By Rohit & Anirudh A modified 'Modernization of State Police Forces' scheme was started by the central government in 2000-01. One of the objectives was to help police forces in meeting the emerging challenges to internal security in the form of terrorism, naxalism etc. The scheme aims to modernize police forces in terms of:
Under this scheme, States have been clubbed into different categories and Centre-State cost sharing is category specific. Since 2005-06, States have been categorized as category ‘A’ and ‘B’ with 100% and 75% Central funding respectively. All the North Eastern States, namely Arunachal Pradesh, Assam, Manipur, Meghalaya, Mizoram, Nagaland, Tripura and Sikkim have been placed in category ‘A’ and thus, are entitled to receive 100% Central assistance for implementation of their annual approved plans. Recently, CAG decided to evaluate the working of the scheme and commissioned ‘performance audit’ reviews covering select general category and special category States. Each review covers a contiguous five year period between 2000 and 2007, but varies across selected states. For the periods under review, each state had a plan outlay (the total amount proposed to be spent in modernizing the state's police forces). However, in most cases, the actual release of funds fell significantly short of this outlay - in some cases the Centre did not contribute its share, in others the States lagged behind. For instance, in the case of Bihar, the Centre released only 56% of its share; while in the case of Rajasthan and West Bengal, the States did not release any funds at all. The graph below shows the actual releases by the Centre and the States (as percentages of their share in the proposed outlays): Further, even the funds that were released were not fully utilized. Thus, the amount finally spent fell significantly short of the initial proposal. The graph below shows the actual expenditure by State: Following are some of the other main findings from the CAG report:
Table 1: Summary of main findings in the CAG audit for different states for Modernisation of State Police Forces |
|
Purpose for which money was sanctioned |
Summary of CAG Findings |
Planning (Every state has to propose an Annual Action Plan every year. The plan is approved by the Ministry of Home Affairs and money is released as per the plan.) |
§ Submissions by the states to the MHA were delayed. § There were also delays in the clearance granted by the MHA. § In various states such as, a) Andhra Pradesh – the government spent money on works not covered by the Annual Action Plan. b) Bihar – Persistent delays in preparation of the Plan by the state police. c) West Bengal – the plans drawn up by the state did not include items covered under the scheme. |
Mobility |
§ Overall shortage of vehicles was observed. Most of the new vehicles replaced the old ones. § The police response time was too long in some states. § To give examples from some states: a) Andhra Pradesh – 58 percent of vehicles procured were utilised for replacing old vehicles. b) Bihar – the shortage of vehicles was 43 percent. c) Uttar Pradesh – 2400 vehicles were procured against a shortage of nearly 10,000 vehicles. |
Residential and non-residential buildings |
§ There were considerable delays in construction of buildings in most states. Consequently, police forces’ own security was in jeopardy. § In states such as: a) Andhra Pradesh – 53 percent of staff quarters and 43 percent of official buildings were not completed (2007). b) Bihar – The total requirement of housing was nearly 60,000. Only six percent of this were included in the Plan. c) Jharkhand – District Control rooms remained non-functional because of shortage of manpower. |
Weapons |
§ Police force in states continue to depend on outdated weapons. § Shortages of weapons also happened as acquisition from ordnance factories was very slow. § The weapons that were procured were mostly kept in the district headquarters. § In some states such as, a) Bihar – AK-47s were kept at the disposal of bodyguards of VIPs. b) West Bengal – Adequate weapons were not supplied to extremist prone police stations. |
Communication |
§ Police Telecommunication Networks were not set up successfully in some states. In others, network was functional only up to the district level. § Shortages of various communication equipments were also observed. § In some states such as, a) Bihar - The Police Telecommunication Network system (costing Rs. 4.96 crore) remained non-functional due to non-construction of tower. b) Maharashtra – Of the 850 purchased Remote Station Units, 452 were lying in stores. |
Forensic Science Laboratory/ Finger Printing Bureau |
§ In most States the Forensic Science Laboratories lacked adequate infrastructure. § In the absence of automatic finger print identification systems, investigation was being done manually in some States. § In some states such as, a) Maharashtra - There were significant delays in receipt and installation. There was also shortage (284 vacant posts) of technical manpower. b) West Bengal - Performance of the Forensic Science Laboratory was poor and in some cases, the delay in issue of investigation reports was as high as 45 months. |
