By Rohit & Anirudh A modified 'Modernization of State Police Forces' scheme was started by the central government in 2000-01. One of the objectives was to help police forces in meeting the emerging challenges to internal security in the form of terrorism, naxalism etc. The scheme aims to modernize police forces in terms of:
Under this scheme, States have been clubbed into different categories and Centre-State cost sharing is category specific. Since 2005-06, States have been categorized as category ‘A’ and ‘B’ with 100% and 75% Central funding respectively. All the North Eastern States, namely Arunachal Pradesh, Assam, Manipur, Meghalaya, Mizoram, Nagaland, Tripura and Sikkim have been placed in category ‘A’ and thus, are entitled to receive 100% Central assistance for implementation of their annual approved plans. Recently, CAG decided to evaluate the working of the scheme and commissioned ‘performance audit’ reviews covering select general category and special category States. Each review covers a contiguous five year period between 2000 and 2007, but varies across selected states. For the periods under review, each state had a plan outlay (the total amount proposed to be spent in modernizing the state's police forces). However, in most cases, the actual release of funds fell significantly short of this outlay - in some cases the Centre did not contribute its share, in others the States lagged behind. For instance, in the case of Bihar, the Centre released only 56% of its share; while in the case of Rajasthan and West Bengal, the States did not release any funds at all. The graph below shows the actual releases by the Centre and the States (as percentages of their share in the proposed outlays): Further, even the funds that were released were not fully utilized. Thus, the amount finally spent fell significantly short of the initial proposal. The graph below shows the actual expenditure by State: Following are some of the other main findings from the CAG report:
Table 1: Summary of main findings in the CAG audit for different states for Modernisation of State Police Forces |
|
Purpose for which money was sanctioned |
Summary of CAG Findings |
Planning (Every state has to propose an Annual Action Plan every year. The plan is approved by the Ministry of Home Affairs and money is released as per the plan.) |
§ Submissions by the states to the MHA were delayed. § There were also delays in the clearance granted by the MHA. § In various states such as, a) Andhra Pradesh – the government spent money on works not covered by the Annual Action Plan. b) Bihar – Persistent delays in preparation of the Plan by the state police. c) West Bengal – the plans drawn up by the state did not include items covered under the scheme. |
Mobility |
§ Overall shortage of vehicles was observed. Most of the new vehicles replaced the old ones. § The police response time was too long in some states. § To give examples from some states: a) Andhra Pradesh – 58 percent of vehicles procured were utilised for replacing old vehicles. b) Bihar – the shortage of vehicles was 43 percent. c) Uttar Pradesh – 2400 vehicles were procured against a shortage of nearly 10,000 vehicles. |
Residential and non-residential buildings |
§ There were considerable delays in construction of buildings in most states. Consequently, police forces’ own security was in jeopardy. § In states such as: a) Andhra Pradesh – 53 percent of staff quarters and 43 percent of official buildings were not completed (2007). b) Bihar – The total requirement of housing was nearly 60,000. Only six percent of this were included in the Plan. c) Jharkhand – District Control rooms remained non-functional because of shortage of manpower. |
Weapons |
§ Police force in states continue to depend on outdated weapons. § Shortages of weapons also happened as acquisition from ordnance factories was very slow. § The weapons that were procured were mostly kept in the district headquarters. § In some states such as, a) Bihar – AK-47s were kept at the disposal of bodyguards of VIPs. b) West Bengal – Adequate weapons were not supplied to extremist prone police stations. |
Communication |
§ Police Telecommunication Networks were not set up successfully in some states. In others, network was functional only up to the district level. § Shortages of various communication equipments were also observed. § In some states such as, a) Bihar - The Police Telecommunication Network system (costing Rs. 4.96 crore) remained non-functional due to non-construction of tower. b) Maharashtra – Of the 850 purchased Remote Station Units, 452 were lying in stores. |
Forensic Science Laboratory/ Finger Printing Bureau |
§ In most States the Forensic Science Laboratories lacked adequate infrastructure. § In the absence of automatic finger print identification systems, investigation was being done manually in some States. § In some states such as, a) Maharashtra - There were significant delays in receipt and installation. There was also shortage (284 vacant posts) of technical manpower. b) West Bengal - Performance of the Forensic Science Laboratory was poor and in some cases, the delay in issue of investigation reports was as high as 45 months. |
Training |
§ It was observed that the percentage of police personnel trained was very low. § Training infrastructure was also inadequate. § In some states such as, a) Bihar - Only 10 per cent of total force was trained. b) West Bengal - Live training was not imparted for handling useful weapons and this severely affected the performance of police forces. |
Sources: CAG Compendium of Performance Audit Reviews on Modernisation of Police Force; PRS. Note: The audit has been done broadly from 2000 to 2007. Consequently, the period of audit for different states may vary. |
Table 1: Summary of main findings in the CAG audit for different states for Modernisation of State Police Forces |
|
Purpose for which money was sanctioned |
Summary of CAG Findings |
Planning (Every state has to propose an Annual Action Plan every year. The plan is approved by the Ministry of Home Affairs and money is released as per the plan.) |
