By Rohit & Anirudh A modified 'Modernization of State Police Forces' scheme was started by the central government in 2000-01. One of the objectives was to help police forces in meeting the emerging challenges to internal security in the form of terrorism, naxalism etc. The scheme aims to modernize police forces in terms of:
Under this scheme, States have been clubbed into different categories and Centre-State cost sharing is category specific. Since 2005-06, States have been categorized as category ‘A’ and ‘B’ with 100% and 75% Central funding respectively. All the North Eastern States, namely Arunachal Pradesh, Assam, Manipur, Meghalaya, Mizoram, Nagaland, Tripura and Sikkim have been placed in category ‘A’ and thus, are entitled to receive 100% Central assistance for implementation of their annual approved plans. Recently, CAG decided to evaluate the working of the scheme and commissioned ‘performance audit’ reviews covering select general category and special category States. Each review covers a contiguous five year period between 2000 and 2007, but varies across selected states. For the periods under review, each state had a plan outlay (the total amount proposed to be spent in modernizing the state's police forces). However, in most cases, the actual release of funds fell significantly short of this outlay - in some cases the Centre did not contribute its share, in others the States lagged behind. For instance, in the case of Bihar, the Centre released only 56% of its share; while in the case of Rajasthan and West Bengal, the States did not release any funds at all. The graph below shows the actual releases by the Centre and the States (as percentages of their share in the proposed outlays): Further, even the funds that were released were not fully utilized. Thus, the amount finally spent fell significantly short of the initial proposal. The graph below shows the actual expenditure by State: Following are some of the other main findings from the CAG report:
Table 1: Summary of main findings in the CAG audit for different states for Modernisation of State Police Forces |
|
Purpose for which money was sanctioned |
Summary of CAG Findings |
Planning (Every state has to propose an Annual Action Plan every year. The plan is approved by the Ministry of Home Affairs and money is released as per the plan.) |
§ Submissions by the states to the MHA were delayed. § There were also delays in the clearance granted by the MHA. § In various states such as, a) Andhra Pradesh – the government spent money on works not covered by the Annual Action Plan. b) Bihar – Persistent delays in preparation of the Plan by the state police. c) West Bengal – the plans drawn up by the state did not include items covered under the scheme. |
Mobility |
§ Overall shortage of vehicles was observed. Most of the new vehicles replaced the old ones. § The police response time was too long in some states. § To give examples from some states: a) Andhra Pradesh – 58 percent of vehicles procured were utilised for replacing old vehicles. b) Bihar – the shortage of vehicles was 43 percent. c) Uttar Pradesh – 2400 vehicles were procured against a shortage of nearly 10,000 vehicles. |
Residential and non-residential buildings |
§ There were considerable delays in construction of buildings in most states. Consequently, police forces’ own security was in jeopardy. § In states such as: a) Andhra Pradesh – 53 percent of staff quarters and 43 percent of official buildings were not completed (2007). b) Bihar – The total requirement of housing was nearly 60,000. Only six percent of this were included in the Plan. c) Jharkhand – District Control rooms remained non-functional because of shortage of manpower. |
Weapons |
§ Police force in states continue to depend on outdated weapons. § Shortages of weapons also happened as acquisition from ordnance factories was very slow. § The weapons that were procured were mostly kept in the district headquarters. § In some states such as, a) Bihar – AK-47s were kept at the disposal of bodyguards of VIPs. b) West Bengal – Adequate weapons were not supplied to extremist prone police stations. |
Communication |
§ Police Telecommunication Networks were not set up successfully in some states. In others, network was functional only up to the district level. § Shortages of various communication equipments were also observed. § In some states such as, a) Bihar - The Police Telecommunication Network system (costing Rs. 4.96 crore) remained non-functional due to non-construction of tower. b) Maharashtra – Of the 850 purchased Remote Station Units, 452 were lying in stores. |
Forensic Science Laboratory/ Finger Printing Bureau |
