Finances of the Railways were presented along with the Union Budget on February 1, 2018 (the Railways Budget was merged with the Union Budget last year).  In the current Budget Session, Lok Sabha is scheduled to discuss the allocation to the Ministry of Railways.  In light of this, we discuss Railways’ finances, and issues that the transporter has been facing with regard to financing.

What are the different sources of revenue for Railways?

Indian Railways has three primary sources of revenue: (i) its own internal resources (revenue from freight and passenger traffic, leasing of railway land, etc.), (ii) budgetary support from the central government, and (iii) extra budgetary resources (such as market borrowings, institutional financing).

Figure 1Railways’ internal revenue for 2018-19 is estimated at Rs 2,01,090 crore which is 7% higher than the revised estimates of 2017-18.  Majority of this revenue comes from traffic (both freight and passenger), and is estimated at Rs 2,00,840 crore.  In the last few years, Railways has been struggling to run its transportation business, and generate its own revenue.  The growth rate of Railways’ earnings from its core business of running freight and passenger trains has been declining.  This is due to a decline in the growth of both freight and passenger traffic (see Figure 1).  Railways is also slowly losing traffic share to other modes of transport such as roads and airlines.  The share of Railways in total freight traffic has declined from 89% in 1950-51 to 30% in 2011-12.

 

The Committee on Restructuring Railways (2015) had observed that raising revenue for Railways is a challenge because: (i) investment is made in projects that do not have traffic and hence do not generate revenue, (ii) the efficiency improvements do not result in increasing revenue, and (iii) delays in projects results in cost escalation, which makes it difficult to recover costs.  Railways also provides passenger fares that are heavily subsidised, which results in the passenger business facing losses of around Rs 33,000 crore in a year (in 2014-15).  Passenger fares are also cross-subsidised by charging higher rates for freight.  The consequence is that freight rates have been increasing which has resulted in freight traffic moving towards roads.

Figure 2Figure 2 shows the trends in capital outlay over the last decade.  A decline in internal revenue generation has meant that Railways funds its capital expenditure through budgetary support from the central government and external borrowings.  While the support from central government has mostly remained consistent, Railways’ borrowings have been increasing.  Various committees have noted that an increased reliance on borrowings will further exacerbate the financial situation of Railways.

The total proposed capital outlay (or capital expenditure) for 2018-19 is Rs 1,48,528 crore which is a 24% increase from the 2017-18 revised estimates (Rs 1,20,000 crore).  Majority of this capital expenditure will be financed through borrowings (55%), followed by the budgetary support from the central government (37%).  Railways will fund only 8% of its capital expenditure from its own internal resources.

How can Railways raise more money?

The Committee on Restructuring Railways had suggested that Railways can raise more revenue through private participation in the following ways: (i) service and management contracts, (ii) leasing to and from the private sector, (iii) joint ventures, and (iv) private ownership.  However, private participation in Railways has been muted as compared to other sectors such as roads, and airports.

Figure 3One of the key reasons for the failure of private participation in Railways is that policy making, the regulatory function, and operations are all vested within the same organisation, that is, the Ministry of Railways.  Railways’ monopoly also discourages private sector entry into the market.  The Committee on Restructuring Railways had recommended that the three roles must be separated from each other.  It had also recommended setting up an independent regulator for the sector.  The regulator will monitor whether tariffs are market determined and competitive.

Where does Railways spend its money?

The total expenditure for 2018-19 is projected at Rs 1,88,100 crore, which is 4% higher than 2017-18.  Staff wages and pension together comprise more than half of the Railways’ expenditure.  For 2018-19, the expenditure on staff is estimated at Rs 76,452 crore.  Allocation to the Pension Fund is estimated at Rs 47,600 crore.  These constitute about 66% of the Railways’ expenditure in 2018-19.

Railways’ primary expenditure, which is towards the payment of salaries and pension, has been gradually increasing (with a jump of around 15% each year in 2016-17 and 2017-18 due to implementation of the Seventh Pay Commission recommendations).  Further, the pension bill is expected to increase further in the years to come, as about 40% of the Railways staff was above the age of 50 years in 2016-17.

The Committee on Restructuring Railways (2015) had observed that the expenditure on staff is extremely high and unmanageable.  This expense is not under the control of Railways and keeps increasing with each Pay Commission revision.  It has also been observed that employee costs (including pensions) is one of the key components that reduces Railways’ ability to generate surplus, and allocate resources towards operations.

What is the allocation towards depreciation of assets?

Railways maintains a Depreciation Reserve Fund (DRF) to finance the costs of new assets replacing the old ones.  In 2018-19, appropriation to the DRF is estimated at Rs 500 crore, 90% lower than 2017-18 (Rs 5,000 crore).  In the last few years, appropriation to the DRF has decreased significantly from Rs 7,775 crore in 2014-15 to Rs 5,000 crore last year.  Provisioning Rs 500 crore towards depreciation might be an extremely small amount considering the scale of infrastructure managed by the Indian Railways, and the requirement to replace old assets to ensure safety.

The Standing Committee on Railways (2015) had observed that appropriation to the DRF is the residual amount after appropriation to the Pension Fund, instead of the actual requirement for maintenance of assets.  Under-provisioning for the DRF has also been observed as one of the reasons behind the decline in track renewals, and procurement of wagons and coaches.

Is there any provision towards safety?

