Applications for the LAMP Fellowship 2025-26 will open on December 1, 2024. Sign up here to be notified when applications open.

By Rohit & Anirudh A modified 'Modernization of State Police Forces' scheme was started by the central government in 2000-01. One of the objectives was to help police forces in meeting the emerging challenges to internal security in the form of terrorism, naxalism etc. The scheme aims to modernize police forces in terms of:

  • Mobility (including purchase of bullet proof and mine proof vehicles)
  • Weaponry
  • Communication Systems
  • Training
  • Forensic Science Laboratory/ Finger Printing Bureau
  • Equipments
  • Buildings

Under this scheme, States have been clubbed into different categories and Centre-State cost sharing is category specific. Since 2005-06, States have been categorized as category ‘A’ and ‘B’ with 100% and 75% Central funding respectively. All the North Eastern States, namely Arunachal Pradesh, Assam, Manipur, Meghalaya, Mizoram, Nagaland, Tripura and Sikkim have been placed in category ‘A’ and thus, are entitled to receive 100% Central assistance for implementation of their annual approved plans. Recently, CAG decided to evaluate the working of the scheme and commissioned ‘performance audit’ reviews covering select general category and special category States. Each review covers a contiguous five year period between 2000 and 2007, but varies across selected states. For the periods under review, each state had a plan outlay (the total amount proposed to be spent in modernizing the state's police forces). However, in most cases, the actual release of funds fell significantly short of this outlay - in some cases the Centre did not contribute its share, in others the States lagged behind. For instance, in the case of Bihar, the Centre released only 56% of its share; while in the case of Rajasthan and West Bengal, the States did not release any funds at all. The graph below shows the actual releases by the Centre and the States (as percentages of their share in the proposed outlays): Further, even the funds that were released were not fully utilized. Thus, the amount finally spent fell significantly short of the initial proposal. The graph below shows the actual expenditure by State: Following are some of the other main findings from the CAG report:

Table 1: Summary of main findings in the CAG audit for different states for Modernisation of State Police Forces

Purpose for which money was sanctioned

Summary of CAG Findings

Planning

(Every state has to propose an Annual Action Plan every year. The plan is approved by the Ministry of Home Affairs and money is released as per the plan.)

§ Submissions by the states to the MHA were delayed.

§ There were also delays in the clearance granted by the MHA.

§ In various states such as,

a) Andhra Pradesh – the government spent money on works not covered by the Annual Action Plan.

b) Bihar – Persistent delays in preparation of the Plan by the state police.

c) West Bengal – the plans drawn up by the state did not include items covered under the scheme.

Mobility

§ Overall shortage of vehicles was observed. Most of the new vehicles replaced the old ones.

§ The police response time was too long in some states.

§ To give examples from some states:

a) Andhra Pradesh – 58 percent of vehicles procured were utilised for replacing old vehicles.

b) Bihar – the shortage of vehicles was 43 percent.

c) Uttar Pradesh – 2400 vehicles were procured against a shortage of nearly 10,000 vehicles.

Residential and non-residential buildings

§ There were considerable delays in construction of buildings in most states. Consequently, police forces’ own security was in jeopardy.

§ In states such as:

a) Andhra Pradesh – 53 percent of staff quarters and 43 percent of official buildings were not completed (2007).

b) Bihar – The total requirement of housing was nearly 60,000. Only six percent of this were included in the Plan.

c) Jharkhand – District Control rooms remained non-functional because of shortage of manpower.

Weapons

§ Police force in states continue to depend on outdated weapons.

§ Shortages of weapons also happened as acquisition from ordnance factories was very slow.

§ The weapons that were procured were mostly kept in the district headquarters.

§ In some states such as,

a) Bihar – AK-47s were kept at the disposal of bodyguards of VIPs.

b) West Bengal – Adequate weapons were not supplied to extremist prone police stations.

Communication

§ Police Telecommunication Networks were not set up successfully in some states. In others, network was functional only up to the district level.

§ Shortages of various communication equipments were also observed.

§ In some states such as,

a) Bihar - The Police Telecommunication Network system (costing Rs. 4.96 crore) remained non-functional due to non-construction of tower.

b) Maharashtra – Of the 850 purchased Remote Station Units, 452 were lying in stores.

