In April 2020, the International Labour Organisation (ILO) estimated that nearly 2.5 crore jobs could be lost worldwide due to the COVID-19 pandemic in 2020.  Further, it observed that more than 40 crore informal workers in India may get pushed into deeper poverty due to the pandemic.  In this blog post, we discuss the effect of COVID-19 on unemployment in urban areas as per the quarterly Periodic Labour Force Survey (PLFS) report released last week, and highlight some of the measures taken by the central government with regard to unemployment.

Methodology for estimating unemployment in PLFS reports

The National Statistics Office (NSO) released its latest quarterly PLFS report for the October-December 2020 quarter.  The PLFS reports give estimates of labour force indicators including Labour Force Participation Rate (LFPR), Unemployment Rate, and distribution of workers across industries.  The reports are released on a quarterly as well as annual basis.  The quarterly reports cover only urban areas whereas the annual report covers both urban and rural areas.  The latest annual report is available for the July 2019-June 2020 period.

The quarterly PLFS reports provide estimates based on the Current Weekly Activity Status (CWS).  The CWS of a person is the activity status obtained during a reference period of seven days preceding the date of the survey.  As per CWS status, a person is considered as unemployed in a week if he did not work even for at least one hour on any day during the reference week but sought or was available for work.  In contrast, the headline numbers on employment-unemployment in the annual PLFS reports are reported based on the usual activity status.  Usual activity status relates to the activity status of a person during the reference period of the last 365 days preceding the date of the survey.

Unemployment rate remains notably higher than the pre-COVID period 

To contain the spread of COVID-19, a nationwide lockdown was imposed from late March till May 2020.   During the lockdown, severe restrictions were placed on the movement of individuals and economic activities were significantly halted barring the activities related to essential goods and services.  Unemployment rate in urban areas rose to 20.9% during the April-June quarter of 2020, more than double the unemployment rate in the same quarter the previous year (8.9%).  Unemployment rate refers to the percentage of unemployed persons in the labour force.  Labour force includes persons who are either employed or unemployed but seeking work.  The lockdown restrictions were gradually relaxed during the subsequent months.   Unemployment rate also saw a decrease as compared to the levels seen in the April-June quarter of 2020.  During the October-December quarter of 2020 (latest data available), unemployment rate had reduced to 10.3%.  However, it was notably higher than the unemployment rate in the same quarter last year (7.9%).

Figure 1: Unemployment rate in urban areas across all age groups as per current weekly activity status (Figures in %)

 image

Note: PLFS includes data for transgenders among males.
Sources: Quarterly Periodic Labour Force Survey Reports, Ministry of Statistics and Program Implementation; PRS.

Recovery post-national lockdown uneven in case of females

Pre-COVID-19 trends suggest that the female unemployment rate has generally been higher than the male unemployment rate in the country (7.3% vs 9.8% during the October-December quarter of 2019, respectively).  Since the onset of the COVID-19 pandemic, this gap seems to have widened.   During the October-December quarter of 2020, the unemployment rate for females was 13.1%, as compared to 9.5% for males.

The Standing Committee on Labour (April 2021) also noted that the pandemic led to large-scale unemployment for female workers, in both organised and unorganised sectors.  It recommended: (i) increasing government procurement from women-led enterprises, (ii) training women in new technologies, (iii) providing women with access to capital, and (iv) investing in childcare and linked infrastructure.

Labour force participation

Persons dropping in and out of the labour force may also influence the unemployment rate.  At a given point of time, there may be persons who are below the legal working age or may drop out of the labour force due to various socio-economic reasons, for instance, to pursue education.  At the same time, there may also be discouraged workers who, while willing and able to be employed, have ceased to seek work.  Labour Force Participation Rate (LFPR) is the indicator that denotes the percentage of the population which is part of the labour force.  The LFPR saw only marginal changes throughout 2019 and 2020.  During the April-June quarter (where COVID-19 restrictions were the most stringent), the LFPR was 35.9%, which was lower than same in the corresponding quarter in 2019 (36.2%).  Note that female LFPR in India is significantly lower than male LFPR (16.6% and 56.7%, respectively, in the October-December quarter of 2019).

Figure 2: LFPR in urban areas across all groups as per current weekly activity status (Figures in %)

image

Note: PLFS includes data for transgenders among males.
Sources: Quarterly Periodic Labour Force Survey Reports, Ministry of Statistics and Program Implementation; PRS.

