The 2010 Commonwealth Games may have ended on October 14th, but the controversy surrounding the organising of the games is far from over. In Parliament, the Opposition has called for a Joint-Parliamentary Committee (JPC) to be formed to investigate suspected financial irregularities in the organising of the Games[1]. In a statement in Parliament on Tuesday, Minister for Youth Affairs & Sports M.S. Gill commented that “All irregularities will be examined and the guilty will not be spared”[2]. In July 2010, the Central Vigilance Commission (CVC) found irregularities in 14 Games related construction projects[3]. It has been reported that officials from the CVC now believe total misappropriation of Games Funds could be between Rs 5000 crore and Rs 8000 crore [4]. So what is being done about it? Currently, six different government organisations are conducting independent inquiries into financial irregularities, corruption, and mismanagement of the Games: the High Level (Shunglu) Commission, CVC, CAG, CBI, Income Tax Department, and Enforcement Directorate (ED).  With so many government organisations involved, it can be difficult to decipher the big picture. Here is a breakdown of what each organisation is doing: High Level Commission (Shunglu Commission): The Commission was appointed by the Prime Minister on October 15th[5]. It is chaired by V.K. Shunglu, former Comptroller and Auditor General of India, who has been given the status equivalent to a Supreme Court Judge[6]. The Commission has a broad mandate to investigate all matters regarding the Games, specifically:[7]

  • Roles and responsibilities of signatories to Host City Contract
  • Planning and execution of development projects and contracts
  • Effectiveness of organisational structure and governance for agencies involved
  • Managerial weaknesses
  • All financial aspects of the event, including wrongdoing
  • Coordination issues amongst agencies
  • Role of advisors and consultants to Organising Committee
  • Overall impact of the games
  • Lessons learnt for the future

A report from the Commission detailing its findings is expected by mid January. Central Vigilance Commission (CVC): The CVC first found financial irregularities in 14 Games projects in July 2010.  Subsequently, it asked the CBI to register a corruption case against MCD officials in connection with a tender issued for a Games project[8]. In total, the CVC has found irregularities in 38 games related projects, under the following departments and agencies:[9]

  • Ministry of Youth Affairs & Sports: 6
  • Delhi Development Authority: 6
  • Public Works Department: 6
  • Municipal Corporation of Delhi: 5
  • Central Public Works Department: 4
  • Organising Committee: 3
  • New Delhi Municipal Council: 3
  • Government of Delhi: 2
  • Department of Commerce: 1
  • Indian Meteorological Department: 1
  • RITES: 1

The CVC has directed the above agencies to respond to queries regarding the irregularities and has directed the CBI to begin a Preliminary Inquiry into them [10]. The CVC will report its findings to the Shunglu Commission. Income Tax Department: The I-T Department is investigating tenders and awards of contracts for Games related works, as well as tax evasion [11]. It has conducted raids in offices of over 30 business firms and individuals [12]. Enforcement Directorate (ED): The ED is proceeding against Organising Committee officials for violations of the Foreign Exchange Management Act (FEMA) for projects involving venue development and overlays contracts awarded by the Organising Committee. Central Bureau of Investigation (CBI): It has been reported that the CBI had received over 300 complaints of corruption in Games projects by August 2010[13]. It is verifying these claims and investigating matters highlighted by the CVC. Comptroller and Auditor General (CAG): In August 2009, the CAG published a report entitled Preparedness for the XIX Commonwealth Games highlighting the lack of preparedness for the Games and its escalating cost.  The CAG is conducting a detailed audit of the Games that is expected to be published in March 2011[14]. Given that CAG reports are tabled in Parliament, the March 2011 report will be critical to the Parliamentary debate on the Games. Two members of the Organising Committee, the Joint Director and the Deputy Director General, were arrested by the CBI this past Monday.  However, Given that the report of the Shunglu Commssion is due in January 2011, the CAG audit will follow two months later, and the current Opposition demand for a JPC remains unresolved, it may be some time before significant details are made public.


[1] http://economictimes.indiatimes.com/news/politics/nation/BJP-to-press-for-JPC-probe-into-spectrum-Adarsh-CWG-scams/articleshow/6934697.cms [2] http://www.thehindu.com/news/article890174.ece [3] ttp://economictimes.indiatimes.com/news/news-by-industry/et-cetera/CVC-finds-irregularities-in-several-CWG-projects/articleshow/6229429.cms [4] http://www.deccanherald.com/content/105830/cwg-fraud-may-touch-rs.html [5] http://www.business-standard.com/india/news/games-over-pm-orders-probe-into-pre-event-mess/411739/ [6] http://economictimes.indiatimes.com/news/politics/nation/CWG-probe-Shunglu-given-status-of-SC-judge/articleshow/6818404.cms [7] http://pib.nic.in/newsite/PrintRelease.aspx?relid=66561 [8] http://timesofindia.indiatimes.com/city/delhi/CWG-construction-CVC-asks-CBI-to-register-corruption-case/articleshow/6237714.cms [9] http://www.hindustantimes.com/specials/sports/cwg-2010/22-more-CWG-works-under-CVC-scanner/CWG2010-TopStories/SP-Article10-614446.aspx [10] http://www.indianexpress.com/news/Claiming-fraud---favour-in-Games-rentals--CVC-to-CBI--begin-probe/700998/ [11]http://www.indianexpress.com/news/it-dept-collects-cwg-works-related-documents/698683/ [12] http://www.thehindu.com/news/national/article837892.ece [13] http://www.indianexpress.com/news/cbi-has-over-300-complaints-regarding-games-works/655692/ [14] http://economictimes.indiatimes.com/news/politics/nation/CAG-starts-Commonwealth-Games-audit-report-by-March-2011/articleshow/6252852.cms

