Finances of the Railways were presented along with the Union Budget on February 1, 2018 (the Railways Budget was merged with the Union Budget last year).  In the current Budget Session, Lok Sabha is scheduled to discuss the allocation to the Ministry of Railways.  In light of this, we discuss Railways’ finances, and issues that the transporter has been facing with regard to financing.

What are the different sources of revenue for Railways?

Indian Railways has three primary sources of revenue: (i) its own internal resources (revenue from freight and passenger traffic, leasing of railway land, etc.), (ii) budgetary support from the central government, and (iii) extra budgetary resources (such as market borrowings, institutional financing).

Figure 1Railways’ internal revenue for 2018-19 is estimated at Rs 2,01,090 crore which is 7% higher than the revised estimates of 2017-18.  Majority of this revenue comes from traffic (both freight and passenger), and is estimated at Rs 2,00,840 crore.  In the last few years, Railways has been struggling to run its transportation business, and generate its own revenue.  The growth rate of Railways’ earnings from its core business of running freight and passenger trains has been declining.  This is due to a decline in the growth of both freight and passenger traffic (see Figure 1).  Railways is also slowly losing traffic share to other modes of transport such as roads and airlines.  The share of Railways in total freight traffic has declined from 89% in 1950-51 to 30% in 2011-12.

 

The Committee on Restructuring Railways (2015) had observed that raising revenue for Railways is a challenge because: (i) investment is made in projects that do not have traffic and hence do not generate revenue, (ii) the efficiency improvements do not result in increasing revenue, and (iii) delays in projects results in cost escalation, which makes it difficult to recover costs.  Railways also provides passenger fares that are heavily subsidised, which results in the passenger business facing losses of around Rs 33,000 crore in a year (in 2014-15).  Passenger fares are also cross-subsidised by charging higher rates for freight.  The consequence is that freight rates have been increasing which has resulted in freight traffic moving towards roads.

Figure 2Figure 2 shows the trends in capital outlay over the last decade.  A decline in internal revenue generation has meant that Railways funds its capital expenditure through budgetary support from the central government and external borrowings.  While the support from central government has mostly remained consistent, Railways’ borrowings have been increasing.  Various committees have noted that an increased reliance on borrowings will further exacerbate the financial situation of Railways.

The total proposed capital outlay (or capital expenditure) for 2018-19 is Rs 1,48,528 crore which is a 24% increase from the 2017-18 revised estimates (Rs 1,20,000 crore).  Majority of this capital expenditure will be financed through borrowings (55%), followed by the budgetary support from the central government (37%).  Railways will fund only 8% of its capital expenditure from its own internal resources.

How can Railways raise more money?

The Committee on Restructuring Railways had suggested that Railways can raise more revenue through private participation in the following ways: (i) service and management contracts, (ii) leasing to and from the private sector, (iii) joint ventures, and (iv) private ownership.  However, private participation in Railways has been muted as compared to other sectors such as roads, and airports.

Figure 3One of the key reasons for the failure of private participation in Railways is that policy making, the regulatory function, and operations are all vested within the same organisation, that is, the Ministry of Railways.  Railways’ monopoly also discourages private sector entry into the market.  The Committee on Restructuring Railways had recommended that the three roles must be separated from each other.  It had also recommended setting up an independent regulator for the sector.  The regulator will monitor whether tariffs are market determined and competitive.

Where does Railways spend its money?

The total expenditure for 2018-19 is projected at Rs 1,88,100 crore, which is 4% higher than 2017-18.  Staff wages and pension together comprise more than half of the Railways’ expenditure.  For 2018-19, the expenditure on staff is estimated at Rs 76,452 crore.  Allocation to the Pension Fund is estimated at Rs 47,600 crore.  These constitute about 66% of the Railways’ expenditure in 2018-19.

Railways’ primary expenditure, which is towards the payment of salaries and pension, has been gradually increasing (with a jump of around 15% each year in 2016-17 and 2017-18 due to implementation of the Seventh Pay Commission recommendations).  Further, the pension bill is expected to increase further in the years to come, as about 40% of the Railways staff was above the age of 50 years in 2016-17.

The Committee on Restructuring Railways (2015) had observed that the expenditure on staff is extremely high and unmanageable.  This expense is not under the control of Railways and keeps increasing with each Pay Commission revision.  It has also been observed that employee costs (including pensions) is one of the key components that reduces Railways’ ability to generate surplus, and allocate resources towards operations.

What is the allocation towards depreciation of assets?

