The government's acquisition of land for projects has been facing protests across the country, the violence in Uttar Pradesh being only the latest. What is Land Acquisition? Land acquisition is the process by which the government forcibly acquires private property for public purpose without the consent of the land-owner. It is thus different from a land purchase, in which the sale is made by a willing seller. How is this process governed? Land Acquisition is governed by the Land Acquisition Act, 1894.  The government has to follow a process of declaring the land to be acquired, notify the interested persons, and acquire the land after paying due compensation. Various state legislatures have also passed Acts that detail various aspects of the acquisition process. Land is a state subject.  Why is Parliament passing a law? Though land is a state subject, "acquisition and requisitioning of property" is in the concurrent list. Both Parliament and state legislatures can make laws on this subject. Is there a new Act being proposed? The government had introduced a Bill to amend this Act in 2007. That Bill lapsed in 2009 at the time of the general elections. The government has stated its intent to re-introduce a similar Bill, but has not yet done so. What are the major changes being proposed? There are significant changes proposed in the 2007 Bill with regard to (a) the purpose for which land may be acquired; (b) the amount of compensation to be paid; (c) the process of acquisition; (d) use of the land acquired; and (e) dispute settlement mechanisms. We explain these briefly below. Purpose: Currently, land may be acquired for a range of uses such as village sites, town or rural planning, residential purposes for poor or displaced persons, planned development (education, housing, health, slum clearance), and for state corporations. Land may also be acquired for use by private companies for the above purposes or if the work "is likely to prove useful to the public". The 2007 Bill had a narrower list: (a) for strategic naval, military or air force purposes; (b) for public infrastructure projects; and (c) for any purpose useful to the general public if 70% of the land has been purchased from willing sellers through the free market. Compensation: The current Act requires market value to be paid for the land and any other property on it (buildings, trees, irrigation work etc) as well as expenses for compelling the person change place of residence or business. It explicitly prohibits taking into account the intended use of land while computing market value. The 2007 Bill requires payment of the highest of three items: the minimum value specified for stamp duty, the average of the top 50 per cent by price of land sale in the vicinity, and the average of the top 50 pc of the land purchased for the project from willing sellers. For computing recent land sale, the intended land use is to be used. Thus, agricultural land being acquired for an industrial project will be paid the price of industrial land. Process of acquisition: Several changes are proposed, including the requirement of a social impact assessment. Any project that displaces more than 400 families (200 in hilly, tribal and desert areas) will require an SIA before the acquisition is approved. Use of land acquired: The 2007 Bill requires the land acquired to be used for that purpose within five years. If this condition is not met, the land reverts to the government (it is not returned to the original land owners). If any acquired land is transferred to another entity, 80 pc of the capital gains has to be shared with the original land-owners and their legal heirs. Dispute Settlement: Currently, all disputes are resolved by civil courts, which results in delays. The 2007 Bill sets up Land Acquisition Compensation Dispute Resolution Authority at the state and national levels. These authorities will have the power of civil courts, and will adjudicate disputes related to compensation claims. Does the proposed Bill address the major issues? The Bill narrows the uses for which land may be acquired. It also changes the compensation due and links that to the market price for which land is to be used. There could be significant changes in acquisition for use by private industry. Firstly, they would have to purchase at least 70 pc of the required land from willing sellers (presumably, at fair market price). Second, the compensation amount for the remaining (upto 30 pc of land) could be significantly higher than the current method. This would be at a premium to the average paid to the willing sellers, and it would be based on intended industrial or commercial use which usually commands a higher price than agricultural land. However, the effect on acquisition for projects such as highways and railways will not be significant, as there is no benchmark for price determination for such use. This article appeared in Rediff News on May 12, 2011 and can be accessed here.

Recently, the central government launched the Pradhan Mantri Sahaj Bijli Har Ghar Yojana (or Saubhagya).[i],[ii]  The scheme seeks to ensure universal household electrification (in both rural and urban areas) by providing last mile connectivity.  The scheme is expected to cover three crore households.  Note that currently about four crore households are un-electrified.  A rural electrification scheme has also been under implementation since 2005.  In light of this, we discuss the current situation of, and key issues related to rural electrification in the country.

Regulatory and policy framework

Under the Electricity Act, 2003, the central and state governments have the joint responsibility of providing electricity to rural areas.  The 2003 Act also mandates that the central government should, in consultation with the state governments, provide for a national policy on (i) stand-alone power systems for rural areas (systems that are not connected to the electricity grid), and (ii) electrification and local distribution in rural areas.  Consequently, the Rural Electrification Policy was notified in August 2006.[iii]

The Rajiv Gandhi Grameen Vidyutikaran Yojana (RGGVY), launched in 2005, was the first scheme on rural electrification.  In December 2014, Ministry of Power launched the Deendayal Upadhyaya Gram Jyoti Yojana (DDUGJY), which subsumed the RGGVY.[iv]  Components of DDUGJY include: (i) separation of agricultural and non-agricultural electricity feeders to improve supply for consumers in rural areas, (ii) improving sub-transmission and distribution infrastructure in rural areas, and (iii) rural electrification by carrying forward targets specified under the RGGVY.

The total financial outlay for DDUGJY over the implementation period (until 2021-22) is Rs 82,300 crore which includes budgetary support of Rs 68,900 crore.  The central government provides 60% of the project cost as grant, the state power distribution companies (discoms) raise 10% of the funds, and 30% is borrowed from financial institutions and banks.

