By Rohit & Anirudh A modified 'Modernization of State Police Forces' scheme was started by the central government in 2000-01. One of the objectives was to help police forces in meeting the emerging challenges to internal security in the form of terrorism, naxalism etc. The scheme aims to modernize police forces in terms of:
Under this scheme, States have been clubbed into different categories and Centre-State cost sharing is category specific. Since 2005-06, States have been categorized as category ‘A’ and ‘B’ with 100% and 75% Central funding respectively. All the North Eastern States, namely Arunachal Pradesh, Assam, Manipur, Meghalaya, Mizoram, Nagaland, Tripura and Sikkim have been placed in category ‘A’ and thus, are entitled to receive 100% Central assistance for implementation of their annual approved plans. Recently, CAG decided to evaluate the working of the scheme and commissioned ‘performance audit’ reviews covering select general category and special category States. Each review covers a contiguous five year period between 2000 and 2007, but varies across selected states. For the periods under review, each state had a plan outlay (the total amount proposed to be spent in modernizing the state's police forces). However, in most cases, the actual release of funds fell significantly short of this outlay - in some cases the Centre did not contribute its share, in others the States lagged behind. For instance, in the case of Bihar, the Centre released only 56% of its share; while in the case of Rajasthan and West Bengal, the States did not release any funds at all. The graph below shows the actual releases by the Centre and the States (as percentages of their share in the proposed outlays): Further, even the funds that were released were not fully utilized. Thus, the amount finally spent fell significantly short of the initial proposal. The graph below shows the actual expenditure by State: Following are some of the other main findings from the CAG report:
Table 1: Summary of main findings in the CAG audit for different states for Modernisation of State Police Forces |
|
Purpose for which money was sanctioned |
Summary of CAG Findings |
Planning (Every state has to propose an Annual Action Plan every year. The plan is approved by the Ministry of Home Affairs and money is released as per the plan.) |
§ Submissions by the states to the MHA were delayed. § There were also delays in the clearance granted by the MHA. § In various states such as, a) Andhra Pradesh – the government spent money on works not covered by the Annual Action Plan. b) Bihar – Persistent delays in preparation of the Plan by the state police. c) West Bengal – the plans drawn up by the state did not include items covered under the scheme. |
Mobility |
§ Overall shortage of vehicles was observed. Most of the new vehicles replaced the old ones. § The police response time was too long in some states. § To give examples from some states: a) Andhra Pradesh – 58 percent of vehicles procured were utilised for replacing old vehicles. b) Bihar – the shortage of vehicles was 43 percent. c) Uttar Pradesh – 2400 vehicles were procured against a shortage of nearly 10,000 vehicles. |
Residential and non-residential buildings |
§ There were considerable delays in construction of buildings in most states. Consequently, police forces’ own security was in jeopardy. § In states such as: a) Andhra Pradesh – 53 percent of staff quarters and 43 percent of official buildings were not completed (2007). b) Bihar – The total requirement of housing was nearly 60,000. Only six percent of this were included in the Plan. c) Jharkhand – District Control rooms remained non-functional because of shortage of manpower. |
Weapons |
§ Police force in states continue to depend on outdated weapons. § Shortages of weapons also happened as acquisition from ordnance factories was very slow. § The weapons that were procured were mostly kept in the district headquarters. § In some states such as, a) Bihar – AK-47s were kept at the disposal of bodyguards of VIPs. b) West Bengal – Adequate weapons were not supplied to extremist prone police stations. |
Communication |
§ Police Telecommunication Networks were not set up successfully in some states. In others, network was functional only up to the district level. § Shortages of various communication equipments were also observed. § In some states such as, a) Bihar - The Police Telecommunication Network system (costing Rs. 4.96 crore) remained non-functional due to non-construction of tower. b) Maharashtra – Of the 850 purchased Remote Station Units, 452 were lying in stores. |
Forensic Science Laboratory/ Finger Printing Bureau |
§ In most States the Forensic Science Laboratories lacked adequate infrastructure. § In the absence of automatic finger print identification systems, investigation was being done manually in some States. § In some states such as, a) Maharashtra - There were significant delays in receipt and installation. There was also shortage (284 vacant posts) of technical manpower. b) West Bengal - Performance of the Forensic Science Laboratory was poor and in some cases, the delay in issue of investigation reports was as high as 45 months. |
