By Rohit & Anirudh A modified 'Modernization of State Police Forces' scheme was started by the central government in 2000-01. One of the objectives was to help police forces in meeting the emerging challenges to internal security in the form of terrorism, naxalism etc. The scheme aims to modernize police forces in terms of:

  • Mobility (including purchase of bullet proof and mine proof vehicles)
  • Weaponry
  • Communication Systems
  • Training
  • Forensic Science Laboratory/ Finger Printing Bureau
  • Equipments
  • Buildings

Under this scheme, States have been clubbed into different categories and Centre-State cost sharing is category specific. Since 2005-06, States have been categorized as category ‘A’ and ‘B’ with 100% and 75% Central funding respectively. All the North Eastern States, namely Arunachal Pradesh, Assam, Manipur, Meghalaya, Mizoram, Nagaland, Tripura and Sikkim have been placed in category ‘A’ and thus, are entitled to receive 100% Central assistance for implementation of their annual approved plans. Recently, CAG decided to evaluate the working of the scheme and commissioned ‘performance audit’ reviews covering select general category and special category States. Each review covers a contiguous five year period between 2000 and 2007, but varies across selected states. For the periods under review, each state had a plan outlay (the total amount proposed to be spent in modernizing the state's police forces). However, in most cases, the actual release of funds fell significantly short of this outlay - in some cases the Centre did not contribute its share, in others the States lagged behind. For instance, in the case of Bihar, the Centre released only 56% of its share; while in the case of Rajasthan and West Bengal, the States did not release any funds at all. The graph below shows the actual releases by the Centre and the States (as percentages of their share in the proposed outlays): Further, even the funds that were released were not fully utilized. Thus, the amount finally spent fell significantly short of the initial proposal. The graph below shows the actual expenditure by State: Following are some of the other main findings from the CAG report:

Table 1: Summary of main findings in the CAG audit for different states for Modernisation of State Police Forces

Purpose for which money was sanctioned

Summary of CAG Findings

Planning

(Every state has to propose an Annual Action Plan every year. The plan is approved by the Ministry of Home Affairs and money is released as per the plan.)

§ Submissions by the states to the MHA were delayed.

§ There were also delays in the clearance granted by the MHA.

§ In various states such as,

a) Andhra Pradesh – the government spent money on works not covered by the Annual Action Plan.

b) Bihar – Persistent delays in preparation of the Plan by the state police.

c) West Bengal – the plans drawn up by the state did not include items covered under the scheme.

Mobility

§ Overall shortage of vehicles was observed. Most of the new vehicles replaced the old ones.

§ The police response time was too long in some states.

§ To give examples from some states:

a) Andhra Pradesh – 58 percent of vehicles procured were utilised for replacing old vehicles.

b) Bihar – the shortage of vehicles was 43 percent.

c) Uttar Pradesh – 2400 vehicles were procured against a shortage of nearly 10,000 vehicles.

Residential and non-residential buildings

§ There were considerable delays in construction of buildings in most states. Consequently, police forces’ own security was in jeopardy.

§ In states such as:

a) Andhra Pradesh – 53 percent of staff quarters and 43 percent of official buildings were not completed (2007).

b) Bihar – The total requirement of housing was nearly 60,000. Only six percent of this were included in the Plan.

c) Jharkhand – District Control rooms remained non-functional because of shortage of manpower.

Weapons

§ Police force in states continue to depend on outdated weapons.

§ Shortages of weapons also happened as acquisition from ordnance factories was very slow.

§ The weapons that were procured were mostly kept in the district headquarters.

§ In some states such as,

a) Bihar – AK-47s were kept at the disposal of bodyguards of VIPs.

b) West Bengal – Adequate weapons were not supplied to extremist prone police stations.

Communication

§ Police Telecommunication Networks were not set up successfully in some states. In others, network was functional only up to the district level.

§ Shortages of various communication equipments were also observed.

§ In some states such as,

a) Bihar - The Police Telecommunication Network system (costing Rs. 4.96 crore) remained non-functional due to non-construction of tower.

b) Maharashtra – Of the 850 purchased Remote Station Units, 452 were lying in stores.

Forensic Science Laboratory/ Finger Printing Bureau

§ In most States the Forensic Science Laboratories lacked adequate infrastructure.

§ In the absence of automatic finger print identification systems, investigation was being done manually in some States.

§ In some states such as,

a) Maharashtra - There were significant delays in receipt and installation. There was also shortage (284 vacant posts) of technical manpower.

b) West Bengal - Performance of the Forensic Science Laboratory was poor and in some cases, the delay in issue of investigation reports was as high as 45 months.

