The 2010 Commonwealth Games may have ended on October 14th, but the controversy surrounding the organising of the games is far from over. In Parliament, the Opposition has called for a Joint-Parliamentary Committee (JPC) to be formed to investigate suspected financial irregularities in the organising of the Games[1]. In a statement in Parliament on Tuesday, Minister for Youth Affairs & Sports M.S. Gill commented that “All irregularities will be examined and the guilty will not be spared”[2]. In July 2010, the Central Vigilance Commission (CVC) found irregularities in 14 Games related construction projects[3]. It has been reported that officials from the CVC now believe total misappropriation of Games Funds could be between Rs 5000 crore and Rs 8000 crore [4]. So what is being done about it? Currently, six different government organisations are conducting independent inquiries into financial irregularities, corruption, and mismanagement of the Games: the High Level (Shunglu) Commission, CVC, CAG, CBI, Income Tax Department, and Enforcement Directorate (ED).  With so many government organisations involved, it can be difficult to decipher the big picture. Here is a breakdown of what each organisation is doing: High Level Commission (Shunglu Commission): The Commission was appointed by the Prime Minister on October 15th[5]. It is chaired by V.K. Shunglu, former Comptroller and Auditor General of India, who has been given the status equivalent to a Supreme Court Judge[6]. The Commission has a broad mandate to investigate all matters regarding the Games, specifically:[7]

  • Roles and responsibilities of signatories to Host City Contract
  • Planning and execution of development projects and contracts
  • Effectiveness of organisational structure and governance for agencies involved
  • Managerial weaknesses
  • All financial aspects of the event, including wrongdoing
  • Coordination issues amongst agencies
  • Role of advisors and consultants to Organising Committee
  • Overall impact of the games
  • Lessons learnt for the future

A report from the Commission detailing its findings is expected by mid January. Central Vigilance Commission (CVC): The CVC first found financial irregularities in 14 Games projects in July 2010.  Subsequently, it asked the CBI to register a corruption case against MCD officials in connection with a tender issued for a Games project[8]. In total, the CVC has found irregularities in 38 games related projects, under the following departments and agencies:[9]

  • Ministry of Youth Affairs & Sports: 6
  • Delhi Development Authority: 6
  • Public Works Department: 6
  • Municipal Corporation of Delhi: 5
  • Central Public Works Department: 4
  • Organising Committee: 3
  • New Delhi Municipal Council: 3
  • Government of Delhi: 2
  • Department of Commerce: 1
  • Indian Meteorological Department: 1
  • RITES: 1

The CVC has directed the above agencies to respond to queries regarding the irregularities and has directed the CBI to begin a Preliminary Inquiry into them [10]. The CVC will report its findings to the Shunglu Commission. Income Tax Department: The I-T Department is investigating tenders and awards of contracts for Games related works, as well as tax evasion [11]. It has conducted raids in offices of over 30 business firms and individuals [12]. Enforcement Directorate (ED): The ED is proceeding against Organising Committee officials for violations of the Foreign Exchange Management Act (FEMA) for projects involving venue development and overlays contracts awarded by the Organising Committee. Central Bureau of Investigation (CBI): It has been reported that the CBI had received over 300 complaints of corruption in Games projects by August 2010[13]. It is verifying these claims and investigating matters highlighted by the CVC. Comptroller and Auditor General (CAG): In August 2009, the CAG published a report entitled Preparedness for the XIX Commonwealth Games highlighting the lack of preparedness for the Games and its escalating cost.  The CAG is conducting a detailed audit of the Games that is expected to be published in March 2011[14]. Given that CAG reports are tabled in Parliament, the March 2011 report will be critical to the Parliamentary debate on the Games. Two members of the Organising Committee, the Joint Director and the Deputy Director General, were arrested by the CBI this past Monday.  However, Given that the report of the Shunglu Commssion is due in January 2011, the CAG audit will follow two months later, and the current Opposition demand for a JPC remains unresolved, it may be some time before significant details are made public.


