The 2010 Commonwealth Games may have ended on October 14th, but the controversy surrounding the organising of the games is far from over. In Parliament, the Opposition has called for a Joint-Parliamentary Committee (JPC) to be formed to investigate suspected financial irregularities in the organising of the Games[1]. In a statement in Parliament on Tuesday, Minister for Youth Affairs & Sports M.S. Gill commented that “All irregularities will be examined and the guilty will not be spared”[2]. In July 2010, the Central Vigilance Commission (CVC) found irregularities in 14 Games related construction projects[3]. It has been reported that officials from the CVC now believe total misappropriation of Games Funds could be between Rs 5000 crore and Rs 8000 crore [4]. So what is being done about it? Currently, six different government organisations are conducting independent inquiries into financial irregularities, corruption, and mismanagement of the Games: the High Level (Shunglu) Commission, CVC, CAG, CBI, Income Tax Department, and Enforcement Directorate (ED).  With so many government organisations involved, it can be difficult to decipher the big picture. Here is a breakdown of what each organisation is doing: High Level Commission (Shunglu Commission): The Commission was appointed by the Prime Minister on October 15th[5]. It is chaired by V.K. Shunglu, former Comptroller and Auditor General of India, who has been given the status equivalent to a Supreme Court Judge[6]. The Commission has a broad mandate to investigate all matters regarding the Games, specifically:[7]

  • Roles and responsibilities of signatories to Host City Contract
  • Planning and execution of development projects and contracts
  • Effectiveness of organisational structure and governance for agencies involved
  • Managerial weaknesses
  • All financial aspects of the event, including wrongdoing
  • Coordination issues amongst agencies
  • Role of advisors and consultants to Organising Committee
  • Overall impact of the games
  • Lessons learnt for the future

A report from the Commission detailing its findings is expected by mid January. Central Vigilance Commission (CVC): The CVC first found financial irregularities in 14 Games projects in July 2010.  Subsequently, it asked the CBI to register a corruption case against MCD officials in connection with a tender issued for a Games project[8]. In total, the CVC has found irregularities in 38 games related projects, under the following departments and agencies:[9]

  • Ministry of Youth Affairs & Sports: 6
  • Delhi Development Authority: 6
  • Public Works Department: 6
  • Municipal Corporation of Delhi: 5
  • Central Public Works Department: 4
  • Organising Committee: 3
  • New Delhi Municipal Council: 3
  • Government of Delhi: 2
  • Department of Commerce: 1
  • Indian Meteorological Department: 1
  • RITES: 1

The CVC has directed the above agencies to respond to queries regarding the irregularities and has directed the CBI to begin a Preliminary Inquiry into them [10]. The CVC will report its findings to the Shunglu Commission. Income Tax Department: The I-T Department is investigating tenders and awards of contracts for Games related works, as well as tax evasion [11]. It has conducted raids in offices of over 30 business firms and individuals [12]. Enforcement Directorate (ED): The ED is proceeding against Organising Committee officials for violations of the Foreign Exchange Management Act (FEMA) for projects involving venue development and overlays contracts awarded by the Organising Committee. Central Bureau of Investigation (CBI): It has been reported that the CBI had received over 300 complaints of corruption in Games projects by August 2010[13]. It is verifying these claims and investigating matters highlighted by the CVC. Comptroller and Auditor General (CAG): In August 2009, the CAG published a report entitled Preparedness for the XIX Commonwealth Games highlighting the lack of preparedness for the Games and its escalating cost.  The CAG is conducting a detailed audit of the Games that is expected to be published in March 2011[14]. Given that CAG reports are tabled in Parliament, the March 2011 report will be critical to the Parliamentary debate on the Games. Two members of the Organising Committee, the Joint Director and the Deputy Director General, were arrested by the CBI this past Monday.  However, Given that the report of the Shunglu Commssion is due in January 2011, the CAG audit will follow two months later, and the current Opposition demand for a JPC remains unresolved, it may be some time before significant details are made public.


