The 2010 Commonwealth Games may have ended on October 14th, but the controversy surrounding the organising of the games is far from over. In Parliament, the Opposition has called for a Joint-Parliamentary Committee (JPC) to be formed to investigate suspected financial irregularities in the organising of the Games[1]. In a statement in Parliament on Tuesday, Minister for Youth Affairs & Sports M.S. Gill commented that “All irregularities will be examined and the guilty will not be spared”[2]. In July 2010, the Central Vigilance Commission (CVC) found irregularities in 14 Games related construction projects[3]. It has been reported that officials from the CVC now believe total misappropriation of Games Funds could be between Rs 5000 crore and Rs 8000 crore [4]. So what is being done about it? Currently, six different government organisations are conducting independent inquiries into financial irregularities, corruption, and mismanagement of the Games: the High Level (Shunglu) Commission, CVC, CAG, CBI, Income Tax Department, and Enforcement Directorate (ED).  With so many government organisations involved, it can be difficult to decipher the big picture. Here is a breakdown of what each organisation is doing: High Level Commission (Shunglu Commission): The Commission was appointed by the Prime Minister on October 15th[5]. It is chaired by V.K. Shunglu, former Comptroller and Auditor General of India, who has been given the status equivalent to a Supreme Court Judge[6]. The Commission has a broad mandate to investigate all matters regarding the Games, specifically:[7]

  • Roles and responsibilities of signatories to Host City Contract
  • Planning and execution of development projects and contracts
  • Effectiveness of organisational structure and governance for agencies involved
  • Managerial weaknesses
  • All financial aspects of the event, including wrongdoing
  • Coordination issues amongst agencies
  • Role of advisors and consultants to Organising Committee
  • Overall impact of the games
  • Lessons learnt for the future

A report from the Commission detailing its findings is expected by mid January. Central Vigilance Commission (CVC): The CVC first found financial irregularities in 14 Games projects in July 2010.  Subsequently, it asked the CBI to register a corruption case against MCD officials in connection with a tender issued for a Games project[8]. In total, the CVC has found irregularities in 38 games related projects, under the following departments and agencies:[9]

  • Ministry of Youth Affairs & Sports: 6
  • Delhi Development Authority: 6
  • Public Works Department: 6
  • Municipal Corporation of Delhi: 5
  • Central Public Works Department: 4
  • Organising Committee: 3
  • New Delhi Municipal Council: 3
  • Government of Delhi: 2
  • Department of Commerce: 1
  • Indian Meteorological Department: 1
  • RITES: 1

The CVC has directed the above agencies to respond to queries regarding the irregularities and has directed the CBI to begin a Preliminary Inquiry into them [10]. The CVC will report its findings to the Shunglu Commission. Income Tax Department: The I-T Department is investigating tenders and awards of contracts for Games related works, as well as tax evasion [11]. It has conducted raids in offices of over 30 business firms and individuals [12]. Enforcement Directorate (ED): The ED is proceeding against Organising Committee officials for violations of the Foreign Exchange Management Act (FEMA) for projects involving venue development and overlays contracts awarded by the Organising Committee. Central Bureau of Investigation (CBI): It has been reported that the CBI had received over 300 complaints of corruption in Games projects by August 2010[13]. It is verifying these claims and investigating matters highlighted by the CVC. Comptroller and Auditor General (CAG): In August 2009, the CAG published a report entitled Preparedness for the XIX Commonwealth Games highlighting the lack of preparedness for the Games and its escalating cost.  The CAG is conducting a detailed audit of the Games that is expected to be published in March 2011[14]. Given that CAG reports are tabled in Parliament, the March 2011 report will be critical to the Parliamentary debate on the Games. Two members of the Organising Committee, the Joint Director and the Deputy Director General, were arrested by the CBI this past Monday.  However, Given that the report of the Shunglu Commssion is due in January 2011, the CAG audit will follow two months later, and the current Opposition demand for a JPC remains unresolved, it may be some time before significant details are made public.


