Earlier this week, Lok Sabha passed the Bill that provides for the allocation of coal mines that were cancelled by the Supreme Court last year. In light of this development, this post looks at the issues surrounding coal block allocations and what the 2015 Bill seeks to achieve.
In September 2014, the Supreme Court cancelled the allocations of 204 coal blocks. Following the Supreme Court judgement, in October 2014, the government promulgated the Coal Mines (Special Provisions) Ordinance, 2014 for the allocation of the cancelled coal mines. The Ordinance, which was replaced by the Coal Mines (Special Provisions) Bill, 2014, could not be passed by Parliament in the last winter session, and lapsed. The government then promulgated the Coal Mines (Special Provisions) Second Ordinance, 2014 on December 26, 2014. The Coal Mines (Special Provisions) Bill, 2015 replaces the second Ordinance and was passed by Lok Sabha on March 4, 2015. Why is coal considered relevant? Coal mining in India has primarily been driven by the need for energy domestically. About 55% of the current commercial energy use is met by coal. The power sector is the major consumer of coal, using about 80% of domestically produced coal. As of April 1, 2014, India is estimated to have a cumulative total of 301.56 billion tonnes of coal reserves up to a depth of 1200 meters. Coal deposits are mainly located in Jharkhand, Odisha, Chhattisgarh, West Bengal, Madhya Pradesh, Andhra Pradesh and Maharashtra. How is coal regulated? The Ministry of Coal has the overall responsibility of managing coal reserves in the country. Coal India Limited, established in 1975, is a public sector undertaking, which looks at the production and marketing of coal in India. Currently, the sector is regulated by the ministry’s Coal Controller’s Organization. The Coal Mines (Nationalisation) Act, 1973 (CMN Act) is the primary legislation determining the eligibility for coal mining in India. The CMN Act allows private Indian companies to mine coal only for captive use. Captive mining is the coal mined for a specific end-use by the mine owner, but not for open sale in the market. End-uses currently allowed under the CMN Act include iron and steel production, generation of power, cement production and coal washing. The central government may notify additional end-uses. How were coal blocks allocated so far? Till 1993, there were no specific criteria for the allocation of captive coal blocks. Captive mining for coal was allowed in 1993 by amendments to the CMN Act. In 1993, a Screening Committee was set up by the Ministry of Coal to provide recommendations on allocations for captive coal mines. All allocations to private companies were made through the Screening Committee. For government companies, allocations for captive mining were made directly by the ministry. Certain coal blocks were allocated by the Ministry of Power for Ultra Mega Power Projects (UMPP) through tariff based competitive bidding (bidding for coal based on the tariff at which power is sold). Between 1993 and 2011, 218 coal blocks were allocated to both public and private companies under the CMN Act. What did the 2014 Supreme Court judgement do? In August 2012, the Comptroller and Auditor General of India released a report on the coal block allocations. CAG recommended that the allocation process should be made more transparent and objective, and done through competitive bidding. Following this report, in September 2012, a Public Interest Litigation matter was filed in the Supreme Court against the coal block allocations. The petition sought to cancel the allotment of the coal blocks in public interest on grounds that it was arbitrary, illegal and unconstitutional. In September 2014, the Supreme Court declared all allocations of coal blocks, made through the Screening Committee and through Government Dispensation route since 1993, as illegal. It cancelled the allocation of 204 out of 218 coal blocks. The allocations were deemed illegal on the grounds that: (i) the allocation procedure followed by the Screening Committee was arbitrary, and (ii) no objective criterion was used to determine the selection of companies. Further, the allocation procedure was held to be impermissible under the CMN Act. Among the 218 coal blocks, 40 were under production and six were ready to start production. Of the 40 blocks under production, 37 were cancelled and of the six ready to produce blocks, five were cancelled. However, the allocation to Ultra Mega Power Projects, which was done via competitive bidding for lowest tariffs, was not declared illegal. What does the 2015 Bill seek to do? Following the cancellation of the coal blocks, concerns were raised about further shortage in the supply of coal, resulting in more power supply disruptions. The 2015 Bill primarily seeks to allocate the coal mines that were declared illegal by the Supreme Court. It provides details for the auction process, compensation for the prior allottees, the process for transfer of mines and details of authorities that would conduct the auction. In December 2014, the ministry notified the Coal Mines (Special Provisions) Rules, 2014. The Rules provide further guidelines in relation to the eligibility and compensation for prior allottees. How is the allocation of coal blocks to be carried out through the 2015 Bill? The Bill creates three categories of mines, Schedule I, II and III. Schedule I consists of all the 204 mines that were cancelled by the Supreme Court. Of these mines, Schedule II consists of all the 42 mines that are under production and Schedule III consists of 32 mines that have a specified end-use such as power, iron and steel, cement and coal washing. Schedule I mines can be allocated by way of either public auction or allocation. For the public auction route any government, private or joint venture company can bid for the coal blocks. They can use the coal mined from these blocks for their own consumption, sale or for any other purpose as specified in their mining lease. The government may also choose to allot Schedule I mines to any government company or any company that was awarded a power plant project through competitive bidding. In such a case, a government company can use the coal mined for own consumption or sale. However, the Bill does not provide clarity on the purpose for which private companies can use the coal. Schedule II and III mines are to be allocated by way of public auction, and the auctions have to be completed by March 31, 2015. Any government company, private company or a joint venture with a specified