The 2010 Commonwealth Games may have ended on October 14th, but the controversy surrounding the organising of the games is far from over. In Parliament, the Opposition has called for a Joint-Parliamentary Committee (JPC) to be formed to investigate suspected financial irregularities in the organising of the Games[1]. In a statement in Parliament on Tuesday, Minister for Youth Affairs & Sports M.S. Gill commented that “All irregularities will be examined and the guilty will not be spared”[2]. In July 2010, the Central Vigilance Commission (CVC) found irregularities in 14 Games related construction projects[3]. It has been reported that officials from the CVC now believe total misappropriation of Games Funds could be between Rs 5000 crore and Rs 8000 crore [4]. So what is being done about it? Currently, six different government organisations are conducting independent inquiries into financial irregularities, corruption, and mismanagement of the Games: the High Level (Shunglu) Commission, CVC, CAG, CBI, Income Tax Department, and Enforcement Directorate (ED).  With so many government organisations involved, it can be difficult to decipher the big picture. Here is a breakdown of what each organisation is doing: High Level Commission (Shunglu Commission): The Commission was appointed by the Prime Minister on October 15th[5]. It is chaired by V.K. Shunglu, former Comptroller and Auditor General of India, who has been given the status equivalent to a Supreme Court Judge[6]. The Commission has a broad mandate to investigate all matters regarding the Games, specifically:[7]

  • Roles and responsibilities of signatories to Host City Contract
  • Planning and execution of development projects and contracts
  • Effectiveness of organisational structure and governance for agencies involved
  • Managerial weaknesses
  • All financial aspects of the event, including wrongdoing
  • Coordination issues amongst agencies
  • Role of advisors and consultants to Organising Committee
  • Overall impact of the games
  • Lessons learnt for the future

A report from the Commission detailing its findings is expected by mid January. Central Vigilance Commission (CVC): The CVC first found financial irregularities in 14 Games projects in July 2010.  Subsequently, it asked the CBI to register a corruption case against MCD officials in connection with a tender issued for a Games project[8]. In total, the CVC has found irregularities in 38 games related projects, under the following departments and agencies:[9]

  • Ministry of Youth Affairs & Sports: 6
  • Delhi Development Authority: 6
  • Public Works Department: 6
  • Municipal Corporation of Delhi: 5
  • Central Public Works Department: 4
  • Organising Committee: 3
  • New Delhi Municipal Council: 3
  • Government of Delhi: 2
  • Department of Commerce: 1
  • Indian Meteorological Department: 1
  • RITES: 1

The CVC has directed the above agencies to respond to queries regarding the irregularities and has directed the CBI to begin a Preliminary Inquiry into them [10]. The CVC will report its findings to the Shunglu Commission. Income Tax Department: The I-T Department is investigating tenders and awards of contracts for Games related works, as well as tax evasion [11]. It has conducted raids in offices of over 30 business firms and individuals [12]. Enforcement Directorate (ED): The ED is proceeding against Organising Committee officials for violations of the Foreign Exchange Management Act (FEMA) for projects involving venue development and overlays contracts awarded by the Organising Committee. Central Bureau of Investigation (CBI): It has been reported that the CBI had received over 300 complaints of corruption in Games projects by August 2010[13]. It is verifying these claims and investigating matters highlighted by the CVC. Comptroller and Auditor General (CAG): In August 2009, the CAG published a report entitled Preparedness for the XIX Commonwealth Games highlighting the lack of preparedness for the Games and its escalating cost.  The CAG is conducting a detailed audit of the Games that is expected to be published in March 2011[14]. Given that CAG reports are tabled in Parliament, the March 2011 report will be critical to the Parliamentary debate on the Games. Two members of the Organising Committee, the Joint Director and the Deputy Director General, were arrested by the CBI this past Monday.  However, Given that the report of the Shunglu Commssion is due in January 2011, the CAG audit will follow two months later, and the current Opposition demand for a JPC remains unresolved, it may be some time before significant details are made public.