Training |
§ It was observed that the percentage of police personnel trained was very low. § Training infrastructure was also inadequate. § In some states such as, a) Bihar - Only 10 per cent of total force was trained. b) West Bengal - Live training was not imparted for handling useful weapons and this severely affected the performance of police forces. |
Sources: CAG Compendium of Performance Audit Reviews on Modernisation of Police Force; PRS. Note: The audit has been done broadly from 2000 to 2007. Consequently, the period of audit for different states may vary. |
Table 1: Summary of main findings in the CAG audit for different states for Modernisation of State Police Forces |
|
Purpose for which money was sanctioned |
Summary of CAG Findings |
Planning (Every state has to propose an Annual Action Plan every year. The plan is approved by the Ministry of Home Affairs and money is released as per the plan.) |
§ Submissions by the states to the Ministry of Home Affairs (MHA) were delayed. § There were also delays in the clearance granted by the MHA. § In various states such as, a) Andhra Pradesh – the government spent Rs 32 crore on works not covered by the Annual Action Plan. b) Bihar – Persistent delays in preparation of the Plan by the state police. c) West Bengal – the plans drawn up by the state did not include items covered under the scheme. |
Mobility |
§ Overall shortage of vehicles was observed. Most of the new vehicles replaced the old ones, and no additions were made. § The police response time was too long in some states. § To give examples from some states: a) Andhra Pradesh – 58 percent of vehicles procured were utilised for replacing old vehicles. b) Bihar – the shortage of vehicles was 43 percent. c) Uttar Pradesh – 2400 vehicles were procured against a shortage of nearly 10,000 vehicles. 203 ambassador cars were procured, though only 55 were approved by the MHA. |
Residential and non-residential buildings |
§ There were considerable delays in construction of buildings in most states. Consequently, police forces’ own security was in jeopardy. Satisfaction levels with the housing provided were also very low. § In states such as: a) Andhra Pradesh – 53 percent of staff quarters and 43 percent of official buildings were not completed (2007). b) Bihar – The total requirement of housing was nearly 60,000. Only six percent of this were included in the Plan, and only 1045 units were completed by 2006. c) Jharkhand – District Control rooms remained non-functional even after spending Rs 2 crore because of shortage of manpower. |
Weapons |
§ It was observed that the police force in states continue to depend on outdated weapons. § Shortages of weapons also happened as acquisition from ordnance factories was very slow. § The weapons that were procured were mostly kept in the district headquarters. § In some states such as, a) Bihar – AK-47s were kept at the disposal of bodyguards of VIPs. b) West Bengal – Adequate weapons were not supplied to extremist prone police stations. |
Communication |
§ Police Telecommunication Networks were not set up successfully in some states. In others, network was functional only up to the district level. § Shortages of various communication equipments were also observed. § In some states such as, a) Bihar - The Police Telecommunication Network system (costing Rs. 4.96 crore) remained non-functional due to non-construction of tower. b) Maharashtra – Of the 850 purchased Remote Station Units, 452 were lying in stores. |
Forensic Science Laboratory/ Finger Printing Bureau |
§ In most States the Forensic Science Laboratories lacked adequate infrastructure. § In the absence of automatic finger print identification systems, investigation was being done manually in some States. § In some states such as, a) Maharashtra - There were significant delays in receipt and installation. There was also shortage (284 vacant posts) of technical manpower. b) West Bengal - Performance of the Forensic Science Laboratory was poor and in some cases, the delay in issue of investigation reports was as high as 45 months. |
Training |
§ It was observed that the percentage of police personnel trained was very low. § Training infrastructure was also inadequate. § In some states such as, a) Bihar - Only 10 per cent of total force was trained. b) West Bengal - Live training was not imparted for handling useful weapons and this severely affected the performance of police forces. |
Sources: CAG Compendium of Performance Audit Reviews on Modernisation of Police Force; PRS. Note: The audit has been done broadly from 2000 to 2007. Consequently, the period of audit for different states may vary. |
