By Rohit & Anirudh A modified 'Modernization of State Police Forces' scheme was started by the central government in 2000-01. One of the objectives was to help police forces in meeting the emerging challenges to internal security in the form of terrorism, naxalism etc. The scheme aims to modernize police forces in terms of:
Under this scheme, States have been clubbed into different categories and Centre-State cost sharing is category specific. Since 2005-06, States have been categorized as category ‘A’ and ‘B’ with 100% and 75% Central funding respectively. All the North Eastern States, namely Arunachal Pradesh, Assam, Manipur, Meghalaya, Mizoram, Nagaland, Tripura and Sikkim have been placed in category ‘A’ and thus, are entitled to receive 100% Central assistance for implementation of their annual approved plans. Recently, CAG decided to evaluate the working of the scheme and commissioned ‘performance audit’ reviews covering select general category and special category States. Each review covers a contiguous five year period between 2000 and 2007, but varies across selected states. For the periods under review, each state had a plan outlay (the total amount proposed to be spent in modernizing the state's police forces). However, in most cases, the actual release of funds fell significantly short of this outlay - in some cases the Centre did not contribute its share, in others the States lagged behind. For instance, in the case of Bihar, the Centre released only 56% of its share; while in the case of Rajasthan and West Bengal, the States did not release any funds at all. The graph below shows the actual releases by the Centre and the States (as percentages of their share in the proposed outlays): Further, even the funds that were released were not fully utilized. Thus, the amount finally spent fell significantly short of the initial proposal. The graph below shows the actual expenditure by State: Following are some of the other main findings from the CAG report:
Table 1: Summary of main findings in the CAG audit for different states for Modernisation of State Police Forces |
|
Purpose for which money was sanctioned |
Summary of CAG Findings |
Planning (Every state has to propose an Annual Action Plan every year. The plan is approved by the Ministry of Home Affairs and money is released as per the plan.) |
§ Submissions by the states to the MHA were delayed. § There were also delays in the clearance granted by the MHA. § In various states such as, a) Andhra Pradesh – the government spent money on works not covered by the Annual Action Plan. b) Bihar – Persistent delays in preparation of the Plan by the state police. c) West Bengal – the plans drawn up by the state did not include items covered under the scheme. |
Mobility |
§ Overall shortage of vehicles was observed. Most of the new vehicles replaced the old ones. § The police response time was too long in some states. § To give examples from some states: a) Andhra Pradesh – 58 percent of vehicles procured were utilised for replacing old vehicles. b) Bihar – the shortage of vehicles was 43 percent. c) Uttar Pradesh – 2400 vehicles were procured against a shortage of nearly 10,000 vehicles. |
Residential and non-residential buildings |
§ There were considerable delays in construction of buildings in most states. Consequently, police forces’ own security was in jeopardy. § In states such as: a) Andhra Pradesh – 53 percent of staff quarters and 43 percent of official buildings were not completed (2007). b) Bihar – The total requirement of housing was nearly 60,000. Only six percent of this were included in the Plan. c) Jharkhand – District Control rooms remained non-functional because of shortage of manpower. |
Weapons |
§ Police force in states continue to depend on outdated weapons. § Shortages of weapons also happened as acquisition from ordnance factories was very slow. § The weapons that were procured were mostly kept in the district headquarters. § In some states such as, a) Bihar – AK-47s were kept at the disposal of bodyguards of VIPs. b) West Bengal – Adequate weapons were not supplied to extremist prone police stations. |
Communication |
§ Police Telecommunication Networks were not set up successfully in some states. In others, network was functional only up to the district level. § Shortages of various communication equipments were also observed. § In some states such as, a) Bihar - The Police Telecommunication Network system (costing Rs. 4.96 crore) remained non-functional due to non-construction of tower. b) Maharashtra – Of the 850 purchased Remote Station Units, 452 were lying in stores. |
Forensic Science Laboratory/ Finger Printing Bureau |
§ In most States the Forensic Science Laboratories lacked adequate infrastructure. § In the absence of automatic finger print identification systems, investigation was being done manually in some States. § In some states such as, a) Maharashtra - There were significant delays in receipt and installation. There was also shortage (284 vacant posts) of technical manpower. b) West Bengal - Performance of the Forensic Science Laboratory was poor and in some cases, the delay in issue of investigation reports was as high as 45 months. |
Training |
