Reports suggest that a debt restructuring plan is being prepared for power distribution companies (discoms) in seven states - Uttar Pradesh, Punjab, Rajasthan, Haryana, Andhra Pradesh, Tamil Nadu and Madhya Pradesh.  According to some estimates, the combined outstanding debt for discoms is Rs 2 lakh crore.  Discoms have been facing heavy losses.  According to a Planning Commission Report, the cost of supplying electricity increased at a rate of 7.4 per cent annually between 1998-99 and 2009-10.  The average tariff has also increased at an annual rate of 7.1 per cent over the same period.  However, the report shows that the average tariff per unit of electricity has consistently been much lower than average cost of supply per unit.  Between 2007-08 and 2011-12, the gap between average cost and average tariff per unit of electricity was between 20 and 30 per cent of costs.

Average cost and average tariff per unit of electricity (Rs per kWh)

Year

Unit cost

Average tariff per unit

Gap between cost and tariff

Gap as percentage of unit cost

2007-08

4.04

3.06

0.98

24%

2008-09

4.6

3.26

1.34

29%

2009-10

4.76

3.33

1.43

30%

2010-11

4.84

3.57

1.27

26%

2011-12

4.87

3.8

1.07

22%

Source: “Annual Report 2011-12 on the Working of State Power Utilities and Electricity Departments”, Planning Commission State discoms have been losing money due to higher costs than revenues, as well as high transmission and distribution (T&D) losses.  The commercial losses for discoms in India (after including subsidies) increased from Rs 16,666 crore in 2007-08 to Rs 37,836 crore in 2011-12. Reports suggest that the restructuring plan being prepared will be worth Rs 1.2 lakh crore in short-term liabilities.  Half of the proposed amount would be issued as bonds by the discoms, backed by a state government guarantee.  Banks and financial institutions would reschedule the remaining Rs 60,000 crore of debt, with a moratorium of three years on payment of the principal amount.  State governments that adopt the financial restructuring plan would not recover any loans given to discoms before they start showing profits. Under a proposed transition finance mechanism, the central government would reimburse 25 per cent of the principal amount of bonds to states that fully implement the plan.  Also, states that achieve a reduction in T&D losses above a targeted level in three years may be given grants.  Newspaper reports also suggest that states will have to prepare plans for eliminating the gap between the average cost and average tariff per unit of electricity.

Recently, the government issued letters de-allocating coal blocks of various companies, based on the recommendations of the  Inter Ministerial Group (IMG).  This post discusses the history behind the de-allocations, the parameters the IMG used while examining the progress of various coal blocks and the action that has been taken by the government. The Comptroller and Auditor General (CAG) released a performance audit report on 'Allocation of Coal Blocks and Augmentation of Coal Production' on August 17, 2012.  Some of the key findings of the Report were:

  • The government failed to conduct competitive bids for the allocation of coal blocks.  This resulted in a benefit of  Rs 1.86 lakh crore (approx.) to private allottees.  The government could have tapped some of this financial benefit by expediting the decision on competitive bidding for allocation of coal blocks.
  • The implementation schedule of a number of coal blocks has been delayed by one to ten years.  This schedule relates to the time frame within which the Mining Plan for the block has to be approved, various clearances have to be submitted, land acquired, etc.
  • From 2005, the Ministry of Coal (MoC) required the allottees to provide bank guarantees which would be encashed if they failed to meet the above mentioned milestones.  The CAG observed that there was a delay in introducing the bank guarantee and linking it with milestones.

The IMG on Coal was constituted for the periodic review of the development of coal blocks and end use plants.  The IMG had requested a status paper from the Coal Controller, MoC.  This has been submitted to the IMG but is not available.  The IMG will decide if private allottees have made substantial progress based on certain parameters.  The parameters used by IMG are:  approval of Mining Plan, status of environment and forest clearance, grant of mining lease and progress made in land acquisition. They are also examining the physical status of End Use Plant (EUP), investment made and the expected date of opening of the mine and commissioning of EUP. The IMG has made the following recommendations:

  • The coal blocks of companies that have not made substantial progress should be de-allocated.  Additionally, they have recommended the deduction of bank guarantee in the cases where the private companies have not reached the milestones as per the time line decided upon.  As of November 22, 2012, the IMG has recommended the de-allocation of the coal blocks listed in Table 1 and the deduction of bank guarantees for the coal blocks in Table 2.
  • Since, the system of bank guarantee was only introduced in March 2005, not all coal blocks had submitted a bank guarantee.  Where a bank guarantee has not been provided but there is substantial progress in meeting the milestones, the IMG may require the allottee to submit a bank guarantee.

[table id=1 /]

 

[table id=5 /]

 

Of the coal blocks that the IMG has recommended for de-allocation, until now the government has accepted the de-allocation of the following: Bramhadih block, Gourangdih, New Patrapara, Chinora block, Warora (Southern Part) block, Lalgarh (North) block, Bhaskarpara block, Dahegaon/Makardhokra-IV block, Gondkhari block and Ramanwara North block.  The government has accepted the deduction of bank guarantees for blocks such as Moitra, Jitpur, Bhaskarpara, Durgapur II/Sariya, Dahegaon/Makardhokra-IV, Marki Mangli II, III and IV, Gondhkari, Lohari, Radhikapur East, Bijahan and Nerad Malegaon. The letters issued by the government de-allocating coal blocks and deducting bank guarantees are available here.

For a detailed summary of the CAG Report, click here.