end-use is eligible to bid for these mines. In addition, the Bill also provides details on authorities that would conduct the auction and allotment and the compensation for prior allottees. Prior allottees are not eligible to participate in the auction process if: (i) they have not paid the additional levy imposed by the Supreme Court; or (ii) if they are convicted of an offence related to coal block allocation and sentenced to imprisonment of more than three years. What are some of the issues to consider in the 2015 Bill? One of the major policy shifts the 2015 Bill seeks to achieve is to enable private companies to mine coal in the future, in order to improve the supply of coal in the market. Currently, the coal sector is regulated by the Coal Controller’s Organization, which is under the Ministry of Coal. The Bill does not establish an independent regulator to ensure a level playing field for both private and government companies bidding for auction of mines to conduct coal mining operations. In the past, when other sectors have opened up to the private sector, an independent regulatory body has been established beforehand. For example, the Telecom Regulatory Authority of India, an independent regulatory body, was established when the telecom sector was opened up for private service providers. The Bill also does not specify any guidelines on the monitoring of mining activities by the new allottees. While the Bill provides broad details of the process of auction and allotment, the actual results with regards to money coming in to the states, will depend more on specific details, such as the tender documents and floor price. It is also to be seen whether the new allotment process ensures equitable distribution of coal blocks among the companies and creates a fair, level-playing field for them. In the past, the functioning of coal mines has been delayed due to delays in land acquisition and environmental clearances. This Bill does not address these issues. The auctioning of coal blocks resulting in improving the supply of coal, and in turn addressing the problem of power shortage in the country, will also depend on the efficient functioning of the mines, in addition to factors such as transparent allocations.
The Supreme Court passed its judgment in General Officer Commanding (Army) vs. CBI on May 01, 2012. The case addressed the issue of need for sanction to prosecute Army officers under the Armed Forces Special Powers Act (AFSPA). The case dealt with two instances of alleged fake encounters. Five people were killed by the Army in Assam in a counter insurgency operation in 1994. Another five people were killed in Jammu and Kashmir in March, 2000 in an encounter. In both cases, it was alleged that the Army officers had staged fake encounters. In both instances, the CBI was directed to investigate the matter. CBI claimed that the people who were killed were indeed victims of fake encounters. The CBI moved the court to initiate prosecution against the accused Army officers. The officers claimed that they could only be prosecuted with the prior sanction (permission) of the central government. The officers relied on provisions of the AFSPA,1958 and the Armed Forces J & K (Special Powers) Act, 1990 to support their claim. (See Notes for the relevant clauses) These provide that legal proceedings cannot be instituted against an officer unless sanction is granted by the central government. It must be noted that Army officers can be tried either before criminal courts or through court-martial (as prescribed under Sections 125 of the Army Act, 1950). The Army officers had appealed that both procedures require prior sanction of the government. The judgment touches upon various issues. Some of these have been discussed in more detail below:
Is prior sanction required to prosecute army officers for 'any' act committed in the line of duty? The judgment reiterated an earlier ruling. It held that sanction would not be required in 'all' cases to prosecute an official. The officer only enjoys immunity from prosecution in cases when he has ‘acted in exercise of powers conferred under the Act’. There should be 'reasonable nexus' between the action and the duties of the official. The Court cited the following example to highlight this point: If in a raid, an officer is attacked and he retaliates, his actions can be linked to a 'lawful discharge of duty'. Even if there were some miscalculations in the retaliation, his actions cannot be labeled to have some personal motive. The Court held that the AFSPA, or the Armed Forces (J&K) Special Powers Act, empowers the central government to ascertain if an action is 'reasonably connected with the discharge of official duty' and is not a misuse of authority. The courts have no jurisdiction in the matter. In making a decision, the government must make an objective assessment of the exigencies leading to the officer’s actions. At what stage is sanction required? The Court ruled that under the AFSPA, or the Armed Forces (J&K) Special Powers Act, sanction is mandatory. But, the need to seek sanction would only arise at the time of cognizance of the offence. Cognizance is the stage when the prosecution begins. Sanction is therefore not required during investigation. Is sanction required for court-martial? The Court ruled that there is no requirement of sanction under the Army Act, 1950. Hence, if the Army chooses, it can prosecute the accused through court-martial instead of going through the criminal court. The Court noted that the case had been delayed for over a decade and prescribed a time bound course of action. It asked the Army to decide on either of the two options - court martial or criminal court - within the next eight weeks. If the Army decides on proceedings before the criminal court, the government will have three months to determine to grant or withhold sanction. Notes Section 6 of the AFSPA, 1958: "6. Protection to persons acting under Act – No prosecution, suit or other legal proceeding shall be instituted, except with the previous sanction of the Central Government, against any person in respect of anything done or purported to be done in exercise of the powers conferred by this Act." Section 7 of the Armed Forces (J&K) Special Powers Act, 1990: "7. Protection of persons acting in good faith under this Act. No prosecution, suit or other legal proceeding shall be instituted, except with the previous sanction of the Central Government, against any person in respect of anything done or purported to be done in exercise of the powers conferred by this Act."