The 2010 Commonwealth Games may have ended on October 14th, but the controversy surrounding the organising of the games is far from over. In Parliament, the Opposition has called for a Joint-Parliamentary Committee (JPC) to be formed to investigate suspected financial irregularities in the organising of the Games[1]. In a statement in Parliament on Tuesday, Minister for Youth Affairs & Sports M.S. Gill commented that “All irregularities will be examined and the guilty will not be spared”[2]. In July 2010, the Central Vigilance Commission (CVC) found irregularities in 14 Games related construction projects[3]. It has been reported that officials from the CVC now believe total misappropriation of Games Funds could be between Rs 5000 crore and Rs 8000 crore [4]. So what is being done about it? Currently, six different government organisations are conducting independent inquiries into financial irregularities, corruption, and mismanagement of the Games: the High Level (Shunglu) Commission, CVC, CAG, CBI, Income Tax Department, and Enforcement Directorate (ED).  With so many government organisations involved, it can be difficult to decipher the big picture. Here is a breakdown of what each organisation is doing: High Level Commission (Shunglu Commission): The Commission was appointed by the Prime Minister on October 15th[5]. It is chaired by V.K. Shunglu, former Comptroller and Auditor General of India, who has been given the status equivalent to a Supreme Court Judge[6]. The Commission has a broad mandate to investigate all matters regarding the Games, specifically:[7]

  • Roles and responsibilities of signatories to Host City Contract
  • Planning and execution of development projects and contracts
  • Effectiveness of organisational structure and governance for agencies involved
  • Managerial weaknesses
  • All financial aspects of the event, including wrongdoing
  • Coordination issues amongst agencies
  • Role of advisors and consultants to Organising Committee
  • Overall impact of the games
  • Lessons learnt for the future

A report from the Commission detailing its findings is expected by mid January. Central Vigilance Commission (CVC): The CVC first found financial irregularities in 14 Games projects in July 2010.  Subsequently, it asked the CBI to register a corruption case against MCD officials in connection with a tender issued for a Games project[8]. In total, the CVC has found irregularities in 38 games related projects, under the following departments and agencies:[9]

  • Ministry of Youth Affairs & Sports: 6
  • Delhi Development Authority: 6
  • Public Works Department: 6
  • Municipal Corporation of Delhi: 5
  • Central Public Works Department: 4
  • Organising Committee: 3
  • New Delhi Municipal Council: 3
  • Government of Delhi: 2
  • Department of Commerce: 1
  • Indian Meteorological Department: 1
  • RITES: 1

The CVC has directed the above agencies to respond to queries regarding the irregularities and has directed the CBI to begin a Preliminary Inquiry into them [10]. The CVC will report its findings to the Shunglu Commission. Income Tax Department: The I-T Department is investigating tenders and awards of contracts for Games related works, as well as tax evasion [11]. It has conducted raids in offices of over 30 business firms and individuals [12]. Enforcement Directorate (ED): The ED is proceeding against Organising Committee officials for violations of the Foreign Exchange Management Act (FEMA) for projects involving venue development and overlays contracts awarded by the Organising Committee. Central Bureau of Investigation (CBI): It has been reported that the CBI had received over 300 complaints of corruption in Games projects by August 2010[13]. It is verifying these claims and investigating matters highlighted by the CVC. Comptroller and Auditor General (CAG): In August 2009, the CAG published a report entitled Preparedness for the XIX Commonwealth Games highlighting the lack of preparedness for the Games and its escalating cost.  The CAG is conducting a detailed audit of the Games that is expected to be published in March 2011[14]. Given that CAG reports are tabled in Parliament, the March 2011 report will be critical to the Parliamentary debate on the Games. Two members of the Organising Committee, the Joint Director and the Deputy Director General, were arrested by the CBI this past Monday.  However, Given that the report of the Shunglu Commssion is due in January 2011, the CAG audit will follow two months later, and the current Opposition demand for a JPC remains unresolved, it may be some time before significant details are made public.


[1] http://economictimes.indiatimes.com/news/politics/nation/BJP-to-press-for-JPC-probe-into-spectrum-Adarsh-CWG-scams/articleshow/6934697.cms [2] http://www.thehindu.com/news/article890174.ece [3] ttp://economictimes.indiatimes.com/news/news-by-industry/et-cetera/CVC-finds-irregularities-in-several-CWG-projects/articleshow/6229429.cms [4] http://www.deccanherald.com/content/105830/cwg-fraud-may-touch-rs.html [5] http://www.business-standard.com/india/news/games-over-pm-orders-probe-into-pre-event-mess/411739/ [6] http://economictimes.indiatimes.com/news/politics/nation/CWG-probe-Shunglu-given-status-of-SC-judge/articleshow/6818404.cms [7] http://pib.nic.in/newsite/PrintRelease.aspx?relid=66561 [8] http://timesofindia.indiatimes.com/city/delhi/CWG-construction-CVC-asks-CBI-to-register-corruption-case/articleshow/6237714.cms [9] http://www.hindustantimes.com/specials/sports/cwg-2010/22-more-CWG-works-under-CVC-scanner/CWG2010-TopStories/SP-Article10-614446.aspx [10] http://www.indianexpress.com/news/Claiming-fraud---favour-in-Games-rentals--CVC-to-CBI--begin-probe/700998/ [11]http://www.indianexpress.com/news/it-dept-collects-cwg-works-related-documents/698683/ [12] http://www.thehindu.com/news/national/article837892.ece [13] http://www.indianexpress.com/news/cbi-has-over-300-complaints-regarding-games-works/655692/ [14] http://economictimes.indiatimes.com/news/politics/nation/CAG-starts-Commonwealth-Games-audit-report-by-March-2011/articleshow/6252852.cms