§ In most States the Forensic Science Laboratories lacked adequate infrastructure. § In the absence of automatic finger print identification systems, investigation was being done manually in some States. § In some states such as, a) Maharashtra - There were significant delays in receipt and installation. There was also shortage (284 vacant posts) of technical manpower. b) West Bengal - Performance of the Forensic Science Laboratory was poor and in some cases, the delay in issue of investigation reports was as high as 45 months. |
Training |
§ It was observed that the percentage of police personnel trained was very low. § Training infrastructure was also inadequate. § In some states such as, a) Bihar - Only 10 per cent of total force was trained. b) West Bengal - Live training was not imparted for handling useful weapons and this severely affected the performance of police forces. |
Sources: CAG Compendium of Performance Audit Reviews on Modernisation of Police Force; PRS. Note: The audit has been done broadly from 2000 to 2007. Consequently, the period of audit for different states may vary. |
Table 1: Summary of main findings in the CAG audit for different states for Modernisation of State Police Forces |
|
Purpose for which money was sanctioned |
Summary of CAG Findings |
Planning (Every state has to propose an Annual Action Plan every year. The plan is approved by the Ministry of Home Affairs and money is released as per the plan.) |
§ Submissions by the states to the Ministry of Home Affairs (MHA) were delayed. § There were also delays in the clearance granted by the MHA. § In various states such as, a) Andhra Pradesh – the government spent Rs 32 crore on works not covered by the Annual Action Plan. b) Bihar – Persistent delays in preparation of the Plan by the state police. c) West Bengal – the plans drawn up by the state did not include items covered under the scheme. |
Mobility |
§ Overall shortage of vehicles was observed. Most of the new vehicles replaced the old ones, and no additions were made. § The police response time was too long in some states. § To give examples from some states: a) Andhra Pradesh – 58 percent of vehicles procured were utilised for replacing old vehicles. b) Bihar – the shortage of vehicles was 43 percent. c) Uttar Pradesh – 2400 vehicles were procured against a shortage of nearly 10,000 vehicles. 203 ambassador cars were procured, though only 55 were approved by the MHA. |
Residential and non-residential buildings |
§ There were considerable delays in construction of buildings in most states. Consequently, police forces’ own security was in jeopardy. Satisfaction levels with the housing provided were also very low. § In states such as: a) Andhra Pradesh – 53 percent of staff quarters and 43 percent of official buildings were not completed (2007). b) Bihar – The total requirement of housing was nearly 60,000. Only six percent of this were included in the Plan, and only 1045 units were completed by 2006. c) Jharkhand – District Control rooms remained non-functional even after spending Rs 2 crore because of shortage of manpower. |
Weapons |
§ It was observed that the police force in states continue to depend on outdated weapons. § Shortages of weapons also happened as acquisition from ordnance factories was very slow. § The weapons that were procured were mostly kept in the district headquarters. § In some states such as, a) Bihar – AK-47s were kept at the disposal of bodyguards of VIPs. b) West Bengal – Adequate weapons were not supplied to extremist prone police stations. |
Communication |
§ Police Telecommunication Networks were not set up successfully in some states. In others, network was functional only up to the district level. § Shortages of various communication equipments were also observed. § In some states such as, a) Bihar - The Police Telecommunication Network system (costing Rs. 4.96 crore) remained non-functional due to non-construction of tower. b) Maharashtra – Of the 850 purchased Remote Station Units, 452 were lying in stores. |
Forensic Science Laboratory/ Finger Printing Bureau |
§ In most States the Forensic Science Laboratories lacked adequate infrastructure. § In the absence of automatic finger print identification systems, investigation was being done manually in some States. § In some states such as, a) Maharashtra - There were significant delays in receipt and installation. There was also shortage (284 vacant posts) of technical manpower. b) West Bengal - Performance of the Forensic Science Laboratory was poor and in some cases, the delay in issue of investigation reports was as high as 45 months. |
Training |
§ It was observed that the percentage of police personnel trained was very low. § Training infrastructure was also inadequate. § In some states such as, a) Bihar - Only 10 per cent of total force was trained. b) West Bengal - Live training was not imparted for handling useful weapons and this severely affected the performance of police forces. |
