The 2010 Commonwealth Games may have ended on October 14th, but the controversy surrounding the organising of the games is far from over. In Parliament, the Opposition has called for a Joint-Parliamentary Committee (JPC) to be formed to investigate suspected financial irregularities in the organising of the Games[1]. In a statement in Parliament on Tuesday, Minister for Youth Affairs & Sports M.S. Gill commented that “All irregularities will be examined and the guilty will not be spared”[2]. In July 2010, the Central Vigilance Commission (CVC) found irregularities in 14 Games related construction projects[3]. It has been reported that officials from the CVC now believe total misappropriation of Games Funds could be between Rs 5000 crore and Rs 8000 crore [4]. So what is being done about it? Currently, six different government organisations are conducting independent inquiries into financial irregularities, corruption, and mismanagement of the Games: the High Level (Shunglu) Commission, CVC, CAG, CBI, Income Tax Department, and Enforcement Directorate (ED).  With so many government organisations involved, it can be difficult to decipher the big picture. Here is a breakdown of what each organisation is doing: High Level Commission (Shunglu Commission): The Commission was appointed by the Prime Minister on October 15th[5]. It is chaired by V.K. Shunglu, former Comptroller and Auditor General of India, who has been given the status equivalent to a Supreme Court Judge[6]. The Commission has a broad mandate to investigate all matters regarding the Games, specifically:[7]

  • Roles and responsibilities of signatories to Host City Contract
  • Planning and execution of development projects and contracts
  • Effectiveness of organisational structure and governance for agencies involved
  • Managerial weaknesses
  • All financial aspects of the event, including wrongdoing
  • Coordination issues amongst agencies
  • Role of advisors and consultants to Organising Committee
  • Overall impact of the games
  • Lessons learnt for the future

A report from the Commission detailing its findings is expected by mid January. Central Vigilance Commission (CVC): The CVC first found financial irregularities in 14 Games projects in July 2010.  Subsequently, it asked the CBI to register a corruption case against MCD officials in connection with a tender issued for a Games project[8]. In total, the CVC has found irregularities in 38 games related projects, under the following departments and agencies:[9]

  • Ministry of Youth Affairs & Sports: 6
  • Delhi Development Authority: 6
  • Public Works Department: 6
  • Municipal Corporation of Delhi: 5
  • Central Public Works Department: 4
  • Organising Committee: 3
  • New Delhi Municipal Council: 3
  • Government of Delhi: 2
  • Department of Commerce: 1
  • Indian Meteorological Department: 1
  • RITES: 1

The CVC has directed the above agencies to respond to queries regarding the irregularities and has directed the CBI to begin a Preliminary Inquiry into them [10]. The CVC will report its findings to the Shunglu Commission. Income Tax Department: The I-T Department is investigating tenders and awards of contracts for Games related works, as well as tax evasion [11]. It has conducted raids in offices of over 30 business firms and individuals [12]. Enforcement Directorate (ED): The ED is proceeding against Organising Committee officials for violations of the Foreign Exchange Management Act (FEMA) for projects involving venue development and overlays contracts awarded by the Organising Committee. Central Bureau of Investigation (CBI): It has been reported that the CBI had received over 300 complaints of corruption in Games projects by August 2010[13]. It is verifying these claims and investigating matters highlighted by the CVC. Comptroller and Auditor General (CAG): In August 2009, the CAG published a report entitled Preparedness for the XIX Commonwealth Games highlighting the lack of preparedness for the Games and its escalating cost.  The CAG is conducting a detailed audit of the Games that is expected to be published in March 2011[14]. Given that CAG reports are tabled in Parliament, the March 2011 report will be critical to the Parliamentary debate on the Games. Two members of the Organising Committee, the Joint Director and the Deputy Director General, were arrested by the CBI this past Monday.  However, Given that the report of the Shunglu Commssion is due in January 2011, the CAG audit will follow two months later, and the current Opposition demand for a JPC remains unresolved, it may be some time before significant details are made public.


