One of the most politically contentious issues in recent times has been the government’s right to acquire land for ‘public purpose’.  Increasingly, farmers are refusing to part with their land without adequate compensation, the most recent example being the agitation in Uttar Pradesh over the acquisition of land for the Yamuna Express Highway. Presently, land acquisition in India is governed by the Land Acquisition Act, an archaic law passed more than a century ago in 1894.  According to the Act, the government has the right to acquire private land without the consent of the land owners if the land is acquired for a “public purpose” project (such as development of towns and village sites, building of schools, hospitals and housing and state run corporations).  The land owners get only the current price value of the land as compensation.  The key provision that has triggered most of the discontent is the one that allows the government to acquire land for private companies if it is for a “public purpose” project.  This has led to conflict over issues of compensation, rehabilitation of displaced people and the type of land that is being acquired. The UPA government introduced the Land Acquisition (Amendment) Bill in conjunction with the Rehabilitation and Resettlement Bill on December 6, 2007 in the Lok Sabha and referred them to the Standing Committee on Rural Development for scrutiny.  The Committee submitted its report on October 21, 2008 but the Bills lapsed at the end of the 14th Lok Sabha.  The government is planning to introduce revised versions of the Bills.  The following paragraphs discuss the lapsed Bills to give some idea of the government’s perspective on the issue while analysing the lacunae in the Bills. The Land Acquisition (Amendment) Bill, 2007 redefined “public purpose” to allow land acquisition only for defence purposes, infrastructure projects, or any project useful to the general public where 70% of the land had already been purchased from willing sellers through the free market.  It prohibited land acquisition for companies unless they had already purchased 70% of the required land.  The Bill also made it mandatory for the government to conduct a social impact assessment if land acquisition resulted in displacement of 400 families in the plains or 200 families in the hills or tribal areas.  The compensation was to be extended to tribals and individuals with tenancy rights under state laws.  The compensation was based on many factors such as market rates, the intended use of the land, and the value of standing crop.  A Land Acquisition Compensation Disputes Settlement Authority was to be established to adjudicate disputes. The Rehabilitation and Resettlement Bill, 2007 sought to provide for benefits and compensation to people displaced by land acquisition or any other involuntary displacements.  The Bill created project-specific authorities to formulate, implement and monitor the rehabilitation process.  It also outlined minimum benefits for displaced families such as land, house, monetary compensation, skill training and preference for jobs.  A grievance redressal system was also provided for. Although the Bills were a step in the right direction, many issues still remained unresolved.  Since the Land Acquisition Bill barred the civil courts from entertaining any disputes related to land acquisition, it was unclear whether there was a mechanism by which a person could challenge the qualification of a project as “public purpose”.  Unlike the Special Economic Zone Act, 2005, the Bill did not specify the type of land that could be acquired (such as waste and barren lands).  The Bill made special provision for land taken in the case of ‘urgency’.  However, it did not define the term urgency, which could lead to confusion and misuse of the term. The biggest loop-hole in the Rehabilitation and Resettlement Bill was the use of non-binding language.  Take for example Clause 25, which stated that “The Government may, by notification, declare any area…as a resettlement area.” Furthermore, Clause 36(1) stated that land for land “shall be allotted…if Government land is available.”  The government could effectively get away with not providing many of the benefits listed in the Bill.  Also, most of the safeguards and benefits were limited to families affected by large-scale displacements (400 or more families in the plains and 200 or more families in the hills and tribal areas).  The benefits for affected families in case of smaller scale displacements were not clearly spelt out.  Lastly, the Bill stated that compensation to displaced families should be borne by the requiring body (body which needs the land for its projects).  Who would bear the expenditure of rehabilitation in case of natural disasters remained ambiguous. If India is to attain economic prosperity, the government needs to strike a balance between the need for development and protecting the rights of people whose land is being acquired. Kaushiki Sanyal The article was published in Sahara Time (Issue dated September 4, 2010, page 36)

The Comptroller and Auditor General (CAG) released a Performance Audit of Allocation of Coal Blocks and Augmentation of Coal Production, on August 17, 2012.  Some of the main findings and recommendations of the report are highlighted below:

  • There were no criteria for allocating coal blocks for captive mining till 1993.  The process of bringing in transparency and objectivity began in January 2004.  However, the process has experienced delays and had yet to materialise as of February 2012.
  • In the intervening period, 194 coal blocks with geological reserves of 44,440 million tonnes were allocated to private and government parties until March 31, 2011.  The report finds that the benefit to private allottees has been estimated at Rs 1.86 lakh crore for Opencast mines.  The report states that the government could have tapped some of this financial benefit by expediting the decision on competitive bidding for allocation of coal blocks.
  • The rate of increase in production of coal by Coal India Limited (CIL) during the 11th Plan period remained below the target set by the Planning Commission.  Capacity addition projects were delayed due to the lack of coordination of government agencies involved in statutory clearances and land acquisition.  There were mismatches in excavation and transportation capacities of mines, and suboptimal use of Heavy Earth Moving Machinery.
  • The CAG recommends that Ministry of Coal (MOC) should work out modalities to implement the procedure of allocation of coal blocks for captive mining through competitive bidding.
  • The CAG recommends that the MOC should constitute an empowered group along the lines of Foreign Investment Promotion Board as a single window mechanism for granting clearances, with representatives from central nodal ministries and state governments.

A one-page summary of the main findings and recommendations can be accessed here.  The full report can be accessed on the CAG website.