The 2010 Commonwealth Games may have ended on October 14th, but the controversy surrounding the organising of the games is far from over. In Parliament, the Opposition has called for a Joint-Parliamentary Committee (JPC) to be formed to investigate suspected financial irregularities in the organising of the Games[1]. In a statement in Parliament on Tuesday, Minister for Youth Affairs & Sports M.S. Gill commented that “All irregularities will be examined and the guilty will not be spared”[2]. In July 2010, the Central Vigilance Commission (CVC) found irregularities in 14 Games related construction projects[3]. It has been reported that officials from the CVC now believe total misappropriation of Games Funds could be between Rs 5000 crore and Rs 8000 crore [4]. So what is being done about it? Currently, six different government organisations are conducting independent inquiries into financial irregularities, corruption, and mismanagement of the Games: the High Level (Shunglu) Commission, CVC, CAG, CBI, Income Tax Department, and Enforcement Directorate (ED).  With so many government organisations involved, it can be difficult to decipher the big picture. Here is a breakdown of what each organisation is doing: High Level Commission (Shunglu Commission): The Commission was appointed by the Prime Minister on October 15th[5]. It is chaired by V.K. Shunglu, former Comptroller and Auditor General of India, who has been given the status equivalent to a Supreme Court Judge[6]. The Commission has a broad mandate to investigate all matters regarding the Games, specifically:[7]

  • Roles and responsibilities of signatories to Host City Contract
  • Planning and execution of development projects and contracts
  • Effectiveness of organisational structure and governance for agencies involved
  • Managerial weaknesses
  • All financial aspects of the event, including wrongdoing
  • Coordination issues amongst agencies
  • Role of advisors and consultants to Organising Committee
  • Overall impact of the games
  • Lessons learnt for the future

A report from the Commission detailing its findings is expected by mid January. Central Vigilance Commission (CVC): The CVC first found financial irregularities in 14 Games projects in July 2010.  Subsequently, it asked the CBI to register a corruption case against MCD officials in connection with a tender issued for a Games project[8]. In total, the CVC has found irregularities in 38 games related projects, under the following departments and agencies:[9]

  • Ministry of Youth Affairs & Sports: 6
  • Delhi Development Authority: 6
  • Public Works Department: 6
  • Municipal Corporation of Delhi: 5
  • Central Public Works Department: 4
  • Organising Committee: 3
  • New Delhi Municipal Council: 3
  • Government of Delhi: 2
  • Department of Commerce: 1
  • Indian Meteorological Department: 1
  • RITES: 1

The CVC has directed the above agencies to respond to queries regarding the irregularities and has directed the CBI to begin a Preliminary Inquiry into them [10]. The CVC will report its findings to the Shunglu Commission. Income Tax Department: The I-T Department is investigating tenders and awards of contracts for Games related works, as well as tax evasion [11]. It has conducted raids in offices of over 30 business firms and individuals [12]. Enforcement Directorate (ED): The ED is proceeding against Organising Committee officials for violations of the Foreign Exchange Management Act (FEMA) for projects involving venue development and overlays contracts awarded by the Organising Committee. Central Bureau of Investigation (CBI): It has been reported that the CBI had received over 300 complaints of corruption in Games projects by August 2010[13]. It is verifying these claims and investigating matters highlighted by the CVC. Comptroller and Auditor General (CAG): In August 2009, the CAG published a report entitled Preparedness for the XIX Commonwealth Games highlighting the lack of preparedness for the Games and its escalating cost.  The CAG is conducting a detailed audit of the Games that is expected to be published in March 2011[14]. Given that CAG reports are tabled in Parliament, the March 2011 report will be critical to the Parliamentary debate on the Games. Two members of the Organising Committee, the Joint Director and the Deputy Director General, were arrested by the CBI this past Monday.  However, Given that the report of the Shunglu Commssion is due in January 2011, the CAG audit will follow two months later, and the current Opposition demand for a JPC remains unresolved, it may be some time before significant details are made public.


[1] http://economictimes.indiatimes.com/news/politics/nation/BJP-to-press-for-JPC-probe-into-spectrum-Adarsh-CWG-scams/articleshow/6934697.cms [2] http://www.thehindu.com/news/article890174.ece [3] ttp://economictimes.indiatimes.com/news/news-by-industry/et-cetera/CVC-finds-irregularities-in-several-CWG-projects/articleshow/6229429.cms [4] http://www.deccanherald.com/content/105830/cwg-fraud-may-touch-rs.html [5] http://www.business-standard.com/india/news/games-over-pm-orders-probe-into-pre-event-mess/411739/ [6] http://economictimes.indiatimes.com/news/politics/nation/CWG-probe-Shunglu-given-status-of-SC-judge/articleshow/6818404.cms [7] http://pib.nic.in/newsite/PrintRelease.aspx?relid=66561 [8] http://timesofindia.indiatimes.com/city/delhi/CWG-construction-CVC-asks-CBI-to-register-corruption-case/articleshow/6237714.cms [9] http://www.hindustantimes.com/specials/sports/cwg-2010/22-more-CWG-works-under-CVC-scanner/CWG2010-TopStories/SP-Article10-614446.aspx [10] http://www.indianexpress.com/news/Claiming-fraud---favour-in-Games-rentals--CVC-to-CBI--begin-probe/700998/ [11]http://www.indianexpress.com/news/it-dept-collects-cwg-works-related-documents/698683/ [12] http://www.thehindu.com/news/national/article837892.ece [13] http://www.indianexpress.com/news/cbi-has-over-300-complaints-regarding-games-works/655692/ [14] http://economictimes.indiatimes.com/news/politics/nation/CAG-starts-Commonwealth-Games-audit-report-by-March-2011/articleshow/6252852.cms

In Budget Session 2018, Rajya Sabha has planned to examine the working of four ministries.  The Ministry of Drinking Water and Sanitation is one of the ministries listed for discussion.  In this post, we look at the key schemes being implemented by the Ministry and their status.

