The central government has enforced a nation-wide lockdown between March 25 and May 3 as part of its measures to contain the spread of COVID-19. During the lockdown, several restrictions have been placed on the movement of individuals and economic activities have come to a halt barring the activities related to essential goods and services. The restrictions are being relaxed in less affected areas in a limited manner since April 20. In this blog, we look at how the lockdown has impacted the demand and supply of electricity and what possible repercussions its prolonged effect may have on the power sector.
Power supply saw a decrease of 25% during the lockdown (year-on-year)
As electricity cannot be stored in large amount, the power generation and supply for a given day are planned based on the forecast for demand. The months of January and February in 2020 had seen an increase of 3% and 7% in power supply, respectively as compared to 2019 (year-on-year). In comparison, the power supply saw a decrease of 3% between March 1 and March 24. During the lockdown between March 24 and April 19, the total power supply saw a decrease of about 25% (year-on-year).
Figure 1: % change in power supply position between March 1 and April 19 (Y-o-Y from 2019 to 2020)
Sources: Daily Reports; POSOCO; PRS.
If we look at the consumption pattern by consumer category, in 2018-19, 41% of total electricity consumption was for industrial purposes, followed by 25% for domestic and 18% for agricultural purposes. As the lockdown has severely reduced the industrial and commercial activities in the country, these segments would have seen a considerable decline in demand for electricity. However, note that the domestic demand may have seen an uptick as people are staying indoors.
Figure 2: Power consumption by consumer segment in 2018-19
Sources: Central Electricity Authority; PRS.
Electricity demand may continue to be subdued over the next few months. At this point, it is unclear that when lockdown restrictions are eased, how soon will economic activities return to pre COVID-19 levels. India’s growth projections also highlight a slowdown in the economy in 2020 which will further impact the demand for electricity. On April 16, the International Monetary Fund has slashed its projection for India’s GDP growth in 2020 from 5.8% to 1.9%.
A nominal increase in energy and peak deficit levels
As power sector related operations have been classified as essential services, the plant operations and availability of fuel (primarily coal) have not been significantly constrained. This can be observed with the energy deficit and peak deficit levels during the lockdown period which have remained at a nominal level. Energy deficit indicates the shortfall in energy supply against the demand during the day. The average energy deficit between March 25 and April 19 has been 0.42% while the corresponding figure was 0.33% between March 1 and March 24. Similarly, the average peak deficit between March 25 and April 19 has been 0.56% as compared to 0.41% between March 1 and March 24. Peak deficit indicates the shortfall in supply against demand during highest consumption period in a day.
Figure 3: Energy deficit and peak deficit between March 1, 2020 and April 19, 2020 (in %)
Sources: Daily Reports; POSOCO; PRS.
Coal stock with power plants increases
Coal is the primary source of power generation in the country (~71% in March 2020). During the lockdown period, the coal stock with coal power plants has seen an increase. As of April 19, total coal-stock with the power plants in the country (in days) has risen to 29 days as compared to 24 days on March 24. This indicates that the supply of coal has not been constrained during the lockdown, at least to the extent of meeting the requirements of power plants.
Energy mix changes during the lockdown, power generation from coal impacted
During the lockdown, power generation has been adjusted to compensate for reduced consumption, Most of this reduction in consumption has been adjusted by reduced coal power generation. As can be seen in Table 1, coal power generation reduced from an average of 2,511 MU between March 1 and March 24 to 1,873 MU between March 25 and April 19 (about 25%). As a result, the contribution of coal in total power generation reduced from an average of 72.5% to 65.6% between these two periods.
Table 1: Energy Mix during March 1-April 19, 2020
Sources: Daily Reports; POSOCO; PRS.
This shift may be happening due to various reasons including: (i) renewable energy sources (solar, wind, and small hydro) have MUST RUN status, i.e., the power generated by them has to be given the highest priority by distribution companies, and (ii) running cost of renewable power plants is lower as compared to thermal power plants.
This suggests that if growth in electricity demand were to remain weak, the adverse impact on the coal power plants could be more as compared to other power generation sources. This will also translate into weak demand for coal in the country as almost 87% of the domestic coal production is used by the power sector. Note that the plant load factor (PLF) of the thermal power plants has seen a considerable decline over the years, decreasing from 77.5% in 2009-10 to 56.4% in 2019-20. Low PLF implies that coal plants have been lying idle. Coal power plants require significant fixed costs, and they incur such costs even when the plant is lying idle. The declining capacity utilisation augmented by a weaker demand will undermine the financial viability of these plants further.
Figure 4: Power generation from coal between March 1, 2020 and April 19, 2020 (in MU)
Sources: Daily Reports; POSOCO; PRS.