§ It was observed that the percentage of police personnel trained was very low. § Training infrastructure was also inadequate. § In some states such as, a) Bihar - Only 10 per cent of total force was trained. b) West Bengal - Live training was not imparted for handling useful weapons and this severely affected the performance of police forces. |
Sources: CAG Compendium of Performance Audit Reviews on Modernisation of Police Force; PRS. Note: The audit has been done broadly from 2000 to 2007. Consequently, the period of audit for different states may vary. |
Table 1: Summary of main findings in the CAG audit for different states for Modernisation of State Police Forces |
|
Purpose for which money was sanctioned |
Summary of CAG Findings |
Planning (Every state has to propose an Annual Action Plan every year. The plan is approved by the Ministry of Home Affairs and money is released as per the plan.) |
§ Submissions by the states to the Ministry of Home Affairs (MHA) were delayed. § There were also delays in the clearance granted by the MHA. § In various states such as, a) Andhra Pradesh – the government spent Rs 32 crore on works not covered by the Annual Action Plan. b) Bihar – Persistent delays in preparation of the Plan by the state police. c) West Bengal – the plans drawn up by the state did not include items covered under the scheme. |
Mobility |
§ Overall shortage of vehicles was observed. Most of the new vehicles replaced the old ones, and no additions were made. § The police response time was too long in some states. § To give examples from some states: a) Andhra Pradesh – 58 percent of vehicles procured were utilised for replacing old vehicles. b) Bihar – the shortage of vehicles was 43 percent. c) Uttar Pradesh – 2400 vehicles were procured against a shortage of nearly 10,000 vehicles. 203 ambassador cars were procured, though only 55 were approved by the MHA. |
Residential and non-residential buildings |
§ There were considerable delays in construction of buildings in most states. Consequently, police forces’ own security was in jeopardy. Satisfaction levels with the housing provided were also very low. § In states such as: a) Andhra Pradesh – 53 percent of staff quarters and 43 percent of official buildings were not completed (2007). b) Bihar – The total requirement of housing was nearly 60,000. Only six percent of this were included in the Plan, and only 1045 units were completed by 2006. c) Jharkhand – District Control rooms remained non-functional even after spending Rs 2 crore because of shortage of manpower. |
Weapons |
§ It was observed that the police force in states continue to depend on outdated weapons. § Shortages of weapons also happened as acquisition from ordnance factories was very slow. § The weapons that were procured were mostly kept in the district headquarters. § In some states such as, a) Bihar – AK-47s were kept at the disposal of bodyguards of VIPs. b) West Bengal – Adequate weapons were not supplied to extremist prone police stations. |
Communication |
§ Police Telecommunication Networks were not set up successfully in some states. In others, network was functional only up to the district level. § Shortages of various communication equipments were also observed. § In some states such as, a) Bihar - The Police Telecommunication Network system (costing Rs. 4.96 crore) remained non-functional due to non-construction of tower. b) Maharashtra – Of the 850 purchased Remote Station Units, 452 were lying in stores. |
Forensic Science Laboratory/ Finger Printing Bureau |
§ In most States the Forensic Science Laboratories lacked adequate infrastructure. § In the absence of automatic finger print identification systems, investigation was being done manually in some States. § In some states such as, a) Maharashtra - There were significant delays in receipt and installation. There was also shortage (284 vacant posts) of technical manpower. b) West Bengal - Performance of the Forensic Science Laboratory was poor and in some cases, the delay in issue of investigation reports was as high as 45 months. |
Training |
§ It was observed that the percentage of police personnel trained was very low. § Training infrastructure was also inadequate. § In some states such as, a) Bihar - Only 10 per cent of total force was trained. b) West Bengal - Live training was not imparted for handling useful weapons and this severely affected the performance of police forces. |
Sources: CAG Compendium of Performance Audit Reviews on Modernisation of Police Force; PRS. Note: The audit has been done broadly from 2000 to 2007. Consequently, the period of audit for different states may vary. |
As of May 11, 2020, there are 67,152 confirmed cases of COVID-19 in India. Since May 4, 24,619 new cases have been registered. Out of the confirmed cases so far, 20,917 patients have been cured/discharged and 2,206 have died. As the spread of COVID-19 has increased across the country, the central government has continued to announce several policy decisions to contain the spread, and support citizens and businesses who are being affected by the pandemic. In this blog post, we summarise some of the key measures taken by the central government in this regard between May 4 and May 11, 2020.