[1] http://economictimes.indiatimes.com/news/politics/nation/BJP-to-press-for-JPC-probe-into-spectrum-Adarsh-CWG-scams/articleshow/6934697.cms [2] http://www.thehindu.com/news/article890174.ece [3] ttp://economictimes.indiatimes.com/news/news-by-industry/et-cetera/CVC-finds-irregularities-in-several-CWG-projects/articleshow/6229429.cms [4] http://www.deccanherald.com/content/105830/cwg-fraud-may-touch-rs.html [5] http://www.business-standard.com/india/news/games-over-pm-orders-probe-into-pre-event-mess/411739/ [6] http://economictimes.indiatimes.com/news/politics/nation/CWG-probe-Shunglu-given-status-of-SC-judge/articleshow/6818404.cms [7] http://pib.nic.in/newsite/PrintRelease.aspx?relid=66561 [8] http://timesofindia.indiatimes.com/city/delhi/CWG-construction-CVC-asks-CBI-to-register-corruption-case/articleshow/6237714.cms [9] http://www.hindustantimes.com/specials/sports/cwg-2010/22-more-CWG-works-under-CVC-scanner/CWG2010-TopStories/SP-Article10-614446.aspx [10] http://www.indianexpress.com/news/Claiming-fraud---favour-in-Games-rentals--CVC-to-CBI--begin-probe/700998/ [11]http://www.indianexpress.com/news/it-dept-collects-cwg-works-related-documents/698683/ [12] http://www.thehindu.com/news/national/article837892.ece [13] http://www.indianexpress.com/news/cbi-has-over-300-complaints-regarding-games-works/655692/ [14] http://economictimes.indiatimes.com/news/politics/nation/CAG-starts-Commonwealth-Games-audit-report-by-March-2011/articleshow/6252852.cms

Recently, the Parliament passed a law that addresses the issue of sexual harassment in the work place.  The Bill, introduced in the Lok Sabha on December 7, 2010, drew on the 1997 judgment of the Supreme Court (known as the Vishaka judgment) to codify measures that employers need to take to address sexual harassment at the work place. (See PRS analysis of the Bill here). The Bill was first passed in the Lok Sabha on September 3, 2011.  It incorporated many of the amendments recommended by the Standing Committee on Human Resource Development that examined the Bill.  The Rajya Sabha passed it on February 27, 2013 without any new amendments (see Bill as passed by Parliament). We compare the key provisions of the Bill, the Standing Committee recommendations and the Bill that was passed by Parliament (for a detailed comparison, see here).

Bill as introduced Standing Committee recommendations Bill as passed by Parliament

Clause 2: Status of domestic workers

Excludes domestic workers from the protection of the Bill. The definition should include (i)  domestic workers; and (ii) situations involving ‘victimization’; Includes domestic worker. Does not include victimisation.

Clause 4: Constitution of Internal Complaints Committee (ICC)

The committee shall include 4 members: a senior woman employee, two or more employees and one member from an NGO committed to the cause of women. The strength of ICC should be increased from 4 to at least 5 (or an odd number) to facilitate decisions in cases where the bench is divided. Disqualifies a member if (a) he has been convicted of an offence or an inquiry is pending against him or (b) he is found guilty in disciplinary proceedings or a disciplinary proceeding is pending against him.
Members may not engage in any paid employment outside the office. Barring paid employment outside the office goes against NGO members who may be employed elsewhere. This clause must be edited. Deletes the provision that disallows NGO members to engage in paid employment outside.  NGO members to be paid fees or allowances.

Clause 6: Constitution and jurisdiction of Local Complaints Committee (LCC)

An LCC is required to be constituted in every district and additional LLCs at block level.  At the block level the additional LCC will address complaints where the complainant does not have recourse to an ICC or where the complaint is against the employer. The functions of the district level and the block level LCCs are not delineated clearly. It is also unclear whether the block level LCCs are temporary committees constituted for dealing with specific cases. Instead of creating additional LCCs at the block level, the District level LCC may be allowed to handle cases. A local member from the block may be co-opted as a member to aid the LCC in its task. Accepted.

Clause 10: Conciliation

The ICC/ LCC shall provide for conciliation if requested by the complainant.  Otherwise, it shall initiate an inquiry. Distinction should be made between minor and major offences. Conciliation should be allowed only for minor offences. Adds a proviso that monetary settlement shall not be the basis on which conciliation is made.

Clause 11: Inquiry into Complaint

ICC/LCC shall proceed to make inquiry into a complaint in such manner as may be prescribed. No suggestion. Inquiries will be conducted in accordance with service rules or in such manner as may be prescribed.For domestic workers, the LCC shall forward the complaint to the police within seven days if a prima facie case exists.  The case shall be registered under section 509 of Indian Penal Code (word, gesture or act intended to insult the modesty of a woman).
Sources: The Protection of Women Against Sexual Harassment at Work Place Bill, 2010; the Standing Committee on HRD Report on the Bill; the Sexual Harassment at Work Place (Prevention, Prohibition and Redressal) Bill, 2012; PRS.