[1] http://economictimes.indiatimes.com/news/politics/nation/BJP-to-press-for-JPC-probe-into-spectrum-Adarsh-CWG-scams/articleshow/6934697.cms [2] http://www.thehindu.com/news/article890174.ece [3] ttp://economictimes.indiatimes.com/news/news-by-industry/et-cetera/CVC-finds-irregularities-in-several-CWG-projects/articleshow/6229429.cms [4] http://www.deccanherald.com/content/105830/cwg-fraud-may-touch-rs.html [5] http://www.business-standard.com/india/news/games-over-pm-orders-probe-into-pre-event-mess/411739/ [6] http://economictimes.indiatimes.com/news/politics/nation/CWG-probe-Shunglu-given-status-of-SC-judge/articleshow/6818404.cms [7] http://pib.nic.in/newsite/PrintRelease.aspx?relid=66561 [8] http://timesofindia.indiatimes.com/city/delhi/CWG-construction-CVC-asks-CBI-to-register-corruption-case/articleshow/6237714.cms [9] http://www.hindustantimes.com/specials/sports/cwg-2010/22-more-CWG-works-under-CVC-scanner/CWG2010-TopStories/SP-Article10-614446.aspx [10] http://www.indianexpress.com/news/Claiming-fraud---favour-in-Games-rentals--CVC-to-CBI--begin-probe/700998/ [11]http://www.indianexpress.com/news/it-dept-collects-cwg-works-related-documents/698683/ [12] http://www.thehindu.com/news/national/article837892.ece [13] http://www.indianexpress.com/news/cbi-has-over-300-complaints-regarding-games-works/655692/ [14] http://economictimes.indiatimes.com/news/politics/nation/CAG-starts-Commonwealth-Games-audit-report-by-March-2011/articleshow/6252852.cms

The Saansad Adarsh Gram Yojana was launched last week, for the development of model villages.  Under the Yojana, Members of Parliament (MPs) will be responsible for developing the socio-economic and physical infrastructure of three villages each by 2019, and a total of eight villages each by 2024.

The first Adarsh Gram must be developed by 2016, and two more by 2019.  From 2019 to 2024, five more Adarsh Grams must be developed by each MP, one each year.  This implies that a total of 6,433 Adarsh Grams, of the 2,65,000 gram panchayats, will be created by 2024. Key features of the Yojana are outlined below.

Objectives

Key objectives of the Yojana include:

  1. The development of model villages, called Adarsh Grams, through the implementation of existing schemes, and certain new initiatives to be designed for the local context, which may vary from village to village.
  2. Creating models of local development which can be replicated in other villages.

Identification of villages

MPs can select any gram panchayat, other than their own village or that of their spouse, to be developed as an Adarsh Gram.  The village must have a population of 3000-5000 people if it is located in the plains, or 1000-3000 people if located in hilly areas.

Lok Sabha MPs can choose a village from their constituency, and Rajya Sabha MPs from the state from which they are elected.  Nominated members can choose a village from any district of the country.  MPs which represent urban constituencies can identify a village from a neighbouring rural constituency.

Funding

No new funds have been allocated for the Yojana.  Resources may be raised through:

  1. Funds from existing schemes, such as the Indira Awas Yojana, Pradhan Mantri Gram Sadak Yojana, Mahatma Gandhi National Rural Employment Guarantee Scheme, and Backward Regions Grant Fund, etc.,
  2. The Member of Parliament Local Area Development Scheme (MPLADS),
  3. The gram panchayat’s own revenue,
  4. Central and State Finance Commission Grants, and
  5. Corporate Social Responsibility funds.

Implementation

A Village Development Plan must be created for each Adarsh Gram.  While each village will develop a list of activities to be carried out, based on its own resources and requirements, possible activities have been listed in the guidelines for the scheme.  For example, Adarsh Grams can work towards providing universal access to basic healthcare facilities, promoting diversified livelihoods through agriculture related livelihoods and skill development, providing pension for all eligible families, housing for all, and promoting social forestry.

The table below outlines key functionaries at the national, state, district, and village level and their responsibilities.

Table 1: Roles and responsibilities of key functionaries

Level Functionary Key roles and responsibilities
National Member of Parliament
  • Identify the Adarsh Gram
  • Facilitate the planning process
  • Mobilise additional funds
  • Monitor the scheme
  Two committees, headed by the Minister of Rural Development, and Secretary, Rural Development, respectively.*
  • Monitor the process of identification and planning
  • Review the implementation of the scheme
  • Identify bottlenecks in the scheme
  • Issue operational guidelines
  • Indicate specific resource support which each Ministry can provide
State A committee headed by the Chief Secretary
  • Supplement central guidelines for the scheme
  • Review Village Development Plans
  • Review implementation
  • Outline monitoring mechanisms
  • Design a grievance redressal mechanism for the scheme
District District Collector
  • Conduct the baseline survey
  • Facilitate the preparation of the Village Development Plan
  • Converge relevant schemes
  • Ensure grievance redressal
  • Monthly progress review of the scheme
Village Gram Panchayat and functionaries of schemes (at various levels)
  • Implement of the scheme
  • Identify common needs of the village
  • Leverage resources from various programmes
  • Ensure participation in the scheme

Note: *These committees will include members from other Ministries.

Sources: Saansad Adarsh Gram Yojana Guidelines, Ministry of Rural Development; PRS

Monitoring

A web based monitoring system will be established to enable the MP and other stakeholders to monitor the scheme.  Outputs relating to physical and financial targets will be measured each quarter.  A mid-term evaluation and post-project evaluation will be conducted through an independent agency.