§ Submissions by the states to the Ministry of Home Affairs (MHA) were delayed. § There were also delays in the clearance granted by the MHA. § In various states such as, a) Andhra Pradesh – the government spent Rs 32 crore on works not covered by the Annual Action Plan. b) Bihar – Persistent delays in preparation of the Plan by the state police. c) West Bengal – the plans drawn up by the state did not include items covered under the scheme. |
Mobility |
§ Overall shortage of vehicles was observed. Most of the new vehicles replaced the old ones, and no additions were made. § The police response time was too long in some states. § To give examples from some states: a) Andhra Pradesh – 58 percent of vehicles procured were utilised for replacing old vehicles. b) Bihar – the shortage of vehicles was 43 percent. c) Uttar Pradesh – 2400 vehicles were procured against a shortage of nearly 10,000 vehicles. 203 ambassador cars were procured, though only 55 were approved by the MHA. |
Residential and non-residential buildings |
§ There were considerable delays in construction of buildings in most states. Consequently, police forces’ own security was in jeopardy. Satisfaction levels with the housing provided were also very low. § In states such as: a) Andhra Pradesh – 53 percent of staff quarters and 43 percent of official buildings were not completed (2007). b) Bihar – The total requirement of housing was nearly 60,000. Only six percent of this were included in the Plan, and only 1045 units were completed by 2006. c) Jharkhand – District Control rooms remained non-functional even after spending Rs 2 crore because of shortage of manpower. |
Weapons |
§ It was observed that the police force in states continue to depend on outdated weapons. § Shortages of weapons also happened as acquisition from ordnance factories was very slow. § The weapons that were procured were mostly kept in the district headquarters. § In some states such as, a) Bihar – AK-47s were kept at the disposal of bodyguards of VIPs. b) West Bengal – Adequate weapons were not supplied to extremist prone police stations. |
Communication |
§ Police Telecommunication Networks were not set up successfully in some states. In others, network was functional only up to the district level. § Shortages of various communication equipments were also observed. § In some states such as, a) Bihar - The Police Telecommunication Network system (costing Rs. 4.96 crore) remained non-functional due to non-construction of tower. b) Maharashtra – Of the 850 purchased Remote Station Units, 452 were lying in stores. |
Forensic Science Laboratory/ Finger Printing Bureau |
§ In most States the Forensic Science Laboratories lacked adequate infrastructure. § In the absence of automatic finger print identification systems, investigation was being done manually in some States. § In some states such as, a) Maharashtra - There were significant delays in receipt and installation. There was also shortage (284 vacant posts) of technical manpower. b) West Bengal - Performance of the Forensic Science Laboratory was poor and in some cases, the delay in issue of investigation reports was as high as 45 months. |
Training |
§ It was observed that the percentage of police personnel trained was very low. § Training infrastructure was also inadequate. § In some states such as, a) Bihar - Only 10 per cent of total force was trained. b) West Bengal - Live training was not imparted for handling useful weapons and this severely affected the performance of police forces. |
Sources: CAG Compendium of Performance Audit Reviews on Modernisation of Police Force; PRS. Note: The audit has been done broadly from 2000 to 2007. Consequently, the period of audit for different states may vary. |
Safety has been one of the biggest concerns in the Indian Railways system. While the number of accidents have gone down over the last few years, the number still remains over 100 accidents a year. In light of the recent train accidents in Uttar Pradesh (UP), we present some details around accidents and safety in the Indian Railways.
Causes of rail accidents
The number of rail accidents has declined from 325 in 2003-04 to 106 in 2015-16.[1] The number of rail accidents as per the cause are shown in the graph below. In 2015-16, majority of the accidents were caused due to derailments (60%), followed by accidents at level crossings (33%).1 In the last decade, accidents caused due to both these causes have reduced by about half. According to news reports, the recent railway accidents in UP were caused due to derailment of coaches.
Derailments
Between 2003-04 and 2015-16, derailments were the second highest reason for casualties.2 The Standing Committee on Railways, when examining the safety in railways, had noted that one of the reasons for derailments is defect in the track or coaches. Of the total track length of 1,14,907 kms in the country, 4,500 kms should be renewed annually.2 However, in 2015-16, of the 5,000 km of track length due for renewal, only 2,700 km was targeted to be renewed.2 The Committee had recommended that Indian Railways should switch completely to the Linke Hoffman Busch (LHB) coaches as they do not pile upon each other during derailments and hence cause lesser casualties.2
Un-manned level crossings
Un-manned level crossings (UMLCs) continue to be the biggest cause of casualties in rail accidents. Currently there are 14,440 UMLCs in the railway network. In 2014-15, about 40% of the accidents occurred at UMLCs, and in 2015-16, about 28%.2 Between 2010 and 2013, the Ministry fell short of meeting their annual targets to eliminate UMLCs. Further, the target of eliminating 1,352 UMLCs was reduced by about 50% to 730 in 2014-15, and 820 in 2015-16.2 Implementation of audio-visual warnings at level crossings has been recommended to warn road users about approaching trains.2 These may include Approaching Train Warning Systems, and Train Actuated Warning Systems.2 The Union Budget 2017-18 proposes to eliminate all unmanned level crossings on broad gauge lines by 2020.