The government's acquisition of land for projects has been facing protests across the country, the violence in Uttar Pradesh being only the latest. What is Land Acquisition? Land acquisition is the process by which the government forcibly acquires private property for public purpose without the consent of the land-owner. It is thus different from a land purchase, in which the sale is made by a willing seller. How is this process governed? Land Acquisition is governed by the Land Acquisition Act, 1894. The government has to follow a process of declaring the land to be acquired, notify the interested persons, and acquire the land after paying due compensation. Various state legislatures have also passed Acts that detail various aspects of the acquisition process. Land is a state subject. Why is Parliament passing a law? Though land is a state subject, "acquisition and requisitioning of property" is in the concurrent list. Both Parliament and state legislatures can make laws on this subject. Is there a new Act being proposed? The government had introduced a Bill to amend this Act in 2007. That Bill lapsed in 2009 at the time of the general elections. The government has stated its intent to re-introduce a similar Bill, but has not yet done so. What are the major changes being proposed? There are significant changes proposed in the 2007 Bill with regard to (a) the purpose for which land may be acquired; (b) the amount of compensation to be paid; (c) the process of acquisition; (d) use of the land acquired; and (e) dispute settlement mechanisms. We explain these briefly below. Purpose: Currently, land may be acquired for a range of uses such as village sites, town or rural planning, residential purposes for poor or displaced persons, planned development (education, housing, health, slum clearance), and for state corporations. Land may also be acquired for use by private companies for the above purposes or if the work "is likely to prove useful to the public". The 2007 Bill had a narrower list: (a) for strategic naval, military or air force purposes; (b) for public infrastructure projects; and (c) for any purpose useful to the general public if 70% of the land has been purchased from willing sellers through the free market. Compensation: The current Act requires market value to be paid for the land and any other property on it (buildings, trees, irrigation work etc) as well as expenses for compelling the person change place of residence or business. It explicitly prohibits taking into account the intended use of land while computing market value. The 2007 Bill requires payment of the highest of three items: the minimum value specified for stamp duty, the average of the top 50 per cent by price of land sale in the vicinity, and the average of the top 50 pc of the land purchased for the project from willing sellers. For computing recent land sale, the intended land use is to be used. Thus, agricultural land being acquired for an industrial project will be paid the price of industrial land. Process of acquisition: Several changes are proposed, including the requirement of a social impact assessment. Any project that displaces more than 400 families (200 in hilly, tribal and desert areas) will require an SIA before the acquisition is approved. Use of land acquired: The 2007 Bill requires the land acquired to be used for that purpose within five years. If this condition is not met, the land reverts to the government (it is not returned to the original land owners). If any acquired land is transferred to another entity, 80 pc of the capital gains has to be shared with the original land-owners and their legal heirs. Dispute Settlement: Currently, all disputes are resolved by civil courts, which results in delays. The 2007 Bill sets up Land Acquisition Compensation Dispute Resolution Authority at the state and national levels. These authorities will have the power of civil courts, and will adjudicate disputes related to compensation claims. Does the proposed Bill address the major issues? The Bill narrows the uses for which land may be acquired. It also changes the compensation due and links that to the market price for which land is to be used. There could be significant changes in acquisition for use by private industry. Firstly, they would have to purchase at least 70 pc of the required land from willing sellers (presumably, at fair market price). Second, the compensation amount for the remaining (upto 30 pc of land) could be significantly higher than the current method. This would be at a premium to the average paid to the willing sellers, and it would be based on intended industrial or commercial use which usually commands a higher price than agricultural land. However, the effect on acquisition for projects such as highways and railways will not be significant, as there is no benchmark for price determination for such use. This article appeared in Rediff News on May 12, 2011 and can be accessed here.