Last year, the Rashtriya Rail Sanraksha Kosh was created to provide for passenger safety.  It was to have a corpus of one lakh crore rupees over a period of five years (Rs 20,000 crore per year).  The central government was to provide a seed amount of Rs 1,000 crore, and the remaining amount would be raised by the Railways from their own revenues or other sources.

As per the revised estimates of 2017-18, no money was allocated towards this fund.  In 2018-19, Rs 5,000 crore has been allocated for it.  With the Railways struggling to meet its expenditure and declining internal revenues, it is unclear how Railways will fund the remaining amount of Rs 95,000 crore for the Rail Sanraksha Kosh.

What happened to the dividend that was waived off last year?

Railways used to pay a return on the budgetary support it received from the government every year, known as dividend.  The rate of this dividend was about 5% in 2015-16.  From 2016-17, the requirement of paying dividend was waived off.  The last dividend amount paid was Rs 8,722 crore in 2015-16.

The Standing Committee on Railways (2017) had noted that part of the benefit from dividend is being utilised to meet the shortfall in the traffic earnings of Railways.  This defeats the purpose of removing the dividend liabilities since they are not being utilised in creating assets or increasing the net revenue of Railways.

On November 28, 2012, the Comptroller and Auditor General submitted its report on the implementation of the Jawaharlal Nehru National Urban Renewal Mission (JNNURM).  According to the report most of the projects initiated under JNNURM have not been completed.  For instance with respect to urban infrastructure projects, only 231 projects out of the 1298 sanctioned projects have been completed.  Similarly, with respect to housing projects, only 22 of the 1517 projects have been completed.  Some of the other key recommendations of the report are:

  •  Some of the reasons for the delay in completing the projects include: (i) delay in acquiring land; (ii) deficiency in preparation of projects; and (iii) non-identification of beneficiaries which increased the risk of ineligible beneficiaries getting the benefits.
  •  A total allocation of Rs 66,084 crore had been made by the Planning Commission.  However, against this total allocation, the central government had made an allocation of only Rs 37,070 out of which until March 30, 2011 only Rs 32,934 had been released.
  • There was a delay in releasing these funds to the states.  A large portion of the funds was released only in the last quarter and more particularly in March.
  • The JNNURM guidelines were deficient as they did not provide adequate guidance to the states on the method of parking the funds and utilization of interest.

The need and objectives of JNNURM According to the 2011 census India’s urban population has increased from 286 million in 2001 to 377 million in 2011 .  With the increase in urban population, there is a requirement to improve the urban infrastructure and improve the service delivery mechanisms.  With these specific objectives in mind, the central government launched the Jawaharlal Nehru National Urban Renewal Mission 2005-2006.  The aim of the Mission is to encourage reforms and fast track planned development of identified cities (such as cities with a population of more than 1 million as per the 2001 census).  JNNURM has two main components namely : (i) Urban Infrastructure and Governance  and (ii) Urban Infrastructure Development for Small and Medium Towns. The duration of JNNURM was from 2005-06 to 2011-12. However, as the projects have not been completed the Government has extended its duration until March 2014. Funds for JNNURM The funds for JNNURM are provided through the Additional Central Assistance.  This implies that the funds are provided as grants to the states directly from the centre.   In the 2012 Union Budget, the central government has allocated Rs 12,522 crore for JNNURM. This represents around 10 % of the total central assistance through the different schemes to states and union territories in 2012-13. As on June 30 2012, 554 projects at a total cost of Rs 62,253 crore have been sanctioned under the Urban Infrastructure and Governance sub-mission of JNNURM.   The table below shows the status of the sanctioned JNNURM  projects in the different states. State wise status of the projects under JNNURM                 (as on August 6, 2012)

Name of State Total Allocation (Rs Lakh) Number of sanctioned projects Completed Projects
Andhra Pradesh 2,11,845 52 18
Arunachal Pradesh 10,740 3 NA
Assam 27,320 2 NA
Bihar 59,241 8 NA
Chandigarh 27,087 3 NA
Chattisgarh 24,803 1 NA
Delhi 2,82,318 23 4
Goa 12,094 2 NA
Gujarat 2,57,881 72 40
Haryana 32,332 4 NA
Himachal Pradesh 13,066 5 NA
Jammu & Kashmir 48,836 5 NA
Jharkhand 94,120 5 NA
Karnataka 1,52,459 47 22
Kerala 67,476 11 NA
Madhya Pradesh 1,32,850 23 7
Maharashtra 5,50,555 80 21
Manipur 15,287 3 NA
Meghalaya 15,668 2 NA
Mizoram 14,822 4 NA
Nagaland 11,628 3 NA
Orissa 32,235 5 NA
Punjab 70,775 6 1
Puducherry 20,680 2 NA
Rajasthan 74,869 13 2
Sikkim 10,613 2 NA
Tamil Nadu 2,25,066 48 12
Tripura 14,018 2 NA
Uttar Pradesh 2,76,941 33 4
Uttarakhand 40,534 14 NA
West Bengal 3,21,840 69 15

Source: Jawaharlal Nehru National Urban Renewal Mission; PRS.

  • Gujarat at 55.55% has the highest number of completed projects, while Uttar Pradesh at 12.24% has the lowest number of completed projects.
  • Out of the larger states, Delhi and Maharashtra at 17% and 26% have a comparatively low rate of completed projects.
  • Maharashtra has the highest number of sanctioned projects, while the North Eastern states, Chattisgarh and Puducherry have the lowest number of sanctioned projects.