Finances of the power sector to be severely impacted
Power distribution companies (discoms) buy power from generation companies and supply it to consumers. In India, most of the discoms are state-owned utilities. One of the key concerns in the Indian power sector has been the poor financial health of its discoms. The discoms have had high levels of debt and have been running losses. The debt problem was partly addressed under the UDAY scheme as state governments took over 75% of the debt of state-run discoms (around 2.1 lakh crore in two years 2015-16 and 2016-17). However, discoms have continued to register losses owing to underpricing of electricity tariff for some consumer segments, and other forms of technical and commercial losses. Outstanding dues of discoms towards power generation companies have also been increasing, indicating financial stress in some discoms. At the end of February 2020, the total outstanding dues of discoms to generation companies stood at Rs 92,602 crore.
Due to the lockdown and its further impact in the near term, the financial situation of discoms is likely to be aggravated. This will also impact other entities in the value chain including generation companies and their fuel suppliers. This may lead to reduced availability of working capital for these entities and an increase in the risk of NPAs in the sector. Note that, as of February 2020, the power sector has the largest share in the deployment of domestic bank credit among industries (Rs 5.4 lakh crore, 19.3% of total).
Following are some of the factors which have impacted the financial situation during the lockdown:
Reduced cross-subsidy: In most states, the electricity tariff for domestic and agriculture consumers is lower than the actual cost of supply. Along with the subsidy by the state governments, this gap in revenue is partly compensated by charging industrial and commercial consumers at a higher rate. Hence, industrial and commercial segments cross-subsidise the power consumption by domestic and agricultural consumers.
The lockdown has led to a halt on commercial and industrial activities while people are staying indoors. This has led to a situation where the demand from the consumer segments who cross-subsidise has decreased while the demand from consumer segments who are cross-subsidised has increased. Due to this, the gap between revenue realised by discoms and cost of supply will widen, leading to further losses for discoms. States may choose to bridge this gap by providing a higher subsidy.
Moratorium to consumers: To mitigate the financial hardship of citizens due to COVID-19, some states such as Rajasthan, Uttar Pradesh, and Goa, among others, have provided consumers with a moratorium for payment of electricity bills. At the same time, the discoms are required to continue supplying electricity. This will mean that the return for the supply made in March and April will be delayed, leading to lesser cash in hand for discoms.
Some state governments such as Bihar also announced a reduction in tariff for domestic and agricultural consumers. Although, the reduction in tariff will be compensated to discoms by government subsidy.
Constraints with government finances: The revenue collection of states has been severely impacted as economic activities have come to a halt. Further, the state governments are directing their resources for funding relief measures such as food distribution, direct cash transfers, and healthcare. This may adversely affect or delay the subsidy transfer to discoms.
The UDAY scheme also requires states to progressively fund greater share in losses of discoms from their budgetary resources (10% in 2018-19, 25% in 2019-20, and 50% in 2020-21). As losses of discoms may widen due to the above-mentioned factors, the state government’s financial burden is likely to increase.
Capacity addition may be adversely impacted
As per the National Electricity Plan, India’s total capacity addition target is around 176 GW for 2017-2022. This comprises of 118 GW from renewable sources, 6.8 GW from hydro sources, and 6.4 GW from coal (apart from 47.8 GW of coal-based power projects already in various stages of production as of January 2018).
India has set a goal of installing 175 GW of Renewable Power Capacity by 2022 as part of its climate change commitments (86 GW has been installed as of January 2020). In January 2020, the Parliamentary Standing Committee on Energy observed that India could only install 82% and 55% of its annual renewable energy capacity addition targets in 2017-18 and 2018-19. As of January 2020, 67% of the target has been achieved for 2019-20.
Due to the impact of COVID-19, the capacity addition targets for various sources is likely to be adversely impacted in the short run as:
construction activities were stopped during the lockdown and will take some time to return to normal,
disruption in the global supply chain may lead to difficulties with the availability of key components leading to delay in execution of projects, for instance, for solar power plants, solar PV modules are mainly imported from China, and
reduced revenue for companies due to weak demand will leave companies with less capacity left for capital expenditure.
Key reforms likely to be delayed
Following are some of the important reforms anticipated in 2020-21 which may get delayed due to the developing situation:
The real-time market for electricity: The real-time market for electricity was to be operationalised from April 1, 2020. However, the lockdown has led to delay in completion of testing and trial runs. The revised date for implementation is now June 1, 2020.
UDAY 2.0/ADITYA: A new scheme for the financial turnaround of discoms was likely to come this year. The scheme would have provided for the installation of smart meters and incentives for rationalisation of the tariff, among other things. It remains to be seen what this scheme would be like since the situation with government finances is also going to worsen due to anticipated economic slowdown.
Auction of coal blocks for commercial mining: The Coal Ministry has been considering auction of coal mines for commercial mining this year. 100% FDI has been allowed in the coal mining activity for commercial sale of coal to attract foreign players. However, the global economic slowdown may mean that the auctions may not generate enough interest from foreign as well as domestic players.
For a detailed analysis of the Indian Power Sector, please see here. For details on the number of daily COVID-19 cases in the country and across states, please see here. For details on the major COVID-19 related notifications released by the centre and the states, please see here.