What are the key functions of the Ministry of Drinking Water and Sanitation?

As per the Constitution, supply of water and sanitation are state subjects which means that states regulate and provide these services.  The Ministry of Drinking Water and Sanitation is primarily responsible for policy planning, funding, and coordination of programs for: (i) safe drinking water; and (ii) sanitation, in rural areas.  From 1999 till 2011, the Ministry operated as a Department under the Ministry of Rural Development.  In 2011, the Department was made an independent Ministry.  Presently, the Ministry oversees the implementation of two key schemes of the government: (i) Swachh Bharat Mission-Gramin (SBM-G), and (ii) National Rural Drinking Water Programme (NRDWP).

How have the finances and spending priorities of the Ministry changed over time?

In the Union Budget 2018-19, the Ministry has been allocated Rs 22,357 crore.  This is a decrease of Rs 1,654 crore (7%) over the revised expenditure of 2017-18.  In 2015-16, the Ministry over-shot its budget by 178%.  Consequently, the allocation in 2016-17 was more than doubled (124%) to Rs 14,009 crore.

In recent years, the priorities of the Ministry have seen a shift (see Figure 1).  The focus has been on providing sanitation facilities in rural areas, mobilising behavioural change to increase usage of toilets, and consequently eliminating open defecation.  However, this has translated into a decrease in the share of allocation towards drinking water (from 87% in 2009-10 to 31% in 2018-19).  In the same period, the share of allocation to rural sanitation has increased from 13% to 69%.Figure 1

What has been the progress under Swacch Bharat Mission- Gramin?

The Swachh Bharat Mission was launched on October 2, 2014 with an aim to achieve universal sanitation coverage, improve cleanliness, and eliminate open defecation in the country by October 2, 2019.

Expenditure on SBM-G:  In 2018-19, Rs 15,343 crore has been allocated towards SBM-G.  The central government allocation to SBM-G for the five year period from 2014-15 to 2018-19 has been estimated to be Rs 1,00,447 crore.  Of this, up to 2018-19, Rs 52,166 crore (52%) has been allocated to the scheme.  This implies that 48% of the funds are still left to be released before October 2019.  Figure 2

Construction of Individual Household Latrines (IHHLs):  For construction of IHHLs, funds are shared between the centre and states in the 60:40 ratio.  Construction of IHHLs account for the largest share of total expenditure under the scheme (97%-98%).  Although the number of toilets constructed each year has increased, the pace of annual growth of constructing these toilets has come down.  In 2015-16, the number of toilets constructed was 156% higher than the previous year.  This could be due to the fact that 2015-16 was the first full year of implementation of the scheme.  The growth in construction of new toilets reduced to 74% in 2016-17, and further to 4% in 2017-18.Table 1

As of February 2018, 78.8% of households in India had a toilet.  This implies that 15 crore toilets have been constructed so far.  However, four crore more toilets need to be construced in the next 20 months for the scheme to achieve its target by 2019.

Open Defecation Free (ODF) villages:  Under SBM-G, a village is ODF when: (i) there are no visible faeces in the village, and (ii) every household as well as public/community institution uses safe technology options for faecal disposal.  After a village declares itself ODF, states are required to carry out verification of the ODF status of such a village.  This includes access to a toilet facility and its usage, and safe disposal of faecal matter through septic tanks.  So far, out of all villages in the country, 72% have been verified as ODF.  This implies that 28% villages are left to be verified as ODF for the scheme to achieve its target by 2019.Table 2

Information, Education and Communication (IEC) activities:  As per the SBM-G guidelines, 8% of funds earmarked for SBM-G in a year should be utilised for IEC activities.  These activities primarily aim to mobilise behavioural change towards the use of toilets among people.  However, allocation towards this component has remained in the 1%-4% range.  In 2017-18, Rs 229 crore is expected to be spent, amounting to 2% of total expenditure.

What is the implementation status of the National Rural Drinking Water Programme?

The National Rural Drinking Water Programme (NRDWP) aims at assisting states in providing adequate and safe drinking water to the rural population in the country.  In 2018-19, the scheme has been allocated Rs 7,000 crore, accounting for 31% of the Ministry’s finances.Figure 3

Coverage under the scheme:  As of August 2017, 96% of rural habitations have access to safe drinking water.  In 2011, the Ministry came out with a strategic plan for the period 2011-22.  The plan identified certain standards for coverage of habitations with water supply, including targets for per day supply of drinking water.  As of February 2018, 74% habitations are fully covered (receiving 55 litres per capita per day), and 22% habitations are partially covered (receiving less than 55 litres per capita per day).  The Ministry aims to cover 90% rural households with piped water supply and 80% rural households with tap connections by 2022.  The Estimates Committee of Parliament (2015) observed that piped water supply was available to only 47% of rural habitations, out of which only 15% had household tap connections.

Contamination of drinking water:  It has been noted that NRDWP is over-dependant on ground water.  However, ground water is contaminated in over 20 states.  For instance, high arsenic contamination has been found in 68 districts of 10 states.  These states are Haryana, Punjab, Uttar Pradesh, Bihar, Jharkhand, Chhattisgarh, West Bengal, Assam, Manipur, and Karnataka.Table 3

Chemical contamination of ground water has also been reported due to deeper drilling for drinking water sources.  It has been recommended that out of the total funds for NRDWP, allocation for water quality monitoring and surveillance should not be less than 5%.  Presently, it is 3% of the total funds.  It has also been suggested that water quality laboratories for water testing should be set up throughout the country.