Forensic Science Laboratory/ Finger Printing Bureau

§ In most States the Forensic Science Laboratories lacked adequate infrastructure.

§ In the absence of automatic finger print identification systems, investigation was being done manually in some States.

§ In some states such as,

a) Maharashtra - There were significant delays in receipt and installation. There was also shortage (284 vacant posts) of technical manpower.

b) West Bengal - Performance of the Forensic Science Laboratory was poor and in some cases, the delay in issue of investigation reports was as high as 45 months.

Training

§ It was observed that the percentage of police personnel trained was very low.

§ Training infrastructure was also inadequate.

§ In some states such as,

a) Bihar - Only 10 per cent of total force was trained.

b) West Bengal - Live training was not imparted for handling useful weapons and this severely affected the performance of police forces.

Sources: CAG Compendium of Performance Audit Reviews on Modernisation of Police Force; PRS.

Note: The audit has been done broadly from 2000 to 2007. Consequently, the period of audit for different states may vary.

Table 1: Summary of main findings in the CAG audit for different states for Modernisation of State Police Forces

Purpose for which money was sanctioned

Summary of CAG Findings

Planning

(Every state has to propose an Annual Action Plan every year. The plan is approved by the Ministry of Home Affairs and money is released as per the plan.)

§ Submissions by the states to the Ministry of Home Affairs (MHA) were delayed.

§ There were also delays in the clearance granted by the MHA.

§ In various states such as,

a) Andhra Pradesh – the government spent Rs 32 crore on works not covered by the Annual Action Plan.

b) Bihar – Persistent delays in preparation of the Plan by the state police.

c) West Bengal – the plans drawn up by the state did not include items covered under the scheme.

Mobility

§ Overall shortage of vehicles was observed. Most of the new vehicles replaced the old ones, and no additions were made.

§ The police response time was too long in some states.

§ To give examples from some states:

a) Andhra Pradesh – 58 percent of vehicles procured were utilised for replacing old vehicles.

b) Bihar – the shortage of vehicles was 43 percent.

c) Uttar Pradesh – 2400 vehicles were procured against a shortage of nearly 10,000 vehicles. 203 ambassador cars were procured, though only 55 were approved by the MHA.

Residential and non-residential buildings

§ There were considerable delays in construction of buildings in most states. Consequently, police forces’ own security was in jeopardy. Satisfaction levels with the housing provided were also very low.

§ In states such as:

a) Andhra Pradesh – 53 percent of staff quarters and 43 percent of official buildings were not completed (2007).

b) Bihar – The total requirement of housing was nearly 60,000. Only six percent of this were included in the Plan, and only 1045 units were completed by 2006.

c) Jharkhand – District Control rooms remained non-functional even after spending Rs 2 crore because of shortage of manpower.

Weapons

§ It was observed that the police force in states continue to depend on outdated weapons.

§ Shortages of weapons also happened as acquisition from ordnance factories was very slow.

§ The weapons that were procured were mostly kept in the district headquarters.

§ In some states such as,

a) Bihar – AK-47s were kept at the disposal of bodyguards of VIPs.

b) West Bengal – Adequate weapons were not supplied to extremist prone police stations.

Communication

§ Police Telecommunication Networks were not set up successfully in some states. In others, network was functional only up to the district level.

§ Shortages of various communication equipments were also observed.

§ In some states such as,

a) Bihar - The Police Telecommunication Network system (costing Rs. 4.96 crore) remained non-functional due to non-construction of tower.

b) Maharashtra – Of the 850 purchased Remote Station Units, 452 were lying in stores.

Forensic Science Laboratory/ Finger Printing Bureau

§ In most States the Forensic Science Laboratories lacked adequate infrastructure.

§ In the absence of automatic finger print identification systems, investigation was being done manually in some States.

§ In some states such as,

a) Maharashtra - There were significant delays in receipt and installation. There was also shortage (284 vacant posts) of technical manpower.

b) West Bengal - Performance of the Forensic Science Laboratory was poor and in some cases, the delay in issue of investigation reports was as high as 45 months.

Training

§ It was observed that the percentage of police personnel trained was very low.

§ Training infrastructure was also inadequate.