[1] http://economictimes.indiatimes.com/news/politics/nation/BJP-to-press-for-JPC-probe-into-spectrum-Adarsh-CWG-scams/articleshow/6934697.cms [2] http://www.thehindu.com/news/article890174.ece [3] ttp://economictimes.indiatimes.com/news/news-by-industry/et-cetera/CVC-finds-irregularities-in-several-CWG-projects/articleshow/6229429.cms [4] http://www.deccanherald.com/content/105830/cwg-fraud-may-touch-rs.html [5] http://www.business-standard.com/india/news/games-over-pm-orders-probe-into-pre-event-mess/411739/ [6] http://economictimes.indiatimes.com/news/politics/nation/CWG-probe-Shunglu-given-status-of-SC-judge/articleshow/6818404.cms [7] http://pib.nic.in/newsite/PrintRelease.aspx?relid=66561 [8] http://timesofindia.indiatimes.com/city/delhi/CWG-construction-CVC-asks-CBI-to-register-corruption-case/articleshow/6237714.cms [9] http://www.hindustantimes.com/specials/sports/cwg-2010/22-more-CWG-works-under-CVC-scanner/CWG2010-TopStories/SP-Article10-614446.aspx [10] http://www.indianexpress.com/news/Claiming-fraud---favour-in-Games-rentals--CVC-to-CBI--begin-probe/700998/ [11]http://www.indianexpress.com/news/it-dept-collects-cwg-works-related-documents/698683/ [12] http://www.thehindu.com/news/national/article837892.ece [13] http://www.indianexpress.com/news/cbi-has-over-300-complaints-regarding-games-works/655692/ [14] http://economictimes.indiatimes.com/news/politics/nation/CAG-starts-Commonwealth-Games-audit-report-by-March-2011/articleshow/6252852.cms

According to news reports, the Supreme Court stayed a Calcutta High Court judgement on the Singur Land Rehabilitation and Development Act, 2011 [Singur Act] on August 24, 2012. The apex court also issued a notice to Tata Motors seeking its response within four weeks, on the West Bengal government's petition challenging the High Court order. In 2008, the Left Front government acquired land in Singur under the Land Acquisition Act, 1894, for Tata Motors to build a Nano car factory.  In its first year of coming to power in West Bengal, the Trinamool Congress (TMC) led government notified the Singur Act through which it sought to reclaim this land to return a portion of it to farmers. On June 22, 2012, a Division bench of the Calcutta High Court struck down the Singur Act terming it unconstitutional and void.  In its judgment, the Court found some sections of the Singur Act to be in conflict with the central Land Acquisition Act, 1894.  As land acquisition is a Concurrent List subject under the Constitution, both Parliament and state legislatures have the power to make laws on it.  However, if provisions in the state law conflict with provisions in the central law, then the state law cannot prevail unless it receives Presidential assent.  The Calcutta High Court held the Singur Act to be unconstitutional because: (a) it was in conflict with the central Land Acquisition Act, 1894, and (b) Presidential assent was not obtained for the Act to prevail in West Bengal. The central Act mentions that for the government to acquire land, it has to demonstrate: (1) that land is being acquired for a public purpose,[i] and (2) that the government will provide compensation to persons from whom land is being acquired.  Provisions in the Singur Act that relate to public purpose and compensation were found to be in conflict with the corresponding provisions in the central Act.  The Court was of the opinion that transfer of land to the farmers does not constitute ‘public purpose’ as defined in the central Act.  As argued by the Tata Motors’ counsel, return of land to unwilling owners is a ‘private purpose’ or in ‘particular interest of individuals’ rather than in the ‘general interest of the community’.  Second, clauses pertaining to compensation to Tata Motors for their investment in the Nano project were found to be vague.  The Singur Act only provides for the refund of the amount paid by Tata Motors and the vendors to the state government for leasing the land.  It does not provide for the payment of any other amount of money for acquiring the Tata Motors’ land nor the principles for the determination of such an amount.  The High Court ordered that these provisions tantamount to ‘no compensation’ and struck down the related provisions. The matter will come up for consideration in the Supreme Court next on October 15, 2012.


[i] According to Section 3 of the Land Acquisition Act, 1894, acquisition of land for ‘public purpose’ includes, among others: provision or planned development of village sites; provision of land for town or rural planning; the provision of land for planned development of land from public funds in pursuance of a scheme or policy of the Government; and the provision of land for a corporation owned or controlled by the State.