Training |
§ It was observed that the percentage of police personnel trained was very low. § Training infrastructure was also inadequate. § In some states such as, a) Bihar - Only 10 per cent of total force was trained. b) West Bengal - Live training was not imparted for handling useful weapons and this severely affected the performance of police forces. |
Sources: CAG Compendium of Performance Audit Reviews on Modernisation of Police Force; PRS. Note: The audit has been done broadly from 2000 to 2007. Consequently, the period of audit for different states may vary. |
Table 1: Summary of main findings in the CAG audit for different states for Modernisation of State Police Forces |
|
Purpose for which money was sanctioned |
Summary of CAG Findings |
Planning (Every state has to propose an Annual Action Plan every year. The plan is approved by the Ministry of Home Affairs and money is released as per the plan.) |
§ Submissions by the states to the Ministry of Home Affairs (MHA) were delayed. § There were also delays in the clearance granted by the MHA. § In various states such as, a) Andhra Pradesh – the government spent Rs 32 crore on works not covered by the Annual Action Plan. b) Bihar – Persistent delays in preparation of the Plan by the state police. c) West Bengal – the plans drawn up by the state did not include items covered under the scheme. |
Mobility |
§ Overall shortage of vehicles was observed. Most of the new vehicles replaced the old ones, and no additions were made. § The police response time was too long in some states. § To give examples from some states: a) Andhra Pradesh – 58 percent of vehicles procured were utilised for replacing old vehicles. b) Bihar – the shortage of vehicles was 43 percent. c) Uttar Pradesh – 2400 vehicles were procured against a shortage of nearly 10,000 vehicles. 203 ambassador cars were procured, though only 55 were approved by the MHA. |
Residential and non-residential buildings |
§ There were considerable delays in construction of buildings in most states. Consequently, police forces’ own security was in jeopardy. Satisfaction levels with the housing provided were also very low. § In states such as: a) Andhra Pradesh – 53 percent of staff quarters and 43 percent of official buildings were not completed (2007). b) Bihar – The total requirement of housing was nearly 60,000. Only six percent of this were included in the Plan, and only 1045 units were completed by 2006. c) Jharkhand – District Control rooms remained non-functional even after spending Rs 2 crore because of shortage of manpower. |
Weapons |
§ It was observed that the police force in states continue to depend on outdated weapons. § Shortages of weapons also happened as acquisition from ordnance factories was very slow. § The weapons that were procured were mostly kept in the district headquarters. § In some states such as, a) Bihar – AK-47s were kept at the disposal of bodyguards of VIPs. b) West Bengal – Adequate weapons were not supplied to extremist prone police stations. |
Communication |
§ Police Telecommunication Networks were not set up successfully in some states. In others, network was functional only up to the district level. § Shortages of various communication equipments were also observed. § In some states such as, a) Bihar - The Police Telecommunication Network system (costing Rs. 4.96 crore) remained non-functional due to non-construction of tower. b) Maharashtra – Of the 850 purchased Remote Station Units, 452 were lying in stores. |
Forensic Science Laboratory/ Finger Printing Bureau |
§ In most States the Forensic Science Laboratories lacked adequate infrastructure. § In the absence of automatic finger print identification systems, investigation was being done manually in some States. § In some states such as, a) Maharashtra - There were significant delays in receipt and installation. There was also shortage (284 vacant posts) of technical manpower. b) West Bengal - Performance of the Forensic Science Laboratory was poor and in some cases, the delay in issue of investigation reports was as high as 45 months. |
Training |
§ It was observed that the percentage of police personnel trained was very low. § Training infrastructure was also inadequate. § In some states such as, a) Bihar - Only 10 per cent of total force was trained. b) West Bengal - Live training was not imparted for handling useful weapons and this severely affected the performance of police forces. |
Sources: CAG Compendium of Performance Audit Reviews on Modernisation of Police Force; PRS. Note: The audit has been done broadly from 2000 to 2007. Consequently, the period of audit for different states may vary. |
As of May 29, 2020, there are 1,65,799 confirmed cases of COVID-19 in India. 47,352 new cases have been registered in the last week (since May 22). Out of the confirmed cases so far, 71,106 patients have been cured/discharged and 4,706 have died. Most cases are in the state of Maharashtra (59,546) followed by the states of Tamil Nadu (19,372), Delhi (16,281) and Gujarat (15,562).