Railways maintains a Depreciation Reserve Fund (DRF) to finance the costs of new assets replacing the old ones.  In 2018-19, appropriation to the DRF is estimated at Rs 500 crore, 90% lower than 2017-18 (Rs 5,000 crore).  In the last few years, appropriation to the DRF has decreased significantly from Rs 7,775 crore in 2014-15 to Rs 5,000 crore last year.  Provisioning Rs 500 crore towards depreciation might be an extremely small amount considering the scale of infrastructure managed by the Indian Railways, and the requirement to replace old assets to ensure safety.

The Standing Committee on Railways (2015) had observed that appropriation to the DRF is the residual amount after appropriation to the Pension Fund, instead of the actual requirement for maintenance of assets.  Under-provisioning for the DRF has also been observed as one of the reasons behind the decline in track renewals, and procurement of wagons and coaches.

Is there any provision towards safety?

Last year, the Rashtriya Rail Sanraksha Kosh was created to provide for passenger safety.  It was to have a corpus of one lakh crore rupees over a period of five years (Rs 20,000 crore per year).  The central government was to provide a seed amount of Rs 1,000 crore, and the remaining amount would be raised by the Railways from their own revenues or other sources.

As per the revised estimates of 2017-18, no money was allocated towards this fund.  In 2018-19, Rs 5,000 crore has been allocated for it.  With the Railways struggling to meet its expenditure and declining internal revenues, it is unclear how Railways will fund the remaining amount of Rs 95,000 crore for the Rail Sanraksha Kosh.

What happened to the dividend that was waived off last year?

Railways used to pay a return on the budgetary support it received from the government every year, known as dividend.  The rate of this dividend was about 5% in 2015-16.  From 2016-17, the requirement of paying dividend was waived off.  The last dividend amount paid was Rs 8,722 crore in 2015-16.

The Standing Committee on Railways (2017) had noted that part of the benefit from dividend is being utilised to meet the shortfall in the traffic earnings of Railways.  This defeats the purpose of removing the dividend liabilities since they are not being utilised in creating assets or increasing the net revenue of Railways.

Recently, the central government launched the Pradhan Mantri Sahaj Bijli Har Ghar Yojana (or Saubhagya).[i],[ii]  The scheme seeks to ensure universal household electrification (in both rural and urban areas) by providing last mile connectivity.  The scheme is expected to cover three crore households.  Note that currently about four crore households are un-electrified.  A rural electrification scheme has also been under implementation since 2005.  In light of this, we discuss the current situation of, and key issues related to rural electrification in the country.

Regulatory and policy framework

Under the Electricity Act, 2003, the central and state governments have the joint responsibility of providing electricity to rural areas.  The 2003 Act also mandates that the central government should, in consultation with the state governments, provide for a national policy on (i) stand-alone power systems for rural areas (systems that are not connected to the electricity grid), and (ii) electrification and local distribution in rural areas.  Consequently, the Rural Electrification Policy was notified in August 2006.[iii]

The Rajiv Gandhi Grameen Vidyutikaran Yojana (RGGVY), launched in 2005, was the first scheme on rural electrification.  In December 2014, Ministry of Power launched the Deendayal Upadhyaya Gram Jyoti Yojana (DDUGJY), which subsumed the RGGVY.[iv]  Components of DDUGJY include: (i) separation of agricultural and non-agricultural electricity feeders to improve supply for consumers in rural areas, (ii) improving sub-transmission and distribution infrastructure in rural areas, and (iii) rural electrification by carrying forward targets specified under the RGGVY.

The total financial outlay for DDUGJY over the implementation period (until 2021-22) is Rs 82,300 crore which includes budgetary support of Rs 68,900 crore.  The central government provides 60% of the project cost as grant, the state power distribution companies (discoms) raise 10% of the funds, and 30% is borrowed from financial institutions and banks.

Status of rural electrification

As of August 2017, about 1% of the villages in India remain un-electrified (3,146 villages).  However, with regard to households, around 23% (4.1 crore households) are yet to be electrified.  Table 1 at the end of this post shows the status of rural electrification across all states.

Issues with rural electrification

Definition of an electrified village

An electrified village is defined as one that has the following: (i) provision of basic infrastructure such as distribution transformers and lines in the inhabited locality, (ii) provision of electricity in public places like schools, panchayat office, health centers, dispensaries, and community centers, and (iii) at least 10% of the total number of households in the village are electrified.[iv]

Therefore, a village is considered to be electrified if 10% of the total number of households in the village have been electrified.  This is apart from the basic infrastructure and electrification of certain public centers in the village.  The Standing Committee on Energy (2013) had observed that according to this definition, a village would be called electrified even if up to 90% of households in it do not have an electricity connection.[v]  It also noted that the infrastructure being provided under the scheme is highly inadequate, unreliable and unsustainable.  The Committee recommended that the actual electrification requirement of villages must be assessed, and it should be ensured that the state discoms provide electricity to the remaining households in the village.