The Minister of Railways, Dinesh Trivedi, presented the Railways Budget 2012 to Parliament on 14th March.  While commenting on the financial position of Railways, the Minister said that 'the Indian Railways are passing through a difficult phase'. The Operating Ratio for the closing year is now estimated to equal 95%. This is significantly higher than the 91.1% figure budgeted last year. Operating Ratio is a metric that compares operating expenses to revenues. A higher ratio indicates lower ability to generate surplus. Surplus is used for capital investments such as laying of new lines, deploying more coaches etc. Therefore, a smaller surplus affects the Railway’s capability to make such investments. Budget v/s Revised estimates 2011-12 Budget 2011-12 had estimated the performance of Railways for the financial year. Revised estimates have now been submitted. Taken together, these two figures help in comparing actual performance against targets. Some observations are enumerated below:

  • Total receipts decreased by Rs 2,746 crore.
  • Total expenditure increased by Rs 2,102 crore.
  • Operating Ratio increased from 91.1% to 95%. This implies a decrease in surplus.
  • Appropriations to the ‘Development Fund’ and the ‘Capital Fund’ decreased from Rs 5,258 crore to Rs 1,492 crore (a decrease of 72%). The ‘Development Fund’ finances expenditure such as passenger amenities; the ‘Capital Fund’ is used for capital augmentation such as laying of new lines.

Budget estimates 2012-13 In 2012-13, Railways plan to improve Operating Ratio to 84.9% and to increase surplus to Rs 15,557 crore. This is more than 10 times the surplus generated in 2011-12 (Revised Estimates). The effective increase in freight rates is estimated to average 23%. During this time, passenger fares are also estimated to increase by an effective average rate of 19%. [1] Infrastructure Performance during the 11th Plan Under the 11th Five Year Plan, the total plan expenditure for Railways had been approved at Rs 2,33,289 crore. The Outcome Budget shows that the actual expenditure is only likely to be Rs 1,92,291 crore. Thus, expenditure will fall short by Rs 40,998 crore. This gaps exists despite a significant increase in the Gross Budgetary Support approved by Parliament. Plan expenditure during 2007-12 (In Rs Crore)

 

Approved Expenditure

Actual Expenditure

Gross Budgetary Support

63,635

75,979

Internal Resources

90,000

67,763

Extra Budgetary Support

79,654

48,549

Total

2,33,289

1,92,291

The Standing Committee on Railways, in its 11th report presented in August 2011, had sought an explanation from the Ministry. According to the Ministry, lower mobilization of internal resources and lack of extra budgetary support are the main reasons for the shortfall.  Internal resource mobilization has been low because of (i) impact of the 6th Pay Commission; and (ii) slow growth in freight earnings due to the economic slowdown. Extra budgetary resources have been low due to non-materialization of funds through the Public-Private Partnership route. Proposals for the 12th Plan Two recent committees – Kakodkar Committee on Railway Safety and the Pitroda Committee on Railway Modernization – have called for large investments in the next five years. The Kakodkar Committee has recommended an investment of Rs 1,00,000 crore in the next five years to improve safety; the Pitroda Committee has recommended an expenditure of Rs 3,96,000 crore in the next five years on modernization. The Railway sub-group of the 12th Five Year Plan has also estimated a requirement of Rs 4,42,744 crore for various other investments proposed to be undertaken during the Plan period. [2] All three groups have called for significant investments in infrastructure augmentation in the next five years. Budget proposals 2012-13 According to the Minister’s speech, the Annual Plan outlay for the year 2012-13 has been set at Rs 60,100 crore. The plan would be financed through:

  • Gross Budgetary Support of Rs 24,000 crore
  • Railway Safety Fund of Rs 2,000 crore
  • Internal Resources of Rs 18,050 crore
  • Extra Budgetary Resources of Rs 16,050 crore. Of this, Rs 15,000 crore would be borrowed from the market through IRFC (Indian Railway Finance Corporation).

What happens now? The Budget is likely to be discussed in the two Houses within the next few days.  Post the discussion, the Ministry's proposals will be put to vote.  Once passed, the Ministry can put its proposals into action. For more details on the Railway Budget, including the projects proposed this year and the status of proposals made last year, please see our analysis here. To understand some of the challenges faced by the Indian Railways, see our blog post from last year. Notes: [1] The ‘effective average fare’ has been calculated by dividing the total income from the segment (freight/ passenger) by the total traffic (in NTKM/ PKM).  This would vary with changes in fares as well as the usage by different categories of users (including the proportion of tickets booked through Tatkal). [2] Source: Report of the Expert Group on Railway Modernization (Chairman: Sam Pitroda)