Measures taken by the government for workers

The Standing Committee on Labour in its report released in August 2021 noted that 90% of workers in India are from the informal sector.  These workers include: (i) migrant workers, (ii) contract labourers, (iii) construction workers, and (iv) street vendors.  The Committee observed that these workers were worst impacted by the pandemic due to seasonality of employment and lack of employer-employee relationship in unorganised sectors.  The Committee recommended central and state governments to: (i) encourage entrepreneurial opportunities, (ii) attract investment in traditional manufacturing sectors and developing industrial clusters, (iii) strengthen social security measures, (iv) maintain a database of workers in the informal sector, and (v) promote vocational training.  It took note of the various steps taken by the central government to support workers and address the challenges and threats posed by the COVID-19 pandemic (applicable to urban areas): 

  • Under the Pradhan Mantri Garib Kalyan Yojana (PMGKY), the central government contributed both 12% employer’s share and 12% employee’s share under Employees Provident Fund (EPF).  Between March and August 2020, a total of Rs 2,567 crore was credited in EPF accounts of 38.85 lakhs eligible employees through 2.63 lakh establishments.
     
  • The Aatmanirbhar Bharat Rozgar Yojna (ABRY) Scheme was launched with effect from October 2020 to incentivise employers for the creation of new employment along with social security benefits and restoration of loss of employment during the COVID-19 pandemic.  Further, statutory provident fund contribution of both employers and employees was reduced to 10% each from the existing 12% for all establishments covered by EPF Organisation for three months.  As of June 30, 2021, an amount of Rs 950 crore has been disbursed under ABRY to around 22 lakh beneficiaries.
     
  • The unemployment benefit under the Atal Beemit Vyakti Kalyan Yojana (launched in July 2018) was enhanced from 25% to 50% of the average earning for insured workers who have lost employment due to COVID-19.
     
  • Under the Prime Minister’s Street Vendor’s Aatma Nirbhar Nidhi (PM SVANidhi) scheme, the central government provided an initial working capital of up to Rs 10,000 to street vendors.  As of June 28, 2021, 25 lakh loan applications have been sanctioned and Rs 2,130 crore disbursed to 21.57 lakh beneficiaries.

The central and state governments have also taken various other measures, such as increasing spending on infrastructure creation and enabling access to cheaper lending for businesses, to sustain economic activity and boost employment generation.

Recently, the central government launched the Pradhan Mantri Sahaj Bijli Har Ghar Yojana (or Saubhagya).[i],[ii]  The scheme seeks to ensure universal household electrification (in both rural and urban areas) by providing last mile connectivity.  The scheme is expected to cover three crore households.  Note that currently about four crore households are un-electrified.  A rural electrification scheme has also been under implementation since 2005.  In light of this, we discuss the current situation of, and key issues related to rural electrification in the country.

Regulatory and policy framework

Under the Electricity Act, 2003, the central and state governments have the joint responsibility of providing electricity to rural areas.  The 2003 Act also mandates that the central government should, in consultation with the state governments, provide for a national policy on (i) stand-alone power systems for rural areas (systems that are not connected to the electricity grid), and (ii) electrification and local distribution in rural areas.  Consequently, the Rural Electrification Policy was notified in August 2006.[iii]

The Rajiv Gandhi Grameen Vidyutikaran Yojana (RGGVY), launched in 2005, was the first scheme on rural electrification.  In December 2014, Ministry of Power launched the Deendayal Upadhyaya Gram Jyoti Yojana (DDUGJY), which subsumed the RGGVY.[iv]  Components of DDUGJY include: (i) separation of agricultural and non-agricultural electricity feeders to improve supply for consumers in rural areas, (ii) improving sub-transmission and distribution infrastructure in rural areas, and (iii) rural electrification by carrying forward targets specified under the RGGVY.

The total financial outlay for DDUGJY over the implementation period (until 2021-22) is Rs 82,300 crore which includes budgetary support of Rs 68,900 crore.  The central government provides 60% of the project cost as grant, the state power distribution companies (discoms) raise 10% of the funds, and 30% is borrowed from financial institutions and banks.

Status of rural electrification

As of August 2017, about 1% of the villages in India remain un-electrified (3,146 villages).  However, with regard to households, around 23% (4.1 crore households) are yet to be electrified.  Table 1 at the end of this post shows the status of rural electrification across all states.