Earlier today, the Union Cabinet announced the merger of the Railways Budget with the Union Budget.  All proposals under the Railways Budget will now be a part of the Union Budget.  However, to ensure detailed scrutiny, the Ministry’s expenditure will be discussed in Parliament.  Further, Railways will continue to maintain its autonomy and financial decision making powers.  In light of this, this post discusses some of the ways in which Railways is financed, and issues it faces with regard to financing. Separation of Railways Budget and its financial implications The Railways Budget was separated from the Union Budget in 1924.  While the Union Budget looks at the overall revenue and expenditure of the central government, the Railways Budget looks at the revenue and expenditure of the Ministry of Railways.  At that time, the proportion of Railways Budget was much higher as compared to the Union Budget.  The separation of the Budgets was done to ensure that the central government receives an assured contribution from the Railways revenues.  However, in the last few years, Railways’ finances have deteriorated and it has been struggling to generate enough surplus to invest in improving its infrastructure. Indian Railways is primarily financed through budgetary support from the central government, its own internal resources (freight and passenger revenue, leasing of railway land, etc.), and external resources (market borrowings, public private partnerships, joint ventures, or market financing). Every year, all ministries, except Railways, get support from the central government based on their estimated revenue and expenditure for the year.  The Railways Ministry is provided with a gross budgetary support from the central government in order to expand its network.  However, unlike other Ministries, Railways pays a return on this investment every year, known as dividend.  The rate of this dividend is currently at around 5%, and also includes the interest on government budgetary support received in the previous years. Various Committees have observed that the system of receiving support from the government and then paying back dividend is counter-productive.  It was recommended that the practice of paying dividend can be avoided until the financial health of Railways improves.  In the announcement made today, the requirement to pay dividend to the central government has been removed.  This would save the Ministry from the liability of paying around Rs 9,700 crore as dividend to the central government every year.  However, Railways will continue to get gross budgetary support from the central government. Declining internal revenue In addition to its core business of providing transportation, Railways also has several social obligations such as: (i) providing certain passenger and coaching services at below cost fares, (ii) running uneconomic branch lines (connectivity to remote areas), and (iii) granting concessions to various categories of people (like senior citizens, children, etc.).  All these add up to about Rs 30,000 crore.  Other inelastic expenses of Railways include pension charges, fuel expenses, lease payments, etc.  Such expenses do not leave any financial room for the Railways to make any infrastructure investments. Railways1 In the last few years, Railways has been struggling due to a decline in its revenue from passenger and freight traffic.  In addition, the support from the central government has broadly remained constant. In 2015-16, the gross budgetary support and internal revenue saw a decline, while there was some increase in the extra budgetary resources (shown in Figure 1).   Railways’ internal revenue primarily comes from freight traffic (about 65%), followed by passenger traffic (about 25%).  About one-third of the passenger revenue comes from first class passenger traffic and the remaining two-third comes from second class passenger traffic.  In 2015-16, Railways passenger traffic decreased by 4% and total passenger revenue decreased by 10% from the budget estimates.  While revenue from second class saw a decrease of 13%, revenue from first class traffic decreased by 3%.  In the last few years, Railways’ internal sources have been declining, primarily due to a decline in both passenger as well as freight traffic. Freight traffic Railways2The share of Railways in total freight traffic has declined from 89% to 30% over the last 60 years, with most of the share moving towards roads (see Figure 2).  With regard to freight traffic, Railways generates most of its revenue from the transportation of coal (about 44%), followed by cement (8%), iron ore (7%), and food-grains (7%).  In 2015-16, freight traffic decreased by 10%, and freight earnings reduced by 5% from the budget estimates. The Railways Budget for 2016-17 estimates an increase of 12% in passenger revenue and a 0.26% increase in passenger traffic.  Achieving a 12% increase in revenue without a corresponding increase in traffic will require an increase in fares. Flexi fares and passenger traffic A few days ago, the Ministry of Railways introduced a flexi-fare system for certain categories of trains.  Under this system, the base fare for Rajdhani, Duronto and Shatabdi trains will increase by 10% with every 10% of berths sold, subject to a ceiling of up to 1.5 times the base fare.  While this could also be a way for Railways to improve its revenue, it has raised concerns about train fares becoming more expensive.  Note that the flexi-fare system will apply only to first class passenger traffic, which contributes to about 8% of the total Railways revenue.  It remains to be seen if the new system increases Railways revenue, or further decreases passenger traffic (people choosing other modes of travel, such as airways, if fares increase significantly). While the Railways is trying to improve revenue by raising fares, this may increase the financial burden on passengers.  In the past, various Parliamentary Committees have observed that the investment planning in Railways from the government’s side is politically driven rather than need driven.  This has resulted in the extension of uneconomic, un-remunerative, yet socially desirable projects in every budget.  It has been recommended that projects based on social and commercial considerations must be categorised separately in the Railways accounts, and funding for the former must come from the central or state governments.  It has also been recommended that Railways should bring in more accuracy in determining its public service obligations. The decision to merge the Railways Budget with the Union Budget seems to be on the lines of several of these recommendations.  However, it remains to be seen whether merging the Railway Budget with the Union Budget will  improve the transporter’s finances or if it would require bringing in more reforms.