One of the most politically contentious issues in recent times has been the government’s right to acquire land for ‘public purpose’.  Increasingly, farmers are refusing to part with their land without adequate compensation, the most recent example being the agitation in Uttar Pradesh over the acquisition of land for the Yamuna Express Highway. Presently, land acquisition in India is governed by the Land Acquisition Act, an archaic law passed more than a century ago in 1894.  According to the Act, the government has the right to acquire private land without the consent of the land owners if the land is acquired for a “public purpose” project (such as development of towns and village sites, building of schools, hospitals and housing and state run corporations).  The land owners get only the current price value of the land as compensation.  The key provision that has triggered most of the discontent is the one that allows the government to acquire land for private companies if it is for a “public purpose” project.  This has led to conflict over issues of compensation, rehabilitation of displaced people and the type of land that is being acquired. The UPA government introduced the Land Acquisition (Amendment) Bill in conjunction with the Rehabilitation and Resettlement Bill on December 6, 2007 in the Lok Sabha and referred them to the Standing Committee on Rural Development for scrutiny.  The Committee submitted its report on October 21, 2008 but the Bills lapsed at the end of the 14th Lok Sabha.  The government is planning to introduce revised versions of the Bills.  The following paragraphs discuss the lapsed Bills to give some idea of the government’s perspective on the issue while analysing the lacunae in the Bills. The Land Acquisition (Amendment) Bill, 2007 redefined “public purpose” to allow land acquisition only for defence purposes, infrastructure projects, or any project useful to the general public where 70% of the land had already been purchased from willing sellers through the free market.  It prohibited land acquisition for companies unless they had already purchased 70% of the required land.  The Bill also made it mandatory for the government to conduct a social impact assessment if land acquisition resulted in displacement of 400 families in the plains or 200 families in the hills or tribal areas.  The compensation was to be extended to tribals and individuals with tenancy rights under state laws.  The compensation was based on many factors such as market rates, the intended use of the land, and the value of standing crop.  A Land Acquisition Compensation Disputes Settlement Authority was to be established to adjudicate disputes. The Rehabilitation and Resettlement Bill, 2007 sought to provide for benefits and compensation to people displaced by land acquisition or any other involuntary displacements.  The Bill created project-specific authorities to formulate, implement and monitor the rehabilitation process.  It also outlined minimum benefits for displaced families such as land, house, monetary compensation, skill training and preference for jobs.  A grievance redressal system was also provided for. Although the Bills were a step in the right direction, many issues still remained unresolved.  Since the Land Acquisition Bill barred the civil courts from entertaining any disputes related to land acquisition, it was unclear whether there was a mechanism by which a person could challenge the qualification of a project as “public purpose”.  Unlike the Special Economic Zone Act, 2005, the Bill did not specify the type of land that could be acquired (such as waste and barren lands).  The Bill made special provision for land taken in the case of ‘urgency’.  However, it did not define the term urgency, which could lead to confusion and misuse of the term. The biggest loop-hole in the Rehabilitation and Resettlement Bill was the use of non-binding language.  Take for example Clause 25, which stated that “The Government may, by notification, declare any area…as a resettlement area.” Furthermore, Clause 36(1) stated that land for land “shall be allotted…if Government land is available.”  The government could effectively get away with not providing many of the benefits listed in the Bill.  Also, most of the safeguards and benefits were limited to families affected by large-scale displacements (400 or more families in the plains and 200 or more families in the hills and tribal areas).  The benefits for affected families in case of smaller scale displacements were not clearly spelt out.  Lastly, the Bill stated that compensation to displaced families should be borne by the requiring body (body which needs the land for its projects).  Who would bear the expenditure of rehabilitation in case of natural disasters remained ambiguous. If India is to attain economic prosperity, the government needs to strike a balance between the need for development and protecting the rights of people whose land is being acquired. Kaushiki Sanyal The article was published in Sahara Time (Issue dated September 4, 2010, page 36)

Recently, the government issued letters de-allocating coal blocks of various companies, based on the recommendations of the  Inter Ministerial Group (IMG).  This post discusses the history behind the de-allocations, the parameters the IMG used while examining the progress of various coal blocks and the action that has been taken by the government. The Comptroller and Auditor General (CAG) released a performance audit report on 'Allocation of Coal Blocks and Augmentation of Coal Production' on August 17, 2012.  Some of the key findings of the Report were:

  • The government failed to conduct competitive bids for the allocation of coal blocks.  This resulted in a benefit of  Rs 1.86 lakh crore (approx.) to private allottees.  The government could have tapped some of this financial benefit by expediting the decision on competitive bidding for allocation of coal blocks.
  • The implementation schedule of a number of coal blocks has been delayed by one to ten years.  This schedule relates to the time frame within which the Mining Plan for the block has to be approved, various clearances have to be submitted, land acquired, etc.
  • From 2005, the Ministry of Coal (MoC) required the allottees to provide bank guarantees which would be encashed if they failed to meet the above mentioned milestones.  The CAG observed that there was a delay in introducing the bank guarantee and linking it with milestones.

The IMG on Coal was constituted for the periodic review of the development of coal blocks and end use plants.  The IMG had requested a status paper from the Coal Controller, MoC.  This has been submitted to the IMG but is not available.  The IMG will decide if private allottees have made substantial progress based on certain parameters.  The parameters used by IMG are:  approval of Mining Plan, status of environment and forest clearance, grant of mining lease and progress made in land acquisition. They are also examining the physical status of End Use Plant (EUP), investment made and the expected date of opening of the mine and commissioning of EUP. The IMG has made the following recommendations:

  • The coal blocks of companies that have not made substantial progress should be de-allocated.  Additionally, they have recommended the deduction of bank guarantee in the cases where the private companies have not reached the milestones as per the time line decided upon.  As of November 22, 2012, the IMG has recommended the de-allocation of the coal blocks listed in Table 1 and the deduction of bank guarantees for the coal blocks in Table 2.
  • Since, the system of bank guarantee was only introduced in March 2005, not all coal blocks had submitted a bank guarantee.  Where a bank guarantee has not been provided but there is substantial progress in meeting the milestones, the IMG may require the allottee to submit a bank guarantee.

[table id=1 /]

 

[table id=5 /]

 

Of the coal blocks that the IMG has recommended for de-allocation, until now the government has accepted the de-allocation of the following: Bramhadih block, Gourangdih, New Patrapara, Chinora block, Warora (Southern Part) block, Lalgarh (North) block, Bhaskarpara block, Dahegaon/Makardhokra-IV block, Gondkhari block and Ramanwara North block.  The government has accepted the deduction of bank guarantees for blocks such as Moitra, Jitpur, Bhaskarpara, Durgapur II/Sariya, Dahegaon/Makardhokra-IV, Marki Mangli II, III and IV, Gondhkari, Lohari, Radhikapur East, Bijahan and Nerad Malegaon. The letters issued by the government de-allocating coal blocks and deducting bank guarantees are available here.

For a detailed summary of the CAG Report, click here.