Issues with rural electrification

Definition of an electrified village

An electrified village is defined as one that has the following: (i) provision of basic infrastructure such as distribution transformers and lines in the inhabited locality, (ii) provision of electricity in public places like schools, panchayat office, health centers, dispensaries, and community centers, and (iii) at least 10% of the total number of households in the village are electrified.[iv]

Therefore, a village is considered to be electrified if 10% of the total number of households in the village have been electrified.  This is apart from the basic infrastructure and electrification of certain public centers in the village.  The Standing Committee on Energy (2013) had observed that according to this definition, a village would be called electrified even if up to 90% of households in it do not have an electricity connection.[v]  It also noted that the infrastructure being provided under the scheme is highly inadequate, unreliable and unsustainable.  The Committee recommended that the actual electrification requirement of villages must be assessed, and it should be ensured that the state discoms provide electricity to the remaining households in the village.

Supply of electricity

The Standing Committee had also noted that while the rural electrification scheme looks at creating infrastructure, the actual supply of electricity to households rests with the state discoms.[v]  These discoms are already facing huge financial losses and hence are unable to supply electricity to the villages.  Discoms continue to supply subsidised power to agricultural and residential consumers, resulting in revenue losses.  Further, the average technical and commercial losses (theft and pilferage of electricity) (AT&C losses) are at around 25%.  While the Ujjwal Discom Assurance Yojana (UDAY) has eased off some of the financial losses of the discoms, it remains to be seen whether discoms are able to reduce the cost-tariff gap and AT&C losses in the future.

It has been recommended that generation capacity should be augmented so that states can meet the additional demand under the rural electrification schemes. Further, the assistance to financially weaker states should be increased so that they can better implement the scheme.[v]

Electricity to below poverty line (BPL) households

Under the rural electrification scheme, the cost for providing free electricity connection per BPL household is Rs 3,000.  It has been observed that this cost per household may be inadequate.[v]  Due to the low cost, the quantity and the quality of work has been getting compromised leading to poor implementation of the scheme.  It has been recommended that the Ministry should revisit the cost provided under the scheme.[v]

The new electrification scheme: Pradhan Mantri Sahaj Bijli Har Ghar Yojana (or Saubhagya)

The new scheme, Saubhagya, seeks to ensure universal household electrification, that is, in both rural and urban areas.  Under Saubhagya, beneficiaries will be identified using the Socio Economic and Caste Census (SECC) 2011 data.  The identified poor households will get free electricity connections.  Other households not covered under the SECC, will be provided electricity connections at a cost of Rs 500.  This amount will be collected by the electricity distribution companies in 10 instalments.

The total outlay of the scheme will be Rs 16,320 crore, of which the central government will provide Rs 12,320 crore.  The outlay for the rural households will be Rs 14,025 crore, of which the centre will provide Rs 10,588 crore.  For urban households the outlay will be Rs 2,295 crore of which the centre will provide Rs. 1,733 crore.

The state discoms will execute the electrification works through contractors or other suitable agencies.  Information technology (mobile apps, web portals) will be used to organise camps in villages to identify beneficiaries.  In order to accelerate the process, applications for electricity connections will be completed on the spot.

So far the focus of electrification schemes has been on rural areas, where typically last mile connectivity has been difficult to provide.  Saubhagya extends the ambit of electrification projects to urban areas as well.  While DDUGJY has focused on the village as the principal unit to measure electrification, the new scheme shifts the targets to household electrification.  While the target for ensuring electricity connection in each household will be a significant step towards ensuring 24×7 power, the question of continuous and quality supply to these households will still rest on the ability of the discoms to provide electricity.  Further, while the scheme provides for free connections, the ability of these households to pay for the electricity they consume may be a concern.

Table 1: Status of rural electrification across states (as of August 2017)

Fig 1 edit

* all villages in Telangana were declared electrified before the bifurcation of the state.
Sources:  Ministry of Power; PRS.

 

[i] “PM launches Pradhan Mantri Sahaj Bijli Har Ghar Yojana “Saubhagya””, Press Information Bureau, Ministry of Power, September 25, 2017.

[ii] “FAQs on Pradhan Mantri Sahaj Bijli Har Ghar Yojana “Saubhagya””, Press Information Bureau, Ministry of Power, September 27, 2017.

[iii].  Rural Electrification Policy, Ministry of Power, August 23, 2006, http://powermin.nic.in/sites/default/files/uploads/RE%20Policy_1.pdf.

[iv].  “Office memorandum: Deendayal Upadhyaya Gram Jyoti Yojana”, Ministry of Power, December 3, 2014, http://powermin.nic.in/rural_electrification/pdf/Deendayal_Upadhyaya_Gram_Jyoti_Yojana.pdf.

[v].  “41st Report: Implementation of Rajiv Gandhi Grameen Vidyutikaran Yojana”, Standing Committee on Energy, December 13, 2013, http://164.100.47.134/lsscommittee/Energy/15_Energy_41.pdf.