§ In some states such as,

a) Bihar - Only 10 per cent of total force was trained.

b) West Bengal - Live training was not imparted for handling useful weapons and this severely affected the performance of police forces.

Sources: CAG Compendium of Performance Audit Reviews on Modernisation of Police Force; PRS.

Note: The audit has been done broadly from 2000 to 2007. Consequently, the period of audit for different states may vary.

On January 17, 2020, the Ministry of Health and Family Welfare acknowledged the emergence of COVID-19 that was spreading across China. On January 30, 2020, the country’s first COVID-19 positive case was reported in Kerala.  By March 11, 2020, the World Health Organisation declared COVID-19 as a global pandemic.  This blog summarises the key policy measures taken by government of Kerala to respond to the pandemic.  

As on April 22, Kerala has had 427 confirmed cases of COVID-19, of which 307 have recovered (highest rate of recovery in the country). Only three deaths have been recorded in the state so far.

 image

Pre-lockdown period: Early measures for containment

Following the first confirmed case involving a returnee from Wuhan, China, the initial responses by the state were aimed at surveilling, identifying, and conducting risk-based categorisation of all passenger arrivals from China and others who had come in close contact with these travellers. As two more cases were confirmed on February 2 and 3, the state government declared a health emergency in the state. 

Subsequently, a health advisory was issued to track, identify, and test all travellers with a travel history to Wuhan since January 15, 2020.  Such passengers and their close contacts were to be kept in isolation for 28 days.  The advisory also directed all lodging establishments to maintain a register of travellers with travel histories to corona-affected countries. A similar advisory was issued for student returnees as well. With no further confirmed cases being reported immediately, on February 12, the state withdrew the health emergency.  However, a high state of response and surveillance continued to be applied.

Second wave of infections

When a second wave of infections began spreading in early March, the government took several multi-pronged measures to address the threat. The following measures were taken in this regard:

  • Health measures: Revised guidelines for the clinical management of COVID19 patients, covering testing, quarantine, hospital admission, and discharge, were issued.  
     
  • Instructions were issued regarding airport safety protocols as well as testing of foreign nationals entering and exiting the state. All foreign arrivals, even if asymptomatic, were to be kept in isolation until their test reports were available. 
     
  • Further guidelines and precautions on social distancing and various hygiene norms, such as, use of sanitsers, were also issued to malls, shopping centres, and salons
     
  • Movement restrictions: All non-medical educational institutions, including anganwadis and madrassas were immediately shut down till March 31 and exams of classes 1-7 were postponed. Exams for classes 8 and above were to be held as scheduled. University exams were also postponed till March 31.
     
  • Government departments were asked to make temporary arrangements regarding working hours of their employees. Officials were also instructed to look into welfare measures for migrant workers.
     
  • Guidelines were also issued to private establishments regarding working time, safety measures, and leave for employees.
     
  • Administrative Measures: On March 17, COVID19 was declared a notified disaster, thus becoming eligible for funds from the State Disaster Response Fund (SDRF). SDRF is the primary fund available with state governments for responses to notified disasters. Notifying a disaster enables states to spend more from the SDRF to fight the said disaster.
     
  • In order to better coordinate the state’s response, the government issued instructions to constitute COVID-19 cells in all departments. Meetings and inspections by government officials were also to be avoided. 
     
  • Local Self Government institutions were assigned various roles and responsibilities. These include: (i) running awareness programs, such as, ‘Break the Chain’ initiative, (ii) conducting sanitation and cleanliness drives, (iii) regular outreach to home isolated/quarantined persons, (iv) activating committee system to manage responsibilities, (v) ensuring availability of essential commodities, (vi) categorising and ensuring available response mechanisms, such as, material resources, volunteers, medical resources etc, and (vii) ensuring special attention to vulnerable populations, such as senior citizens, and persons with co-morbidities or undergoing special treatments. 

The lockdown period

On March 23, Kerala announced a state-wide lockdown till March 31.  A day later, the central government announced a nation-wide 21-day lockdown.  

Restrictions imposed under the state’s order included: (i) stoppage of all forms of passenger transport services, (ii) prohibition of a gathering of more than five persons, and (iii) closure of all commercial establishments, officers, and factories, except those exempted.  Use of taxis, autos or private vehicles was permitted only for procurement of essential commodities or for medical emergencies. Establishments providing essential goods and services such as banks, media, telecom services, petrol bunks, and hospitals were permitted to operate.  