Source: Ministry of Health and Family Welfare; PRS.
Industry
Relaxation of labour laws in some states
The Gujarat, Himachal Pradesh, Rajasthan, Haryana, and Uttarakhand governments have passed notifications to increase maximum weekly work hours from 48 hours to 72 hours and daily work hours from 9 hours to 12 hours for certain factories. This was done to combat the shortage of labour caused by the lockdown. Further, some state governments stated that longer shifts would ensure a fewer number of workers in factories so as to allow for social distancing.
Madhya Pradesh has promulgated the Madhya Pradesh Labour Laws (Amendment) Ordinance, 2020. The Ordinance exempts establishments with less than 100 workers from adhering to the Madhya Pradesh Industrial Employment (Standing Orders) Act, 1961, which regulates the conditions of employment of workers. Further, it allows the state government to exempt any establishment or class of establishments from the Madhya Pradesh Shram Kalyan Nidhi Adhiniyam, 1982, which provides for the constitution of a welfare fund for labour.
The Uttar Pradesh government has published a draft Ordinance which exempts all factories and establishments engaged in manufacturing processes from all labour laws for a period of three years. Certain conditions will continue to apply with regard to payment of wages, safety, compensation and work hours, amongst others. However, labour laws providing for social security, industrial dispute resolution, trade unions, strikes, amongst others, will not apply under the Ordinance.
Financial aid
Central government signs an agreement with Asian Infrastructure Investment Bank for COVID-19 support
The central government and Asian Infrastructure Investment Bank (AIIB) signed a 500 million dollar agreement for the COVID-19 Emergency Response and Health Systems Preparedness Project. The project aims to help India respond to the COVID-19 pandemic and strengthen India’s public health system to manage future disease outbreaks. The project is being financed by the World Bank and AIIB in the amount of 1.5 billion dollars, of which one billion dollars is being provided by World Bank and 500 million dollars is being provided by AIIB. This financial support will be available to all states and union territories and will be used to address the needs of at-risk populations, medical personnel, and creating medical and testing facilities, amongst others. The project will be implemented by the National Health Mission, the National Center for Disease Control, and the Indian Council of Medical Research, under the Ministry of Health and Family Welfare.
Travel
Restarting of passenger travel by railways
Indian Railways plans to restart passenger trains from May 12 onwards. It will begin with 15 pairs of trains which will run from New Delhi station connecting Dibrugarh, Agartala, Howrah, Patna, Bilaspur, Ranchi, Bhubaneswar, Secunderabad, Bengaluru, Chennai, Thiruvananthapuram, Madgaon, Mumbai Central, Ahmedabad and Jammu Tawi. Booking for reservation in these trains will start at 4 pm on May 11. Thereafter, Indian Railways plans to start more services on new routes.
Return of Indians stranded abroad
The central government will facilitate the return of Indian nationals stranded abroad in a phased manner beginning on May 7. The travel will be arranged by aircraft and naval ships. The stranded Indians utilising the service will be required to pay for it. Medical screening of the passengers will be done before the flight. On reaching India, passengers will be required to download the Aarogya Setu app. Further, they will be quarantined by the concerned state government in either a hospital or a quarantine institution for 14 days on a payment basis. After quarantine, passengers will be tested for COVID-19 and further action will be taken based on the results.
For more information on the spread of COVID-19 and the central and state government response to the pandemic, please see here.