Casualties and compensation
In the last few years, Railways has paid an average compensation of Rs 3.03 crore every year for accidents (see figure below).[2]
Note: Compensation paid during a year relates to the cases settled and not to accidents/casualties during that year.
Consequential train accidents
Accidents in railways may or may not have a significant impact on the overall system. Consequential train accidents are those which have serious repercussions in terms of loss of human life or injury, damage to railway property or interruption to rail traffic. These include collisions, derailments, fire in trains, and similar accidents that have serious repercussions in terms of casualties and damage to property. These exclude cases of trespassing at unmanned railway crossings.
As seen in the figure below, the share of failure of railways staff is the biggest cause of consequential rail accidents. The number of rail accidents due to failure of reasons other than the railway staff (sabotage) has increased in the last few years.
Accidents due to failure of railway staff
It has been noted that more than half of the accidents are due to lapses on the part of railway staff.2 Such lapses include carelessness in working, poor maintenance, adoption of short-cuts, and non-observance of laid down safety rules and procedures. To address these issues, conducting a regular refresher course for each category of railway staff has been recommended.2
Accidents due to loco-pilots2,[3]
Accidents also occur due to signalling errors for which loco-pilots (train-operators) are responsible. With rail traffic increasing, loco-pilots encounter a signal every few kilometres and have to constantly be on high alert. Further, currently no technological support is available to the loco-pilots and they have to keep a vigilant watch on the signal and control the train accordingly.2 These Loco-pilots are over-worked as they have to be on duty beyond their stipulated working hours. This work stress and fatigue puts the life of thousands of commuters at risk and affects the safety of train operations.2 It has been recommended that loco-pilots and other related running staff should be provided with sound working conditions, better medical facilities and other amenities to improve their performance.2
Actions taken by Railways with regard to the recent train accident
According to news reports, the recent accident of Utkal Express in UP resulted in 22 casualties and over 150 injuries.[4] It has also been reported that following this incident, the Railways Ministry initiated action against certain officials (including a senior divisional engineer), and three senior officers (including a General Manager and a Railway Board Member).
The Committee on Restructuring of Railways had noted that currently each Railway zone (headed by a General Manager) is responsible for operation, management, and development of the railway system under its jurisdiction.[5] However, the power to make financial decisions does not rest with the zones and hence they do not possess enough autonomy to generate their own revenue, or take independent decisions.5
While the zones prepare their annual budget, the Railway Board provides the annual financial budget outlay for each of them. As a result of such budgetary control, the GM’s powers have been reduced leaving them with little independence in planning their operations.5
The Committee recommended that the General Managers must be fully empowered to take all necessary decisions independent of the Railway Board.5 Zonal Railways should also have full power for expenditure and re-appropriations and sanctions. This will make each Zonal Railway accountable for its transport output, profitability and safety under its jurisdiction.
Under-investment in railways leading to accidents
In 2012, a Committee headed by Mr. Anil Kakodkar had estimated that the total financial cost of implementing safety measures over the five-year period (2012-17) was likely be around Rs one lakh crore. In the Union Budget 2017-18, the creation of a Rashtriya Rail Sanraksha Kosh was proposed for passenger safety. It will have a corpus of Rs one lakh crore, which will be built over a five-year period (Rs 20,000 crore per year).
The Standing Committee on Railways had noted that slow expansion of rail network has put undue burden on the existing infrastructure leading to severe congestion and safety compromises.2 Since independence, while the rail network has increased by 23%, passenger and freight traffic over this network has increased by 1,344% and 1,642% respectively.2 This suggests that railway lines are severely congested. Further, under-investment in the sector has resulted in congested routes, inability to add new trains, reduction of train speeds, and more rail accidents.2 Therefore, avoiding such accidents in the future would also require significant investments towards capital and maintenance of rail infrastructure.2
Tags: railways, safety, accidents, finances, derailment, casualty, passengers, train
[1] Railways Year Book 2015-16, Ministry of Railways, http://www.indianrailways.gov.in/railwayboard/uploads/directorate/stat_econ/IRSP_2015-16/Year_Book_Eng/8.pdf.
[2] “12th Report: Safety and security in Railways”, Standing Committee on Railways, December 14, 2016, http://164.100.47.193/lsscommittee/Railways/16_Railways_12.pdf.
[3] Report of High Level Safety Review Committee, Ministry of Railways, February 17, 2012.
[4] “Utkal Express derailment: Four railway officials suspended as death toll rises to 22”, The Indian Express, August 20, 2017, http://indianexpress.com/article/india/utkal-express-train-derailment-four-railway-officers-suspended-suresh-prabhu-muzaffarnagar-22-dead-4805532/.
[5] Report of the Committee for Mobilization of Resources for Major Railway Projects and Restructuring of Railway Ministry and Railway Board, Ministry of Railways, June 2015, http://www.indianrailways.gov.in/railwayboard/uploads/directorate/HLSRC/FINAL_FILE_Final.pdf.