Status of rural electrification

As of August 2017, about 1% of the villages in India remain un-electrified (3,146 villages).  However, with regard to households, around 23% (4.1 crore households) are yet to be electrified.  Table 1 at the end of this post shows the status of rural electrification across all states.

Issues with rural electrification

Definition of an electrified village

An electrified village is defined as one that has the following: (i) provision of basic infrastructure such as distribution transformers and lines in the inhabited locality, (ii) provision of electricity in public places like schools, panchayat office, health centers, dispensaries, and community centers, and (iii) at least 10% of the total number of households in the village are electrified.[iv]

Therefore, a village is considered to be electrified if 10% of the total number of households in the village have been electrified.  This is apart from the basic infrastructure and electrification of certain public centers in the village.  The Standing Committee on Energy (2013) had observed that according to this definition, a village would be called electrified even if up to 90% of households in it do not have an electricity connection.[v]  It also noted that the infrastructure being provided under the scheme is highly inadequate, unreliable and unsustainable.  The Committee recommended that the actual electrification requirement of villages must be assessed, and it should be ensured that the state discoms provide electricity to the remaining households in the village.

Supply of electricity

The Standing Committee had also noted that while the rural electrification scheme looks at creating infrastructure, the actual supply of electricity to households rests with the state discoms.[v]  These discoms are already facing huge financial losses and hence are unable to supply electricity to the villages.  Discoms continue to supply subsidised power to agricultural and residential consumers, resulting in revenue losses.  Further, the average technical and commercial losses (theft and pilferage of electricity) (AT&C losses) are at around 25%.  While the Ujjwal Discom Assurance Yojana (UDAY) has eased off some of the financial losses of the discoms, it remains to be seen whether discoms are able to reduce the cost-tariff gap and AT&C losses in the future.

It has been recommended that generation capacity should be augmented so that states can meet the additional demand under the rural electrification schemes. Further, the assistance to financially weaker states should be increased so that they can better implement the scheme.[v]

Electricity to below poverty line (BPL) households

Under the rural electrification scheme, the cost for providing free electricity connection per BPL household is Rs 3,000.  It has been observed that this cost per household may be inadequate.[v]  Due to the low cost, the quantity and the quality of work has been getting compromised leading to poor implementation of the scheme.  It has been recommended that the Ministry should revisit the cost provided under the scheme.[v]

The new electrification scheme: Pradhan Mantri Sahaj Bijli Har Ghar Yojana (or Saubhagya)

The new scheme, Saubhagya, seeks to ensure universal household electrification, that is, in both rural and urban areas.  Under Saubhagya, beneficiaries will be identified using the Socio Economic and Caste Census (SECC) 2011 data.  The identified poor households will get free electricity connections.  Other households not covered under the SECC, will be provided electricity connections at a cost of Rs 500.  This amount will be collected by the electricity distribution companies in 10 instalments.

The total outlay of the scheme will be Rs 16,320 crore, of which the central government will provide Rs 12,320 crore.  The outlay for the rural households will be Rs 14,025 crore, of which the centre will provide Rs 10,588 crore.  For urban households the outlay will be Rs 2,295 crore of which the centre will provide Rs. 1,733 crore.

The state discoms will execute the electrification works through contractors or other suitable agencies.  Information technology (mobile apps, web portals) will be used to organise camps in villages to identify beneficiaries.  In order to accelerate the process, applications for electricity connections will be completed on the spot.

So far the focus of electrification schemes has been on rural areas, where typically last mile connectivity has been difficult to provide.  Saubhagya extends the ambit of electrification projects to urban areas as well.  While DDUGJY has focused on the village as the principal unit to measure electrification, the new scheme shifts the targets to household electrification.  While the target for ensuring electricity connection in each household will be a significant step towards ensuring 24×7 power, the question of continuous and quality supply to these households will still rest on the ability of the discoms to provide electricity.  Further, while the scheme provides for free connections, the ability of these households to pay for the electricity they consume may be a concern.

Table 1: Status of rural electrification across states (as of August 2017)

Fig 1 edit

* all villages in Telangana were declared electrified before the bifurcation of the state.
Sources:  Ministry of Power; PRS.

 

[i] “PM launches Pradhan Mantri Sahaj Bijli Har Ghar Yojana “Saubhagya””, Press Information Bureau, Ministry of Power, September 25, 2017.

[ii] “FAQs on Pradhan Mantri Sahaj Bijli Har Ghar Yojana “Saubhagya””, Press Information Bureau, Ministry of Power, September 27, 2017.

[iii].  Rural Electrification Policy, Ministry of Power, August 23, 2006, http://powermin.nic.in/sites/default/files/uploads/RE%20Policy_1.pdf.

[iv].  “Office memorandum: Deendayal Upadhyaya Gram Jyoti Yojana”, Ministry of Power, December 3, 2014, http://powermin.nic.in/rural_electrification/pdf/Deendayal_Upadhyaya_Gram_Jyoti_Yojana.pdf.

[v].  “41st Report: Implementation of Rajiv Gandhi Grameen Vidyutikaran Yojana”, Standing Committee on Energy, December 13, 2013, http://164.100.47.134/lsscommittee/Energy/15_Energy_41.pdf.