Training

§ It was observed that the percentage of police personnel trained was very low.

§ Training infrastructure was also inadequate.

§ In some states such as,

a) Bihar - Only 10 per cent of total force was trained.

b) West Bengal - Live training was not imparted for handling useful weapons and this severely affected the performance of police forces.

Sources: CAG Compendium of Performance Audit Reviews on Modernisation of Police Force; PRS.

Note: The audit has been done broadly from 2000 to 2007. Consequently, the period of audit for different states may vary.

Table 1: Summary of main findings in the CAG audit for different states for Modernisation of State Police Forces

Purpose for which money was sanctioned

Summary of CAG Findings

Planning

(Every state has to propose an Annual Action Plan every year. The plan is approved by the Ministry of Home Affairs and money is released as per the plan.)

§ Submissions by the states to the Ministry of Home Affairs (MHA) were delayed.

§ There were also delays in the clearance granted by the MHA.

§ In various states such as,

a) Andhra Pradesh – the government spent Rs 32 crore on works not covered by the Annual Action Plan.

b) Bihar – Persistent delays in preparation of the Plan by the state police.

c) West Bengal – the plans drawn up by the state did not include items covered under the scheme.

Mobility

§ Overall shortage of vehicles was observed. Most of the new vehicles replaced the old ones, and no additions were made.

§ The police response time was too long in some states.

§ To give examples from some states:

a) Andhra Pradesh – 58 percent of vehicles procured were utilised for replacing old vehicles.

b) Bihar – the shortage of vehicles was 43 percent.

c) Uttar Pradesh – 2400 vehicles were procured against a shortage of nearly 10,000 vehicles. 203 ambassador cars were procured, though only 55 were approved by the MHA.

Residential and non-residential buildings

§ There were considerable delays in construction of buildings in most states. Consequently, police forces’ own security was in jeopardy. Satisfaction levels with the housing provided were also very low.

§ In states such as:

a) Andhra Pradesh – 53 percent of staff quarters and 43 percent of official buildings were not completed (2007).

b) Bihar – The total requirement of housing was nearly 60,000. Only six percent of this were included in the Plan, and only 1045 units were completed by 2006.

c) Jharkhand – District Control rooms remained non-functional even after spending Rs 2 crore because of shortage of manpower.

Weapons

§ It was observed that the police force in states continue to depend on outdated weapons.

§ Shortages of weapons also happened as acquisition from ordnance factories was very slow.

§ The weapons that were procured were mostly kept in the district headquarters.

§ In some states such as,

a) Bihar – AK-47s were kept at the disposal of bodyguards of VIPs.

b) West Bengal – Adequate weapons were not supplied to extremist prone police stations.

Communication

§ Police Telecommunication Networks were not set up successfully in some states. In others, network was functional only up to the district level.

§ Shortages of various communication equipments were also observed.

§ In some states such as,

a) Bihar - The Police Telecommunication Network system (costing Rs. 4.96 crore) remained non-functional due to non-construction of tower.

b) Maharashtra – Of the 850 purchased Remote Station Units, 452 were lying in stores.

Forensic Science Laboratory/ Finger Printing Bureau

§ In most States the Forensic Science Laboratories lacked adequate infrastructure.

§ In the absence of automatic finger print identification systems, investigation was being done manually in some States.

§ In some states such as,

a) Maharashtra - There were significant delays in receipt and installation. There was also shortage (284 vacant posts) of technical manpower.

b) West Bengal - Performance of the Forensic Science Laboratory was poor and in some cases, the delay in issue of investigation reports was as high as 45 months.

Training

§ It was observed that the percentage of police personnel trained was very low.

§ Training infrastructure was also inadequate.

§ In some states such as,

a) Bihar - Only 10 per cent of total force was trained.

b) West Bengal - Live training was not imparted for handling useful weapons and this severely affected the performance of police forces.

Sources: CAG Compendium of Performance Audit Reviews on Modernisation of Police Force; PRS.

Note: The audit has been done broadly from 2000 to 2007. Consequently, the period of audit for different states may vary.

Last week, oil-marketing companies (or OMCs, such as Indian Oil Corporation Limited and Hindustan Petroleum Corporation Limited) raised the price of domestic LPG in the country. [1]  The price of a domestic cylinder (14.2kg) has increased from Rs 714 in January 2020 to Rs 858.5 in February 2020.  This is a 20% hike in the price of a LPG cylinder.  Note that this is the sixth consecutive month for which LPG prices have been revised upwards.  Figure 1 shows the variation in price of a domestic (non-subsidised) LPG cylinder in Delhi over the last year.