Sources: CAG Compendium of Performance Audit Reviews on Modernisation of Police Force; PRS. Note: The audit has been done broadly from 2000 to 2007. Consequently, the period of audit for different states may vary. |
TRAI released its recommendations on auction of spectrum on April 23, 2012. The recommendations are in pursuance of the Supreme Court order cancelling 122 telecom licences. The cancellation was ordered on grounds of procedural irregularities and arbitrariness in the first-cum-first-serve policy for allocation of spectrum. The recommendations, if adopted by the Department of Telecommunications, would change various aspects of the present telecom policy, including (a) relationship between a telecom licence and spectrum; (b) procedure for allocation of spectrum; (c) pricing of spectrum; (d) limits on spectrum allocation; and (e) use of spectrum. Relationship between telecom licences and spectrum Previously, under the Telecom Policy 1994 (updated in 1999), spectrum was tied in with telecom licences. Since 2003, licence conditions provided for award of two blocks of 6.2 MHz of spectrum for GSM technology and two blocks of 5 MHz for CDMA technology. As per the government’s decision of January 17, 2008 (as explained in TRAI's consultation paper, see page 3 paragraph 7) additional spectrum would be awarded on the basis of increment in the number of subscribers. Service providers had to pay a licence fee (on obtaining the licence), an annual licence fee and a spectrum usage charge determined on the basis of their adjusted gross revenue. TRAI has recommended that telecom licences and spectrum should be de-linked. The service provider would thus pay separately for the value of the licence and the spectrum. With this formulation an entity that does not hold a licence, but is eligible to secure one, may also procure spectrum. This would help in avoiding situations where licence holders have to wait to secure spectrum or offer wire line services in the absence of spectrum. Procedure for allocation of spectrum TRAI has recommended that spectrum be auctioned by means of a simultaneous multiple round ascending auction (SMRA). This means that the service providers would bid for spectrum in different blocks simultaneously. In the first round of auction a reserve price (base price) set by the government is used. Reserve price for auction and payment mechanism A reserve price indicates the minimum amount the bidder must pay to win the object. In case it is too low, it may reduce the gains made by the seller and lead to a sub-optimal sale. If it is too high, it may reduce the number of bidders and the probability of the good not being sold. Various countries have adopted a reserve price of 0.5 times the final price. TRAI has recommended that the reserve price should be 0.8 times the expected winning bid. It has also recommended that telecom companies pay 67% to 75% of the final price in installments over 10 years, depending on the spectrum band. TRAI has reasoned that a higher price would reduce the possibility of further sales upon bidders securing spectrum. However, this may lead to fewer bidders and ultimately fewer service providers. It is argued in news reports that this may increase investments to be made by the service providers and eventually an increase in tariffs. Spectrum blocks and caps TRAI has recommended that the spectrum cap should be determined on the basis of market share. A service provider can now secure a maximum of 50% of spectrum assigned in each band in each service area. However, a service provider cannot hold more than 25% of the total spectrum assigned in all the bands across the country. As per the January 2008 decision, additional spectrum could be awarded to telecom companies when they reached incremental slabs of subscribers. This could extend to two blocks of 1 MHz for GSM technology, and two blocks of 1.25 MHz for CDMA, for each slab of subscribers. TRAI has recommended that spectrum should be auctioned in blocks of 1.25 MHz. Each auction would at least offer 5 MHz of spectrum at a time. Smaller blocks would ensure that service providers who are nearing the spectrum cap may secure spectrum without exceeding the cap. However, experts have argued that 1.25 MHz block may be too limited for launching services. Also, TRAI in the recommendation has noted that a minimum of 5 MHz of contiguous spectrum is required to launch efficient services with new technologies. Use of spectrum TRAI has recommended that the use of spectrum should be liberalised. This implies that spectrum should be technology neutral. Telecom companies would now be free to launch services with any technology of their choice.