With the spread of COVID-19, the central government initially undertook many measures to contain the spread of the pandemic, including restrictions on travel and movement through national lockdown. With gradual resumption of activities, the central government has recently announced measures to ease restrictions on travel and movement. Further, the government has continued to announce policy decisions to ease the financial stress caused by the pandemic, and to contain further spread of the pandemic. In this blog post, we summarise some of the key measures taken by the central government in this regard between May 23 and May 29, 2020.
Figure 1: Day wise number of COVID-19 cases in the country
Source: Ministry of Health and Family Welfare; PRS.
Finance
RBI announces additional measures to ease financial stress caused by COVID-19
On May 22, the Reserve Bank of India (RBI) issued a statement with various development and regulatory policies to ease the financial stress caused by COVID-19. These measures include: (i) improving liquidity in the market; (ii) support to exports and imports; and (iii) easing capital financing. Subsequently, following measures have been notified by the RBI:
Travel and Movement
Domestic Air travel resumes; fare limits set by government
Domestic passenger air travel has been resumed in a phased manned (with one-third capacity of operations) from May 25, 2020 based on the announcement of the Ministry of Civil Aviation on May 21. To ensure that airlines do not charge excessive fare and to ensure that journey is only for essential purposes, the Ministry of Civil Aviation issued an order to limit the minimum and maximum fare that airlines can charge from the passenger. The routes have been divided in seven sectors based on the approximate duration of the flight. For routes with shortest duration (for example, Delhi to Chandigarh), the minimum and maximum fare will be Rs 2,000 and Rs 6,000, respectively. For routes with the longest duration (for example, Delhi to Thiruvananthapuram), the minimum and maximum fare will be Rs 6,500 and Rs 18,600, respectively.
Further, the Ministry announced that all operational routes under the Regional Connectivity (UDAN) Scheme with up to 500 km of length or operational routes in priority areas (North East region, hilly states or islands) are permitted to resume operations. This is in addition to the one-third capacity of operations announced earlier.
Health
Guidelines for international arrivals issued
The Ministry of Health and Family Welfare issued guidelines for international arrivals. All travellers are required to give an undertaking that they will undergo a 14-day mandatory institutional quarantine at their own cost (7 days in institutional quarantine followed by a 7-day isolation at home). In emergency cases (such as pregnancy or death in the family), home quarantine will be permitted. Use of Aarogya Setu app will be mandatory in such cases. Only asymptomatic passengers will be allowed to board (flight/ship) after thermal screening. On arrival, thermal screening will be carried out for all passengers. The passengers found to be symptomatic will be isolated and taken to a medical facility.
Movement of migrant labourers
Supreme Court gives an interim order regarding problems of migrant labourers
The Supreme Court of India took cognisance of the problems of migrant labourers who have been stranded in different parts of the country. In its order, the Court observed that there are lapses being noticed in the process of registration, transportation and in providing food and shelter to the migrant workers. In view of these difficulties, the Court issued the following interim directions:
The Court directed the central and state governments to produce record of all necessary details such as the number of migrant workers, the plan to transport them to their destination, and the mechanism of registration.
Other measures
PM CARES Fund included in the list of CSR eligible activities
The Ministry of Corporate Affairs notified the inclusion of PM CARES fund in the list of activities eligible for Corporate Social Responsibility (CSR) under the Companies Act, 2013. Under the Act, companies with net worth, turnover or profits above a specified amount are required to spend 2% of their average net profits in the last three financial years towards CSR activities. This measure will come into effect retrospectively from March 28, 2020, when the fund was setup.
For more information on the spread of COVID-19 and the central and state government response to the pandemic, please see here.