Figure 1: Variation in price of non-subsidised domestic LPG cylinder

 

Sources:  Indian Oil and Corporation Limited; PRS.

How is the price of LPG cylinders determined?

LPG prices are revised every month.  The price is determined by public sector OMCs namely, Indian Oil Corporation Limited, Hindustan Petroleum Corporation Limited and Bharat Petroleum Corporation Limited, in line with the changes in the international market prices and other market conditions. [2]  The international market price affects the import parity price of petroleum products (the price that importers pay for import of product at the respective Indian ports).  This includes exchange rate, ocean freight, insurance and customs duty among others.

The Ministry of Petroleum and Natural Gas has stated that the recent hike in the price of LPG cylinder is due to a sharp rise in international LPG prices during January 2020 (from USD 448/Metric Tonne to USD 567/Metric Tonne). [3] 

What is the difference between the price of a subsidised and non-subsidised cylinder?

The price determined by the OMCs reflects the price of a non-subsidised domestic LPG cylinder.  The government modulates the effective price to provide subsidised LPG cylinders to consumers under the 'Pratyaksha Hastaantarit Laabh' direct benefit transfer (or DBT-PAHAL) scheme. [4]   Under the scheme, a consumer (with annual income of up to Rs 10 lakh) can avail DBT cash-subsidy for a LPG cylinder.   The beneficiaries buy LPG cylinders at market rate and subsequently receive subsidy directly in their bank accounts.  

With the recent increase in price of a LPG cylinder, the government has increased the subsidy amount for PAHAL consumers from Rs. 153.86 per cylinder to Rs. 291.48 per cylinder (89% increase).3   This is done to ensure that the subsidized LPG consumers are insulated from the volatility of LPG prices in the international market.  Table 1 shows the amount of subsidy provided by the government for LPG cylinder.  Note that price of a subsidised cylinder has increased from Rs 494 to Rs 567 (14.8%) from February 2019 to February 2020. 

Table 1: Difference between the price of subsidised and non-subsidised LPG cylinder

As on

Non-subsidised cylinder

Subsidised cylinder

Subsidy

February 2018

Rs 736.00

Rs 495.63

Rs 240.37

February 2019

Rs 659.00

Rs 493.53

Rs 165.47

February 2020

Rs 858.50

Rs 567.02

Rs 291.48

Sources: Unstarred Question No.1211, February 13, 2019, Ministry of Petroleum and Natural Gas, Rajya Sabha.
 Note: Prices are at Delhi. 

How many people avail the subsidy on LPG cylinders?

Currently, there are a total of 27.16 crore LPG (domestic) connections in the country.3  Of these, 26.12 crore (94%) consumers are beneficiaries under the PAHAL scheme, and therefore, can avail LPG cylinders at subsidised rates.  Note that, under the scheme, a maximum of 12 subsidised cylinders per year can be availed under one connection.  Further, a household cannot have more than one connection. 

What is the cost of subsidy for the government?

The subsidy on domestic LPG is met through the budgetary grants of the Ministry of Petroleum and Natural Gas.  In 2020-21, the government is estimated to spend Rs 37,256 crore on LPG subsidy.   This includes Rs 35,605 crore for DBT-PAHAL and Rs 1,118 crore for Pradhan Mantri Ujjwala Yojana.  This is an increase of 9.3% from the expenditure in 2019-20 of Rs 34,086 crore (revised estimate).  Note that LPG subsidy constitutes 87% of the Ministry's total budget (Rs 42,901 crore).   

Figure 2 below shows the year-wise expenditure on LPG subsidy, and as a proportion of the total budget of the Ministry from 2015-16 to 2020-21. 

Figure 2: LPG subsidy over the years (2015-16 to 2020-21). 

Sources: Union Budget Documents; PRS.

For more trends and analysis related to the finances of the Ministry of Petroleum and Natural Gas, see  here

[1] "LPG price hiked by Rs 144.5 per cylinder", Economic Times, February 12, 2020,  https://economictimes.indiatimes.com/industry/energy/oil-gas/lpg-price-hiked-by-rs-144-5-per-cylinder/articleshow/74096745.cms.

[2] Frequently Asked Questions (FAQ), Petroleum Planning and Analysis Cell,  https://www.ppac.gov.in/content/137_3_Faq.aspx.

[3] "LPG Price is Derived based on International Market Price", Press Information Bureau, Ministry of Petroleum and Natural Gas, February 13, 2020. 

[4] PAHAL-Direct Benefits Transfer for LPG (DBTL) Consumers Scheme, Ministry of Petroleum and Natural Gas,  http://petroleum.nic.in/dbt/whatisdbtl.html.