Recently, there have been multiple Naxal attacks on CRPF personnel in Chhattisgarh. Parliamentary Committees have previously examined the working of the Central Armed Police Forces (CAPFs). In this context, we examine issues related to functioning of these Forces and recommendations made to address them.
What is the role of the Central Armed Police Forces (CAPFs)?
Under the Constitution, police and public order are state subjects. However, the Ministry of Home Affairs (MHA) assists state governments by providing them support of the Central Armed Police Forces. The Ministry maintains seven CAPFs: (i) the Central Reserve Police Force, which assists in internal security and counterinsurgency, (ii) the Central Industrial Security Force, which protects vital installations (like airports) and public sector undertakings, (iii) the National Security Guards, which is a special counterterrorism force, and (iv) four border guarding forces, which are the Border Security Force, Indo-Tibetan Border Police, Sashastra Seema Bal, and Assam Rifles.
What is the sanctioned strength of CAPFs personnel compared to the actual strength?
As of January 2017, the sanctioned strength of the seven CAPFs was 10,78,514 personnel. However, 15% of these posts (1,58,591 posts) were lying vacant. Data from the Bureau of Police Research and Development shows that vacancies in the CAPFs have remained over the years. Table 1 shows the level of vacancies in the seven CAPFs between 2012 and 2017. The level of vacancies is different for various police forces. For example, in 2017, the Sashastra Seema Bal had the highest level of vacancies at 57%. On the other hand, the Border Security Force had 2% vacancies. The Central Reserve Police Force, which account for 30% of the sanctioned strength of the seven CAPFs, had a vacancy of 8%.
How often are CAPFs deployed?
According to the Estimates Committee of Parliament, the number of deployment of CAPFs battalions has increased from 91 in 2012-13 to 119 in 2016-17. The Committee has noted that there has been heavy dependence by states on central police forces even for day-to-day law and order issues. This is likely to affect anti-insurgency and border-guarding operations of the Forces, as well as curtail their time for training. The continuous deployment also leaves less time for rest and recuperation.
The Estimates Committee recommended that states must develop their own systems, and augment their police forces by providing adequate training and equipment. It further recommended that the central government should supplement the efforts of state governments by providing financial assistance and other help for capacity building of their forces.
What is the financial allocation to CAPFs?
Under the Union Budget 2018-19, an allocation of Rs 62,741 crore was made to the seven CAPFs. Of this, 32% (Rs 20,268 crore) has been allocated to the Central Reserve Police Forces. The Estimates Committee has pointed out that most of the expenditure of the CAPFs was on salaries. According to the Committee, the financial performance in case of outlays allocated for capacity augmentation has been very poor. For example, under the Modernization Plan-II, Rs 11,009 crore was approved for the period 2012-17. However, the allocation during the period 2013-16 was Rs 251 crore and the reported expenditure was Rs 198 crore.
What are the working conditions for CAPFs personnel?
The Standing Committee on Home Affairs in the year 2017 had expressed concern over the working conditions of personnel of the border guarding forces (Border Security Force, Assam Rifles, Indo-Tibetan Border Police, and Sashastra Seema Bal). The Committee observed that they had to work 16-18 hours a day, with little time for rest or sleep. The personnel were also not satisfied with medical facilities that had been provided at border locations.
In addition, the Standing Committee observed that personnel of the CAPFs have not been treated at par with the Armed Forces, in terms of pay and allowances. The demand for Paramilitary Service Pay, similar to Military Service Pay, had not been agreed to by the Seventh Central Pay Commission. Further, the Committee observed that the hard-area allowance for personnel of the border guarding forces was much lower as compared to members of the Armed Forces, despite being posted in areas with difficult terrain and harsh weather.
What is the status of training facilities and infrastructure available to CAPFs?
The Estimates Committee has noted that all CAPFs have set up training institutions to meet their training requirements and impart professional skills on specialised topics. However, the Committee noted that there is an urgent need to upgrade the curriculum and infrastructure in these training institutes. It recommended that while purchasing the latest equipment, training needs should also be taken care of, and if required, should be included in the purchase agreement itself. Further, it recommended that the contents of training should be a mix of conventional matters as well as latest technologies such as IT, and cyber security.
According to the Estimates Committee, the MHA has been making efforts to provide modern arms, ammunition, and vehicles to the CAPFs. In this regard, the Modernization Plan-II, for the period 2012-17, was approved by the Cabinet Committee on Security. The Plan aims to provide financial support to CAPFs for modernisation in areas of arms, clothing, and equipment.
However, the Committee observed that the procurement process under the Plan was cumbersome and time consuming. It recommended that the bottlenecks in procurement should be identified and corrective action should be taken. It further suggested that the MHA and CAPFs should hold negotiations with ordnance factories and manufacturers in the public or private sector, to ensure an uninterrupted supply of equipment and other infrastructure.