Supply of electricity

The Standing Committee had also noted that while the rural electrification scheme looks at creating infrastructure, the actual supply of electricity to households rests with the state discoms.[v]  These discoms are already facing huge financial losses and hence are unable to supply electricity to the villages.  Discoms continue to supply subsidised power to agricultural and residential consumers, resulting in revenue losses.  Further, the average technical and commercial losses (theft and pilferage of electricity) (AT&C losses) are at around 25%.  While the Ujjwal Discom Assurance Yojana (UDAY) has eased off some of the financial losses of the discoms, it remains to be seen whether discoms are able to reduce the cost-tariff gap and AT&C losses in the future.

It has been recommended that generation capacity should be augmented so that states can meet the additional demand under the rural electrification schemes. Further, the assistance to financially weaker states should be increased so that they can better implement the scheme.[v]

Electricity to below poverty line (BPL) households

Under the rural electrification scheme, the cost for providing free electricity connection per BPL household is Rs 3,000.  It has been observed that this cost per household may be inadequate.[v]  Due to the low cost, the quantity and the quality of work has been getting compromised leading to poor implementation of the scheme.  It has been recommended that the Ministry should revisit the cost provided under the scheme.[v]

The new electrification scheme: Pradhan Mantri Sahaj Bijli Har Ghar Yojana (or Saubhagya)

The new scheme, Saubhagya, seeks to ensure universal household electrification, that is, in both rural and urban areas.  Under Saubhagya, beneficiaries will be identified using the Socio Economic and Caste Census (SECC) 2011 data.  The identified poor households will get free electricity connections.  Other households not covered under the SECC, will be provided electricity connections at a cost of Rs 500.  This amount will be collected by the electricity distribution companies in 10 instalments.

The total outlay of the scheme will be Rs 16,320 crore, of which the central government will provide Rs 12,320 crore.  The outlay for the rural households will be Rs 14,025 crore, of which the centre will provide Rs 10,588 crore.  For urban households the outlay will be Rs 2,295 crore of which the centre will provide Rs. 1,733 crore.

The state discoms will execute the electrification works through contractors or other suitable agencies.  Information technology (mobile apps, web portals) will be used to organise camps in villages to identify beneficiaries.  In order to accelerate the process, applications for electricity connections will be completed on the spot.

So far the focus of electrification schemes has been on rural areas, where typically last mile connectivity has been difficult to provide.  Saubhagya extends the ambit of electrification projects to urban areas as well.  While DDUGJY has focused on the village as the principal unit to measure electrification, the new scheme shifts the targets to household electrification.  While the target for ensuring electricity connection in each household will be a significant step towards ensuring 24×7 power, the question of continuous and quality supply to these households will still rest on the ability of the discoms to provide electricity.  Further, while the scheme provides for free connections, the ability of these households to pay for the electricity they consume may be a concern.

Table 1: Status of rural electrification across states (as of August 2017)

Fig 1 edit

* all villages in Telangana were declared electrified before the bifurcation of the state.
Sources:  Ministry of Power; PRS.

 

[i] “PM launches Pradhan Mantri Sahaj Bijli Har Ghar Yojana “Saubhagya””, Press Information Bureau, Ministry of Power, September 25, 2017.

[ii] “FAQs on Pradhan Mantri Sahaj Bijli Har Ghar Yojana “Saubhagya””, Press Information Bureau, Ministry of Power, September 27, 2017.

[iii].  Rural Electrification Policy, Ministry of Power, August 23, 2006, http://powermin.nic.in/sites/default/files/uploads/RE%20Policy_1.pdf.

[iv].  “Office memorandum: Deendayal Upadhyaya Gram Jyoti Yojana”, Ministry of Power, December 3, 2014, http://powermin.nic.in/rural_electrification/pdf/Deendayal_Upadhyaya_Gram_Jyoti_Yojana.pdf.

[v].  “41st Report: Implementation of Rajiv Gandhi Grameen Vidyutikaran Yojana”, Standing Committee on Energy, December 13, 2013, http://164.100.47.134/lsscommittee/Energy/15_Energy_41.pdf.