[1] http://economictimes.indiatimes.com/news/politics/nation/BJP-to-press-for-JPC-probe-into-spectrum-Adarsh-CWG-scams/articleshow/6934697.cms [2] http://www.thehindu.com/news/article890174.ece [3] ttp://economictimes.indiatimes.com/news/news-by-industry/et-cetera/CVC-finds-irregularities-in-several-CWG-projects/articleshow/6229429.cms [4] http://www.deccanherald.com/content/105830/cwg-fraud-may-touch-rs.html [5] http://www.business-standard.com/india/news/games-over-pm-orders-probe-into-pre-event-mess/411739/ [6] http://economictimes.indiatimes.com/news/politics/nation/CWG-probe-Shunglu-given-status-of-SC-judge/articleshow/6818404.cms [7] http://pib.nic.in/newsite/PrintRelease.aspx?relid=66561 [8] http://timesofindia.indiatimes.com/city/delhi/CWG-construction-CVC-asks-CBI-to-register-corruption-case/articleshow/6237714.cms [9] http://www.hindustantimes.com/specials/sports/cwg-2010/22-more-CWG-works-under-CVC-scanner/CWG2010-TopStories/SP-Article10-614446.aspx [10] http://www.indianexpress.com/news/Claiming-fraud---favour-in-Games-rentals--CVC-to-CBI--begin-probe/700998/ [11]http://www.indianexpress.com/news/it-dept-collects-cwg-works-related-documents/698683/ [12] http://www.thehindu.com/news/national/article837892.ece [13] http://www.indianexpress.com/news/cbi-has-over-300-complaints-regarding-games-works/655692/ [14] http://economictimes.indiatimes.com/news/politics/nation/CAG-starts-Commonwealth-Games-audit-report-by-March-2011/articleshow/6252852.cms

Recently the Chairman of Rajya Sabha issued a direction to extend the sitting hours and change the timing of Question Hour in the Upper House. Beginning with the Winter Session, which starts on November 24, Rajya Sabha will meet from 11 am to 6 pm, an hour more than its typical sitting hours. Question Hour will be scheduled from 12 pm to 1 pm, which was earlier held in the first hour of meeting. Members of Parliament (MPs), in addition to their legislative capacity, play an important role to keep the government accountable. One mechanism for them to hold the government responsible for its policies and actions is Question Hour in Parliament. During Question Hour, MPs raise questions to Ministers on various policy matters and decisions. Currently, all MPs can submit up to ten questions for every day that Parliament is in Session. Of these, 250 Questions are picked up by a random ballot to be answered each day that Parliament meets. While 230 Questions are answered in writing by Ministries, 20 Questions are scheduled to be answered orally by Ministers on the floor of the House. When a Question is answered orally by a Minister, MPs are also able to ask him/her two Supplementary Questions as a follow up to the response given. Therefore the proper functioning of Question Hour allows Parliament to be effective in its accountability function. Over the years Question Hour has become a major casualty to disruptions in Parliament. The last decade has seen a decline in the number of questions answered orally on the floor of the House. Rajya Sabha had tried to address this problem in 2011, when Question Hour was shifted to be held from 2 pm to 3 pm, but this was discontinued within a few days. Percentage of Questions Answered Orally The 2014 Budget Session saw both Houses of Parliament work for over hundred percent of their scheduled sitting time. However, while Question Hour functioned for 87% of its scheduled time in Lok Sabha, it functioned for only 40% of its scheduled time in Rajya Sabha. In 13 of the 27 sittings of the 2014 Budget Session, Question Hour in Rajya Sabha was adjourned within a few minutes due to disruptions. It was as a result of these increasing disruptions in the Upper House that the change in timing of the Question Hour and extension of its hours of sitting were proposed. While the Rules of Procedures of Rajya Sabha designate the first hour of sitting for Question Hour, they also allow the Chairman of the House to direct otherwise. It is using this Rule that the Chairman of Rajya Sabha, Mr. Hamid Ansari, issued directions for the Question Hour to be shifted to noon. It now remains to be seen whether this change in timing of Question Hour in the Upper House will be sufficient to allow for its smoother functioning. Sources: M.N. Kaul and S.L. Shakdher, Practice and Procedure of Parliament, Lok Sabha Secretariat, 6th Edition, 2009 Rajya Sabha Rules of Procedure, Rajya Sabha Secretariat, 2010