On April 15, the central government extended the lockdown till May 3.  Some of the key measures undertaken during the lockdown period are: 

Administrative Measures

  • A round-the-clock war room, comprising members of different departments, was set up to monitor and supervise all COVID-19 containment activities. 
     
  • Corona media cell was set up to monitor and tackle the threat of fake news surrounding COVID19.  
     
  • With the legislature not in session, the Kerala Epidemic Diseases Ordinance, 2020 was promulgated by the Governor of Kerala on March 26. The Ordinance empowers the state government to undertake necessary measures and specify regulations to counter the threat of an epidemic disease.  It also specifies a penalty for those who violate orders made under this Ordinance. 

Healthcare Measures

Essential Goods and Services

  • On March 25, the state declared a list of essential services under the Kerala Essential Services Maintenance Act, 1994. 
     
  • Various exemptions from lockdown were issued to services that were later deemed essential. These include: (i) shops and bakeries, including departmental stores, (ii) online food deliveries, (iii) parcel services, for delivery of essential goods, (iv) automobile service workshops, (v) shops and service centres for mobile phones, computers etc, only on Sundays, and (vi) plumbers and electricians to undertake maintenance work in houses and flats. 
     
  • On April 3, orders were issued to set up community kitchens under the aegis of Kudumbasree and Local Self Governments (LSGs). Kudumbasree is the poverty eradication and women empowerment programme implemented by the Kerala government. As on April 20, a total of 339 Community Kitchens have been functioning in 249 panchayats across 14 districts of the state. They have served a total of 5,91,687 meals since April 4, 2020. The government has also instructed LSGs to hire volunteers for the kitchen and pay them an honorarium of Rs. 400 (for one-time service) or Rs. 650 (for the whole-day).

Welfare Measures

  • Under SDRF norms, funds were released to the Health Department for relief and response activities for COVID-19. 
     
  • Each District Collector has been allocated Rs. 50 lakh for carrying out various COVID-19 outbreak-related control and prevention activities.
     
  • Financial assistance has been sanctioned to (i) fishermen, (ii) artists, (iii) lottery agents and sellers, and (iii) elephants and other such animals being looked after. 
     
  • A 2000-crore worth Chief Minister’s Helping Hand Loan Scheme was announced for people facing lockdown-related unemployment and hardships. The scheme will be operationalised through neighbourhood groups under the aegis of Kudumbasree. 

Post-lockdown strategies – Strategies easing lockdown relaxations

  • Expert Committee: On April 4, an Expert Committee was constituted by the government and on April 6, the Committee submitted its Report on the guidelines for post-lockdown regulations. It recommended a conditional, three-phase strategy, with districts being the unit of implementation. Relaxations would be progressively eased in each phase depending on criteria, such as, (i) number of new confirmed cases, (ii) percentage increase/decrease in number of persons under home surveillance, and (iii) no emergence of hotspots.. 
     
  • Containment Guidelines: After the lockdown was extended till May 3, the state released revised guidelines for containment, that recommended classification of districts into four zones, based on number of cases and disease threat. The zones – Red, Orange A, Orange B, and Green – would have different, graded restrictions, with Red having stringent restrictions in the form of a lockdown till May 3. The Orange A and B zones would have a lockdown till April 24 and 20 respectively, followed by a partial relaxation thereafter. Green zone would have a lockdown till April 20 and relaxation in restrictions thereafter.
     
  • Based on the above order, the state issued an advisory for industrial units to follow while resuming operations. Some of the Standard Operating Procedures to be followed include: (i) conducting disinfectation of premises, machinery, and vehicles, (ii) arranging exclusive transportation facilities with vehicles operating at 30-40% capacity, (iii) mandatory thermal scanning of people, (iv) following hygiene and social distancing norms, including a cap on elevator capacities and size of meetings (v) mandatory corona-related insurance cover for workers, (vi) mandatory use of CCTVs, and (vii) preparing a list of nearby COVID-19 hospitals .

For more information on the spread of COVID-19 and the central and state government response to the pandemic, please see here.