[1] http://economictimes.indiatimes.com/news/politics/nation/BJP-to-press-for-JPC-probe-into-spectrum-Adarsh-CWG-scams/articleshow/6934697.cms [2] http://www.thehindu.com/news/article890174.ece [3] ttp://economictimes.indiatimes.com/news/news-by-industry/et-cetera/CVC-finds-irregularities-in-several-CWG-projects/articleshow/6229429.cms [4] http://www.deccanherald.com/content/105830/cwg-fraud-may-touch-rs.html [5] http://www.business-standard.com/india/news/games-over-pm-orders-probe-into-pre-event-mess/411739/ [6] http://economictimes.indiatimes.com/news/politics/nation/CWG-probe-Shunglu-given-status-of-SC-judge/articleshow/6818404.cms [7] http://pib.nic.in/newsite/PrintRelease.aspx?relid=66561 [8] http://timesofindia.indiatimes.com/city/delhi/CWG-construction-CVC-asks-CBI-to-register-corruption-case/articleshow/6237714.cms [9] http://www.hindustantimes.com/specials/sports/cwg-2010/22-more-CWG-works-under-CVC-scanner/CWG2010-TopStories/SP-Article10-614446.aspx [10] http://www.indianexpress.com/news/Claiming-fraud---favour-in-Games-rentals--CVC-to-CBI--begin-probe/700998/ [11]http://www.indianexpress.com/news/it-dept-collects-cwg-works-related-documents/698683/ [12] http://www.thehindu.com/news/national/article837892.ece [13] http://www.indianexpress.com/news/cbi-has-over-300-complaints-regarding-games-works/655692/ [14] http://economictimes.indiatimes.com/news/politics/nation/CAG-starts-Commonwealth-Games-audit-report-by-March-2011/articleshow/6252852.cms

In recent news reports there have been deliberations on whether there is a possibility of appealing a central government decision on forest clearances.  In this context, the National Green Tribunal (NGT) has directed states to comply with the statutory requirement of passing an order notifying diversion of forest land for non-forest purposes.  It has also held that it can hear appeals from the orders of state governments and other authorities on forest clearances. The NGT was established in 2010 to deal with cases relating to environmental protection, and conservation of forests and other natural resources.  The need was felt to have a mechanism to hear appeals filed by aggrieved citizens against government orders on forest clearances.  For instance, the NGT can hear appeals against an order of the appellate authority, state government or pollution control board under the Water (Prevention and Control of Pollution) Act, 1974. How is a forest clearance obtained? Obtaining a forest clearance is a key step in the process of setting up a project.  Recently the Chhatrasal coal mine allotted to Reliance Power's 4,000 MW Sasan thermal power project in Madhya Pradesh has received forest clearance.  The Ministry of Environment and Forests (MoEF) first gives ‘in-principle’ approval to divert forest land for non-forest purposes based on the recommendations of the Forest Advisory Committee.  This approval is subject to the project developer complying with certain conditions.  Once these conditions are complied with, the central government issues the final clearance.  It is only after this clearance that the state government passes an order notifying the diversion of forest land.  The NGT’s decision deals with this point in the process during which an appeal can be filed against the order of forest clearance.  For the flowchart put out by the MoEF on the procedure for obtaining a forest clearance, see here. What was the NGT’s ruling on forest clearances? The NGT was hearing an appeal against a forest clearance given by the MoEF to divert 61 hectares of forest land for a hydroelectric project by GMR in Uttarakhand.  The NGT has ruled  that it does not have the jurisdiction to hear appeals against forest clearances given to projects by the MoEF.  However, the NGT has the power to hear appeals on an order or decision made by a state government or other authorities under the Forest (Conservation) Act, 1980.  The judgment observed that though Section 2 of the Forest (Conservation) Act, 1980 requires that state governments pass separate orders notifying the diversion of land, this requirement is not being followed.  The NGT has directed that state governments pass a reasoned order notifying the diversion of the forest land for non-forest purposes, immediately after the central government has given its clearance.  This will allow aggrieved citizens to challenge the forest clearance of a project after the state government has passed an order.  Additionally, the NGT has also directed the MoEF to issue a notification streamlining the procedure to be adopted by state governments and other authorities for passing orders granting forest clearance under section 2 of the Forest (Conservation) Act, 1980. There are some concerns that an appeal to the NGT can only be made after the state government has passed an order notifying the diversion of forest land and significant resources have been invested in the project. What is the status of applications for forest clearances made to the MoEF? The MoEF has given approval to 1126 proposals that involve the diversion of 15,639 hectares of forest land from July 13, 2011 to July 12, 2012.  The category of projects accorded the most number of approvals was road projects (308) followed by transmission lines (137).  Some of the other categories of projects that received clearance for a significant number of projects were mining, hydel and irrigation projects.  However, most land was diverted for mining related projects i.e., 40% of the total forest land diverted in this period.  Figure 1 shows a break up of the extent of forest land diverted for various categories of projects.  The number of forest clearances pending for decision by the MoEF for applications made in the years 2012, 2011 and 2010 are 197, 129 and 48 respectively. [i]

Source: “Environmental Clearance accorded from 13.07.2011 to 12.07.2012”, October 12, 2012, MoEF.

 

  [1] MoEF,  Rajya Sabha, Unstarred Question no. 2520, September 4, 2012