planning to introduce revised versions of the Bills.  The following paragraphs discuss the lapsed Bills to give some idea of the government’s perspective on the issue while analysing the lacunae in the Bills. The Land Acquisition (Amendment) Bill, 2007 redefined “public purpose” to allow land acquisition only for defence purposes, infrastructure projects, or any project useful to the general public where 70% of the land had already been purchased from willing sellers through the free market.  It prohibited land acquisition for companies unless they had already purchased 70% of the required land.  The Bill also made it mandatory for the government to conduct a social impact assessment if land acquisition resulted in displacement of 400 families in the plains or 200 families in the hills or tribal areas.  The compensation was to be extended to tribals and individuals with tenancy rights under state laws.  The compensation was based on many factors such as market rates, the intended use of the land, and the value of standing crop.  A Land Acquisition Compensation Disputes Settlement Authority was to be established to adjudicate disputes. The Rehabilitation and Resettlement Bill, 2007 sought to provide for benefits and compensation to people displaced by land acquisition or any other involuntary displacements.  The Bill created project-specific authorities to formulate, implement and monitor the rehabilitation process.  It also outlined minimum benefits for displaced families such as land, house, monetary compensation, skill training and preference for jobs.  A grievance redressal system was also provided for. Although the Bills were a step in the right direction, many issues still remained unresolved.  Since the Land Acquisition Bill barred the civil courts from entertaining any disputes related to land acquisition, it was unclear whether there was a mechanism by which a person could challenge the qualification of a project as “public purpose”.  Unlike the Special Economic Zone Act, 2005, the Bill did not specify the type of land that could be acquired (such as waste and barren lands).  The Bill made special provision for land taken in the case of ‘urgency’.  However, it did not define the term urgency, which could lead to confusion and misuse of the term. The biggest loop-hole in the Rehabilitation and Resettlement Bill was the use of non-binding language.  Take for example Clause 25, which stated that “The Government may, by notification, declare any area…as a resettlement area.” Furthermore, Clause 36(1) stated that land for land “shall be allotted…if Government land is available.”  The government could effectively get away with not providing many of the benefits listed in the Bill.  Also, most of the safeguards and benefits were limited to families affected by large-scale displacements (400 or more families in the plains and 200 or more families in the hills and tribal areas).  The benefits for affected families in case of smaller scale displacements were not clearly spelt out.  Lastly, the Bill stated that compensation to displaced families should be borne by the requiring body (body which needs the land for its projects).  Who would bear the expenditure of rehabilitation in case of natural disasters remained ambiguous. If India is to attain economic prosperity, the government needs to strike a balance between the need for development and protecting the rights of people whose land is being acquired. Kaushiki Sanyal The article was published in Sahara Time (Issue dated September 4, 2010, page 36)

In law, the addition or deletion a single punctuation or a single word can have a major impact on the effect of that law.  One such example can be seen from the recommended changes in the Civil Liability for Nuclear Damage Bill, 2010 by Parliament’s Standing Committee. The Civil Liability for Nuclear Damage Bill, 2010 was introduced in the Lok Sabha on May 7, 2010.  The Bill was referred to the Parliamentary Committee on Science and Technology, Environment and Forests, which submitted its report on the Bill yesterday (August 18, 2010).  The Committee has made a number of recommendations regarding certain clauses in the Bill (See summary here).  One of these may have the effect of diluting the provision currently in the Bill.  The main recommendations pertain to:

  • Preventing the entry of private operators.
  • Allowing the government to increase the total liability for a nuclear incident by notification, but not decrease it.
  • Increasing the liability of the operator to Rs 1,500 crore from Rs 500 crore.
  • Increasing the time limit for claiming compensation to 20 years from 10 years.
  • Changing the provision giving operators a right of recourse against persons actually responsible for causing damage.

Clause 17 of the Bill which gives operators a right of recourse against those actually causing damage had been opposed as it was felt that it was not strong enough to hold suppliers liable in case the damage was caused by them.  Clause 17 gave a right of recourse under three conditions.  The exact clause is reproduced below: The operator of a nuclear installation shall have a right of recourse where — (a) such right is expressly provided for in a contract in writing; (b) the nuclear incident has resulted from the wilful act or gross negligence on the part of the supplier of the material, equipment or services, or of his employee; (c) the nuclear incident has resulted from the act of commission or omission of a person done with the intent to cause nuclear damage. Under this clause, a right of recourse exists when (a) there is a contract giving such a right, or (b) the supplier acts deliberately or in a grossly negligent manner to cause nuclear damage, or (c) a person causes nuclear damage with the intent to do so.  If any of the three cases can be proved by the operator, he has a right of recourse. The Committee has stated that “Clause 17(b) gives escape route to the suppliers of nuclear materials, equipments, services of his employees as their willful act or gross negligence would be difficult to establish in a civil nuclear compensation case.” It recommended that Clause 17(b) should be modified to cover consequences “of latent or patent defect, supply of sub-standard material, defective equipment or services or from the gross negligence on the part of the supplier of the material, equipment or service.” The Committee also recommended another change in Clause 17.  It recommended that clause 17(a) may end with “and”. This provision may dilute the right of recourse available to operators.  The modified clause 17 would read as: The operator of a nuclear installation shall have a right of recourse where — (a) such right is expressly provided for in a contract in writing; and, (b) the nuclear incident has resulted as a consequence of latent or patent defect, supply of sub-standard material, defective equipment or services or from the gross negligence on the part of the supplier of the material, equipment or services.; (c) the nuclear incident has resulted from the act of commission or omission of a person done with the intent to cause nuclear damage. This implies that for Clauses 17(b) or (c) to be applicable, the condition specified in clause 17(a) has to be compulsorily satisfied.  Two examples highlight the consequence of the recommended change in Clause 17(a) of the Bill:

  1. A person X deliberately commits sabotage in a nuclear plant and causes damage.  Under the Bill, the operator has recourse under Clause 17(c).  If the recommendation regarding clause 17 is accepted, the operator may also have to also prove the existence of a pre-existing contract with X in addition to clause 17(c).
  2. If a supplier supplies defective equipment, but does not have a contract in writing stating that he will be liable for damage caused by defective equipment, the operator may not have a right of recourse against the supplier under 17(b).

The effect of the changes recommended by the committee may thus dilute the provision as it exists in the Bill.  The table below compares the position in the Bill and the position as per the Standing Committee’s recommendations:

Right of recourse - The Bill gives operators a right to recourse under three conditions:  (a) if there is a clear contract; (b) if the damage is caused by someone with intent to cause damage; (c) against suppliers if damage is caused by their wilful act or negligence. In the Bill the three conditions are separated by a semi-colon.  The Committee recommended that the semi-colon in clause 17(a) should be replaced by “and”. This might imply that all three conditions mentioned need to exist for an operator to have recourse.
Right to recourse against suppliers exists in cases of “willful act or gross negligence on the part of the supplier”. (Clause 17) The Committee felt that the right of recourse against suppliers is vague.  It recommended that recourse against the supplier should be strengthened.  The supplier is liable if an incident has occurred due to (i) defects, or (ii) sub-standard material, or (iii) gross negligence of the supplier of the material, equipment or services. The variance with the Convention continues to exist.